Ready to assemble the highest vertical clearance cable-stayed bridge in Vietnam in June

BẢO TÚ |

Ho Chi Minh City - Phuoc Khanh bridge is entering the final sprint phase to close in June, removing the final bottleneck on the Ben Luc - Long Thanh expressway.

Phuoc Khanh bridge (belonging to package J3-1) across the Long Tau River, connecting Binh Khanh commune (HCMC) and Dai Phuoc commune (Dong Nai) is a complex technical item and decisive for the progress of the entire Ben Luc - Long Thanh expressway. The project has a length of 3, 186 m, a scale of 4 lanes with a navigation clearance of 55 m, the highest in Vietnam today. After nearly 5 years of stagnation due to capital problems and loan agreement extension, this package has restarted with a new contractor, currently bringing the total project volume to about 95%.

Toàn cảnh công trường cầu Phước Khánh bắc qua sông Lòng Tàu (nối TPHCM và Đồng Nai) đang trong giai đoạn thi công nước rút. Ảnh: Anh Tú
Overview of the Phuoc Khanh bridge construction site across the Long Tau River (connecting Ho Chi Minh City and Dong Nai) which is in the final sprint phase. Photo: Anh Tu

Recorded at the construction site, the construction pace is being pushed to the highest level. To compensate for the progress, the contractor organizes continuous work in 3 shifts, 4 crews. During the day, each bridge pier maintains about 80 - 85 engineers and workers; at night, there are 40 - 50 people clinging to the pier and supervisory forces on duty 24/24.

Cầu Phước Khánh được xem là “nút thắt” cuối cùng, mang tính quyết định đến tiến độ thông xe của toàn tuyến cao tốc Bến Lức - Long Thành.
Phuoc Khanh bridge is considered the last "bottleneck", which is decisive for the traffic opening progress of the entire Ben Luc - Long Thanh expressway. Photo" Anh Tu

Mr. Vu Hoang, a worker directly constructing at the project, said that all human resources are closely following the motto "eat quickly, sleep urgently" to ensure progress.

Sharing the same opinion, Phuoc Khanh bridge supervision consultant, Mr. Le Van Khanh shared that, despite harsh weather conditions or erratic rain and sunshine, the construction site still maintains continuous operation thanks to units proactively coordinating and applying flexible and most suitable construction plans.

Hàng chục kỹ sư, công nhân bám trụ trên độ cao hàng chục mét, miệt mài thi công dưới thời tiết nắng nóng.
Dozens of engineers and workers stick to a height of tens of meters, diligently constructing in hot weather. Photo: Thai Bao
 Nhịp chính của cầu có tổng cộng 48 dây văng, hiện các đơn vị thi công đã hoàn thành căng kéo phần lớn khối lượng kết cấu dây. Ảnh: Thái Bảo
The main span of the bridge has a total of 48 cables, currently the construction units have completed stretching most of the cable structure volume. Photo: Thai Bao
Theo kế hoạch, cầu Phước Khánh sẽ chính thức hợp long nhịp chính vào giữa tháng 6.2026.
According to the plan, Phuoc Khanh bridge will officially close the main span in mid-June 2026. Photo: Anh Tu
Phần đường dẫn hai đầu cầu đã hoàn thành. Ảnh: Thái Bảo
The approach roads at both ends of the bridge have been completed. Photo: Thai Bao

Technically, Phuoc Khanh bridge has a total of 48 cables, divided equally for two spans, 24 cables on each side and has now completed stretching 12/14 cables in each stage. At pier 15 alone, only 2 cables are completed for the structure part. The cantilever casting item is being maintained stably with an 8-day per span cycle as committed.

With the current pace, it is expected that from June 15 to 20, 2026, the main bridge will be officially joined, marking a milestone in moving to the completion phase.

Dự kiến toàn bộ công trình hoàn thành tháng 9.2026, gỡ nút thắt cuối cung cho
The entire project is expected to be completed in September 2026, removing the final bottleneck for the Ben Luc - Long Thanh expressway. Photo: Thai Bao.

According to the plan, immediately after the joining, items such as railing, asphalt concrete pavement and lighting system will be urgently deployed in July. It is expected that by September 2026, the entire bridge deck will be completed.

When the project is put into operation, vehicles traveling from the Mekong Delta provinces to Long Thanh airport will be connected smoothly, no longer having to go through the center of Ho Chi Minh City, thereby contributing to drastically reducing inner-city traffic pressure.

BẢO TÚ
RELATED NEWS

Construction site of a cable-stayed bridge project worth over 600 billion VND in Thai Nguyen

|

Thai Nguyen - Dozens of workers and machinery are being mobilized to implement the Gia Bay bridge construction project.

Day and night construction at the construction site of the widest cable-stayed bridge project in Hai Phong

|

Hai Phong - To date, the construction of the nearly 1,500m long cable-stayed main bridge under the Nguyen Trai bridge project has reached about 32% of the progress, striving to reach the finish line in September 2027.

Saigon Hot News: Vietnam's highest vertical cable-stayed bridge accelerates to wait for assembly

|

Saigon Hot News on April 5th: Vietnam's highest vertical cable-stayed bridge accelerates to wait for assembly; Candidates with many emotions in the competency assessment exam...

Solutions to protect personal data, respond to online fraud risks

|

Technology businesses in Vietnam are developing information security solutions, protecting personal data, and responding to online fraud risks.

Man City is only 2 points behind Arsenal

|

On the night of May 9 (Vietnam time), Man City defeated Brentford 3-0, thereby narrowing the gap with Arsenal in the Premier League.

Older Brother Overcoming Thousands of Obstacles" is the owner of a million-view channel, director of a movie worth over 200 billion VND

|

Huynh Lap surprised when participating in the show "Anh Trai Vuot Ngan Chong Gai" season 2.

Close-up of the T-54B tank at the My Dinh F1 racetrack during the Sao Enlisted concert

|

Not only is it a music concert, Sao Ngu Ngu Concert 2026 also attracts attention with the performance of the T-54B tank.

Hanoi Party Secretary experiences identification application when traveling on the metro

|

Hanoi - Secretary of the City Party Committee Tran Duc Thang directly experienced the electronic ticket control system applying electronic identification and authentication when traveling on the metro.

Construction site of a cable-stayed bridge project worth over 600 billion VND in Thai Nguyen

Việt Bắc |

Thai Nguyen - Dozens of workers and machinery are being mobilized to implement the Gia Bay bridge construction project.

Day and night construction at the construction site of the widest cable-stayed bridge project in Hai Phong

Mai Dung |

Hai Phong - To date, the construction of the nearly 1,500m long cable-stayed main bridge under the Nguyen Trai bridge project has reached about 32% of the progress, striving to reach the finish line in September 2027.

Saigon Hot News: Vietnam's highest vertical cable-stayed bridge accelerates to wait for assembly

Thanh Chân - Chân Phúc |

Saigon Hot News on April 5th: Vietnam's highest vertical cable-stayed bridge accelerates to wait for assembly; Candidates with many emotions in the competency assessment exam...