Sa Pa Airport continues to bid after 2 times of not finding an investor

Đinh Đại |

Lao Cai - After 3 years of groundbreaking, Sa Pa airport has not yet found an investor and is preparing to invite bids for the third time.

In mid-May 2025, according to the reporter of Lao Dong Newspaper in Cam Con Commune (Bao Yen District), dozens of households have moved to the resettlement area, giving up land to serve the Sa Pa Airport construction project worth 7,000 billion VND.

Next to the Noi Bai - Lao Cai Expressway, you can see dozens of spacious and beautiful houses that have sprung up. The appearance of the resettlement area is changing dramatically.

Nhung ngoi nha, diem truong hoc bo hoang sau khi giai phong mat bang phuc vu du an Cang hang khong Sa Pa. Anh: Dinh Dai
Abandoned houses and schools after site clearance for the Sa Pa Airport project. Photo: Dinh Dai

However, 3 years have passed since the groundbreaking, this 7,000 billion VND airport project has only stopped at site clearance and struggled to find investors.

Mr. Nguyen Van Hoan (Cam Con commune, Bao Yen district) was fed up: "We, the people, have heard and known about this Sa Pa airport project for many years. But that was also the time, after the households agreed to hand over the houses and land to serve the construction, but until now, nothing has been seen."

According to Mr. Hoan, the smooth site clearance has shown the support of the people in the commune. Therefore, people hope that the project's progress and the process of finding investors need to be accelerated to create stability for economic development.

Khu tai dinh cu to dep moc len canh cao toc Noi Bai - Lao Cai. Anh: Dinh Dai
A large and beautiful resettlement area has sprung up next to the Noi Bai - Lao Cai Expressway. Photo: Dinh Dai

Through research, in 2021, the Prime Minister decided to invest in the Sa Pa airport construction project under the PPP (public-private partnership) form.

The project is divided into 2 investment phases, in which phase 1 - construction of Sa Pa airport to meet the standards of a level 4C airport and a level II military airport, reaching a capacity of 1.5 million passengers/year; phase 2 will complete the project items to reach a capacity of 3 million passengers/year.

The project implementation period is 50 years, of which the construction period is 4 years; the operation, exploitation and capital recovery period is 46 years. Phase 1 of the project will be implemented from 2021; phase 2 will be implemented after 2028.

Sa Pa airport has a land use area of 371 hectares with a total investment of nearly 7,000 billion VND. Of which, the State capital accounts for about VND 2,700 billion, the rest is capital mobilized by investors.

Cong tac giai phong mat bang hien da xong, chi cho co doanh nghiep vao dau tu. Anh: Dinh Dai
The site clearance work is now completed, just waiting for businesses to invest. Photo: Dinh Dai

However, despite 2 bidding invitations, the project has not been able to be implemented yet because it has not found a partner. The reason was pointed out that the enterprise saw that the investment was large and it was difficult to make a profit, so it did not do it.

Talking to PV Lao Dong Newspaper, the leader of the Management Board of the Investment Project Construction of Lao Cai Transport Projects said: "The site clearance of the second phase of the Sa Pa Airport Project has been completed. Lao Cai province is coordinating with the stakeholders to conduct adjustments to attract investors.

Đinh Đại
TIN LIÊN QUAN

Landslide collapses house in Sa Pa, 1 person died

|

Lao Cai - The landslide in Sa Pa town killed 1 person.

Sa Pa town wishes to keep its name after the merger

|

Lao Cai - Sa Pa town is developing plans to merge at the commune level to reduce units according to the direction of the Central Government.

I always remember when I sang about Uncle Ho at the Presidential Palace, everyone cried

|

In the program Saturday Afternoon Coffee, People's Artist Thanh Hoa shared memories of singing about Uncle Ho that made many people cry.

The National Assembly considers a mechanism to remove difficulties for 11 transport BOT projects

|

The Law on Investment under the Public-private partnership method - PPP Law (amended) stipulates the mechanism for handling problems of revenue reduction for transport BOT projects.

The exhibition of 100 years of revolutionary journalism opens Quang Ninh Press Festival

|

Quang Ninh - On May 17, the exhibition of 100 years of Vietnamese revolutionary press and achievements of the province opened, officially opening the Quang Ninh Press Festival.

fierce competition, candidates worry about difficulties in passing the Pedagogical School

|

With the number of candidates registering for the exam increasing, many students expressed concern about the difficulty of passing the top pedagogical schools.

Sa Pa Airport continues to bid after 2 times of not finding an investor

|

Lao Cai - After 3 years of groundbreaking, Sa Pa airport has not yet found an investor and is preparing to invite bids for the third time.

Landslide collapses house in Sa Pa, 1 person died

Đinh Đại |

Lao Cai - The landslide in Sa Pa town killed 1 person.

Sa Pa town wishes to keep its name after the merger

Bảo Nguyên |

Lao Cai - Sa Pa town is developing plans to merge at the commune level to reduce units according to the direction of the Central Government.

Tây Bắc cuối ngày: Lý do sân bay Sa Pa chưa thể khởi công

Nhóm PV |

Sân bay Sa Pa chưa thể khởi công; Đường nông thôn mới dùng đã hỏng; Phú Thọ tìm nhà thầu dự án 75 tỉ đồng là một số tin tức nổi bật.