Information from the People's Committee of Hoa Binh province said that the Hoa Binh - Moc Chau expressway project (section from Km19+000 - Km53+000 in Hoa Binh province) has a construction scale of 34km long. Total investment is 9,997 billion VND.
This is a project identified by Hoa Binh and Son La provinces as a key project that needs to be accelerated this year.
In Hoa Binh province, there is a total length of 34 km, including 21 km through Da Bac district with 88 households in communes: Cao Son, Tien Phong, Tu Ly and Da Bac town having their houses and land affected. live.
According to the proposed site clearance documents of the Hoa Binh - Moc Chau expressway project, Da Bac district must recover a total area of over 173.8 hectares of land.
In the middle of August, reporters' records in Da Bac district show that the work of counting, compensation, and site clearance is being actively implemented by relevant units, trying to hand over clean land to project.
Talking to reporters, Mr. Nguyen Thanh Tuan - Vice Chairman of Da Bac District People's Committee said - the district has established a compensation and resettlement working group for the Hoa Binh - Moc Chau expressway project headed by the Vice Chairman of the District People's Committee. The team leader, along with members of the district's departments, branches, and unions, invited the project investor to participate to coordinate in the process of carrying out compensation and site clearance tasks.
Every week, leaders of the district Party Committee and People's Committee will hold meetings with the working group to evaluate progress and promptly direct the removal of difficulties and problems that arise.
According to Mr. Tuan, up to now more than 8km has been counted, the section from km24+300 - km32+500 (corresponding to a total of 568 plots, 63ha that need to be recovered).
At the same time, the District People's Committee has directed relevant agencies and units to urgently develop land price plans, approve specific land prices and prepare a draft compensation plan for public listing. After receiving comments and after the listing process, the first plan will be approved for the area announced to be withdrawn.
For forest and rice land areas, the District People's Committee closely coordinates with departments and branches to complete the procedures and documents for forest and rice land conversion.
Regarding the expected start of construction, Vice Chairman of the People's Committee of Da Bac district informed that the locality had reported to the provincial leaders and agreed with the investor on the expected starting location in Seo hamlet, Cao Son commune. Currently, the investor is applying for policies and implementing procedures to organize the groundbreaking ceremony.
Previously, the People's Committee of Hoa Binh province issued a document requesting the Management Board of investment projects for construction of traffic works in Hoa Binh province (investor) to coordinate with relevant units to speed up procedures according to regulations. legal regulations to ensure the start of construction of the Hoa Binh - Moc Chau Expressway Project (section from Km19+000 - Km53+000 in Hoa Binh province) before September 2, 2024.