Binh Duong Inspectorate points out violations in 3 public investment projects

ĐÌNH TRỌNG |

Binh Duong Provincial Inspectorate has inspected 3 public investment projects in Thu Dau Mot city, phase 2021-2023, and pointed out related violations.

Binh Duong Provincial Inspectorate has selected 3 bid packages for inspection, including: bid package No. 1 - "construction and equipment" of the road project from Huynh Van Luy to Dong Cay Viet Street (Lien Khu 1-5 Road); bid package No. 2 - "construction and equipment accompanying construction and installation" of the project to renovate, upgrade and expand Phu My Secondary School; bid package No. 3 - "construction and equipment accompanying construction and installation" of the project to renovate, upgrade and expand Hoa Phu Secondary School.

Binh Duong Provincial Inspectorate has just announced the inspection conclusion, pointing out violations by related units.

The Finance - Planning Department of Thu Dau Mot City People's Committee has appraised the bidding documents of 3 packages with shortcomings, leading to the submission to Thu Dau Mot City People's Committee for approval of bidding documents with some evaluation criteria that are not suitable for the scale and technical nature of the packages.

sgfg
Inter-zone Road 1-5. Photo: Dinh Trong

The appraisal of the contractor selection results for package 2 was still lacking, leading to the submission to the People's Committee of Thu Dau Mot City for approval of the contractor selection results but did not ensure the validity of the bidding documents when the authority to sign the bid guarantee and the letter of credit commitment was not clarified.

Notably, the Thu Dau Mot City Construction Investment Project Management Board (representing the investor) organized an inspection of the bidding document preparation work of the bidding consultancy unit that was not strict, leading to the appraisal and approval of the bidding documents with some evaluation criteria that were not suitable for the scale and technical nature of the bidding package (all 3 bidding packages).

Du an Truong THCS Hoa Phu.
Project to upgrade and expand Hoa Phu Secondary School. Photo: Dinh Trong

In addition, the organization of monitoring and checking the process of evaluating bidding documents is not strict, leading to the submission of appraisal and approval of contractor selection results but not ensuring the validity of bidding documents when the authority to sign bid guarantees and letters of credit commitment (bid package No. 2) is not clarified.

In addition, the Binh Duong Provincial Inspectorate also pointed out many violations by enterprises related to the above 3 bidding packages. For Quang Minh Construction Technology Consulting Company Limited (the consulting unit that prepared the bidding documents and evaluated the bidding documents for bidding packages No. 1 and 2), it put forward a number of conditions that were not suitable for the scale and nature of the bidding packages.

In addition, the failure to clarify the right to sign bid guarantees and credit commitment letters led to the approval of contractor selection results but did not ensure the validity of bidding documents.

Du an
Phu My Secondary School upgrade and expansion package. Photo: Dinh Trong

Regarding the consulting unit for bidding package No. 3, Lien Thanh Urban Construction Technical Consulting Joint Stock Company, Binh Duong Provincial Inspectorate also pointed out many violations in preparing bidding documents, including some criteria for evaluating bidding documents that were not suitable for the scale and technical nature of the bidding package...

The above two companies' administrative violations in planning and investment could result in a fine of 80 to 100 million VND. However, the statute of limitations for fines has now expired.

For the construction and installation contractors including the Joint Venture of Van Thinh Phat Trading Construction Company Limited and Nguyen Gia Construction Company Limited (package 2), the Joint Venture of Bao Son Company Limited and Tan Buu Long Company Limited (package 3), the construction quality of the project still has cracks at some points on the wall.

Vach tuong du an bi mot so vet nut. Anh: Dinh Trong
The project wall has some cracks. Photo: Dinh Trong
ĐÌNH TRỌNG
TIN LIÊN QUAN

Nhiều dự án nhà ở xã hội tại Bà Rịa - Vũng Tàu chậm tiến độ

Thành An |

Bà Rịa - Vũng Tàu - Dự kiến phát triển 12.798 căn nhà ở xã hội giai đoạn 2023-2025, song đến hết 2024 chỉ có thể bố trí 313 căn nhà ở xã hội.

Hình ảnh vòng xoay 7ha xây khu phức hợp lớn nhất Bình Dương

ĐÌNH TRỌNG |

Tỉnh Bình Dương đang khẩn trương để chính thức động thổ và khởi động dự án phức hợp Khu văn hóa thương mại dịch vụ - nhà ga trung tâm A1.

Bình Dương đang thực hiện dự án nhà ở xã hội gần 1.900 căn

ĐÌNH TRỌNG |

Bình Dương - Một dự án nhà ở xã hội quy mô 1.867 căn hộ tại phường Thuận Giao, thành phố Thuận An đã được động thổ và đang triển khai.

Vinafco lãi 2,8 tỉ, chưa bồi thường vụ rơi pin xuống biển

Lục Giang |

Vinafco đang phối hợp cùng các chủ hàng, công ty bảo hiểm và các cơ quan chức năng giải quyết sự cố vụ 37 container rơi xuống biển, trong đó có hơn 10 tấn pin.

Xuất hiện clip đánh, đá trẻ tại nhà trẻ, công an vào cuộc

Phan Thành |

Bình Thuận - Từ hình ảnh bảo mẫu đánh bầm tím trẻ nhỏ và đoạn camera cảnh đánh, đá trẻ nhỏ tại nhà trẻ, công an vào cuộc làm rõ.

Bão chưa vào nhưng một số nhà dân ở Quảng Ngãi đã tốc mái

VIÊN NGUYỄN |

Gió lốc trong đêm làm tốc mái 3 ngôi nhà của người dân ở xã Bình Hải, huyện Bình Sơn, tỉnh Quảng Ngãi.

Lộ diện doanh nghiệp cấp bò giống bị dịch lở mồm long móng

HƯNG THƠ |

Bò của dự án khi cấp phát cho người nghèo ở huyện miền núi tỉnh Quảng Trị thì bị lở mồm long móng và lây lan.

Nổ mìn thi công dự án ở dốc Cun, nhiều xe xếp hàng dài chờ đợi

Minh Nguyễn |

Hòa Bình - Trong quá trình nổ mìn để thi công dự án xử lý nguy cơ mất an toàn thông đoạn qua dốc Cun, cơ quan chức năng đã cấm phương tiện lưu thông.

Many social housing projects in Ba Ria - Vung Tau are behind schedule.

Thành An |

Ba Ria - Vung Tau - Plan to develop 12,798 social housing units in the 2023-2025 period, but by the end of 2024, only 313 social housing units can be arranged.

Image of 7ha roundabout building the largest complex in Binh Duong

ĐÌNH TRỌNG |

Binh Duong province is urgently preparing to officially break ground and launch the A1 Central Station - Cultural and Commercial Service Complex project.

Binh Duong is implementing a social housing project of nearly 1,900 apartments.

ĐÌNH TRỌNG |

Binh Duong - A social housing project with 1,867 apartments in Thuan Giao ward, Thuan An city has broken ground and is being implemented.