Thanh Hoa completes 100% of the foundation for the 500kV transmission line circuit 3

Xuân Hùng |

As of July 30, the 500kV circuit 3 transmission line project through Thanh Hóa has completed 200/200 tower foundations.

On July 30, Mr. Do Trong Hung - Member of the Central Party Committee, Secretary of the Thanh Hoa Provincial Party Committee, Chairman of the Thanh Hoa Provincial People's Council, along with many provincial leaders, visited, presented gifts, and encouraged officials, engineers, workers, and laborers working on the construction site of the 500kV transmission line project, phase 3, passing through Nong Cong district and Nghi Son town.

According to the report of the Central Power Projects Management Board, the 500kV transmission line project, phase 3, Quynh Luu - Thanh Hoa section is 92km long; of which the section passing through Thanh Hoa province is approximately 74.6km long, including 166 pole foundation positions in Nghi Son town and 5 districts: Nong Cong, Nhu Thanh, Thieu Hoa, Trieu Son, Dong Son, and 82 tension spans.

As of July 30, the 500kV Quynh Luu - Thanh Hoa transmission line project has completed 200/200 foundation positions; 178 steel poles have been erected, and 22 steel poles are being erected, striving to complete the pole erection by August 2, 2024, and to complete the wire pulling of the Quynh Luu - Thanh Hoa section by August 15, 2024.

s
Secretary of the Thanh Hoa Provincial Party Committee happily presents gifts to workers at the construction site. Photo: M.H

Visiting the construction site in Thang Tho commune (Nong Cong) and Cac Son commune (Nghi Son town), Secretary of the Provincial Party Committee Do Trong Hung emphasized: The 500kV transmission line project, phase 3, is a national key project, playing a particularly important role in ensuring the country's energy security, aiming to transmit electricity from the South to the Central and Northern regions, ensuring economic - social development, people's livelihoods, and national defense and security.

According to Mr. Do Trong Hung, since the beginning of 2024, the Government and the Prime Minister have paid special attention to leadership, direction, and have identified this as a particularly important project that must be completed. Following the directives of the Government and the Prime Minister, Thanh Hoa province has identified this as a key project of key projects, with 131km of transmission lines and 299 pole positions... passing through various terrains from plains to mountainous areas.

To implement the project, the Provincial Party Committee, the People's Council, and the People's Committee have directed departments and sectors to proactively coordinate closely with the Ministry of Industry and Trade, the State Capital Management Committee, Vietnam Electricity Group, central ministries, and mobilized the entire political system to participate, with the highest political determination.

Therefore, Thanh Hoa is one of the localities that handed over the site for pole foundation construction and tension spans the earliest. Along with doing well in site clearance, promoting the tradition of "great rear for the front line," the Party Committee, government, and people of Thanh Hoa province have supported, shared, and encouraged officials and engineers working on the construction site both materially and spiritually.

Mr. Do Trong Hung sincerely thanked the contractors, officials, engineers, and workers on the construction site for overcoming difficulties, harsh weather, and challenging terrain with the spirit of "overcoming the sun, winning the rain" in performing their tasks; highly appreciated the local party committees and governments where the project passes through for their decisive and synchronous implementation of the project according to the Prime Minister's directives.

Xuân Hùng
TIN LIÊN QUAN

“Chạy nước rút” trên công trường đường dây 500kV mạch 3

QUÁCH DU |

Thanh Hóa - Những ngày này, bất chấp nắng mưa, các cán bộ kỹ sư, công nhân ngành điện đang “chạy nước rút” thi công đường dây 500kV mạch 3.

Khối lượng thi công dự án 500kV mạch 3 tại Hà Tĩnh còn lớn

TRẦN TUẤN |

Sáng 23.7, báo cáo của Sở Công Thương Hà Tĩnh cho thấy, hiện nay khối lượng thi công của dự án 500kV mạch 3 tại Hà Tĩnh còn rất lớn.

Hoàn thành đường dây 500kV mạch 3 dịp kỷ niệm Quốc khánh

PHẠM ĐÔNG |

Thủ tướng Chính phủ yêu cầu hoàn thành dự án đường dây 500kV mạch 3 chào mừng kỷ niệm 79 năm Cách mạng tháng Tám và Quốc khánh 2.9.

Israel tấn công Lebanon, tuyên bố giai đoạn cuộc chiến mới

Song Minh |

Lực lượng Phòng vệ Israel (IDF) cho biết đã tiến hành không kích vào các mục tiêu của Hezbollah ở miền nam Lebanon.

Sau bão số 4, áp thấp mới liên tiếp xuất hiện ở Philippines

Khánh Minh |

Sau khi áp thấp nhiệt đới Gener mạnh lên thành bão số 4 trên Biển Đông, từ nay đến 1.10, ít nhất 2 áp thấp mới dự kiến xuất hiện gần Philippines.

Thêm nhiều thiết bị phát nổ ở Lebanon sau vụ nổ máy nhắn tin

Bùi Đức |

Nhiều thiết bị điện tử đồng thời phát nổ ở thủ đô Beirut cùng nhiều khu vực khác của Lebanon khiến ít nhất 9 người thiệt mạng và 300 người bị thương.

Dự án ở nút giao nổi tiếng kẹt xe tại khu Đông TPHCM trì trệ

MINH QUÂN |

TPHCM - Nút giao Mỹ Thủy, nơi nổi tiếng kẹt xe và tai nạn, đang triển khai dự án hơn 3.600 tỉ đồng nhưng thi công ì ạch do TP Thủ Đức chậm bàn giao mặt bằng.

Bị thu hồi, trung tâm nông nghiệp ngang nhiên tập kết quặng

Lam Thanh |

Thái Nguyên - Hoạt động kém hiệu quả, Trung tâm Nông nghiệp ứng dụng công nghệ cao tại TP Thái Nguyên thành bãi chứa quặng, vật liệu xây dựng.

"Sprinting" on the construction site of 500kV circuit 3 line

QUÁCH DU |

Thanh Hoa - These days, despite the sun and rain, engineers and workers in the electricity industry are "sprinting" to construct the 500kV circuit 3 line.

The construction volume of the 500kV circuit 3 project in Ha Tinh is still large

TRẦN TUẤN |

On the morning of July 23, a report from the Department of Industry and Trade of Ha Tinh showed that the current construction volume of the 500kV circuit 3 project in Ha Tinh is still very large.

Completed the 500kV 3rd circuit line on the occasion of the National Day celebration

PHẠM ĐÔNG |

The Prime Minister requested the completion of the 500kV circuit 3 line project to celebrate the 79th anniversary of the August Revolution and National Day September 2.