Another bottom spillway gate of Tuyen Quang hydroelectric reservoir was ordered to close this afternoon

Huy Hùng |

Another bottom spillway gate of Tuyen Quang hydroelectric reservoir was ordered to close at 12:00 on October 7.

The Ministry of Agriculture and Environment has just issued a telegram on closing the bottom spillway of Tuyen Quang hydroelectric reservoir. The dispatch clearly stated that at 07:00 on October 7, 2025, the upstream water level of Tuyen Quang Lake was at 114.14m, the downstream water level was 53.95m, the flow to the lake was 2,007 m3/s, the total downstream flow was 1,818 m3/s.

Implementing the Inter-reservoir operation process in the Red River basin in Decision No. 740/QD-TTg dated June 17, 2019 of the Prime Minister, Decision No. 922/QD-TTg dated May 14, 2025 of the Prime Minister amending and supplementing a number of articles of the Inter-reservoir operation process in the Red River basin, the Minister of Agriculture and Environment ordered the Director of Tuyen Quang Hydropower Company:

Closing 1 bottom spillway gate of Tuyen Quang hydroelectric reservoir at 12:00 on October 7, 2025. 2. Closely monitor the developments of floods, construction safety, flow to the reservoir, water levels upstream and downstream of the reservoir and promptly report to the Ministry of Agriculture and Environment (through the Department of Dyke Management and Natural Disaster Prevention and Control) and relevant agencies according to regulations.

To ensure safety downstream when operating Tuyen Quang hydroelectric reservoir, in an official dispatch sent to the People's Committees of Tuyen Quang, Phu Tho, Hanoi provinces and cities, the Ministry of Agriculture and Environment requested the People's Committees of provinces and cities:

Notify authorities at all levels, people, and organizations operating on rivers and along rivers to know information to proactively take measures to ensure safety and adjust operations accordingly. Timely report any unusual situations to the Ministry of Agriculture and Environment (through the Department of Dyke Management and Natural Disaster Prevention and Control). Propose that the People's Committees of provinces and cities implement.

Huy Hùng
RELATED NEWS

Order to close the bottom spillway of Tuyen Quang Hydropower Reservoir tonight

|

1 bottom spillway of Tuyen Quang hydroelectric reservoir was ordered to close at 10:00 p.m. on October 6.

Close-up of Hoa Binh Hydropower Plant opening 2 bottom spillways

|

Phu Tho - Hoa Binh Hydropower Plant has opened 2 consecutive bottom spillways to prevent floods, creating a majestic scene of white water pouring down on the Da River.

Order to open 2 consecutive bottom spillways of Hoa Binh Hydropower Reservoir today

|

2 bottom spillways of Hoa Binh Hydropower Reservoir were ordered to open.

2 areas in Ho Chi Minh City propose to establish low emission zones to limit gasoline and oil vehicles from 2026

|

Ho Chi Minh City is studying the establishment of a low-emission zone in the central area and Can Gio to limit the operation of gasoline and oil vehicles that do not meet emission standards from 2026.

Hundreds of thousands of people line up to buy tickets for the G-Dragon concert taking place at Vinhomes Ocean Park 3

|

On the first day of ticket sales, the G-DRAGON 2025 WORLD TOUR [Übermensch] concert attracted hundreds of thousands of people online waiting to buy tickets.

Principal apologizes to parents and students after the 25,000 VND meal that caused a stir

|

Quang Tri - When the image of a 25,000 VND meal at Ba Don Primary School No. 1 spread, the school's principal sent an apology letter to parents and students.

Fans queue for more than 3 hours to buy tickets to watch Vietnam play Nepal

|

Many fans lined up for more than 3 hours waiting to buy tickets to watch the Vietnam team face Nepal at Binh Duong Stadium (Thu Dau Mot Ward, Ho Chi Minh City).

People suffer to go to work, make their own boats to move in the sea after heavy rain

|

After heavy rain, many roads turned into rivers, making the journey to work difficult for people.

Order to close the bottom spillway of Tuyen Quang Hydropower Reservoir tonight

Huy Hùng |

1 bottom spillway of Tuyen Quang hydroelectric reservoir was ordered to close at 10:00 p.m. on October 6.

Close-up of Hoa Binh Hydropower Plant opening 2 bottom spillways

Minh Nguyễn - Yên San |

Phu Tho - Hoa Binh Hydropower Plant has opened 2 consecutive bottom spillways to prevent floods, creating a majestic scene of white water pouring down on the Da River.

Order to open 2 consecutive bottom spillways of Hoa Binh Hydropower Reservoir today

Huy Hùng |

2 bottom spillways of Hoa Binh Hydropower Reservoir were ordered to open.