On June 20, Dong Nai City People's Committee just issued a plan to implement compensation, support, and resettlement for the Ben Thanh - Suoi Tien metro line extension project to Dong Nai City Administrative Center and Long Thanh International Airport (Long Thanh airport).
According to the plan, the City Land Fund Development Center will take the lead in coordinating with the surveying unit, relevant units, and people whose land is recovered to carry out surveying, planting markers, determining land recovery boundaries, making land recovery maps and completing them in July 2026.
The City People's Committee also noted that measurement is organized into many teams and groups to speed up progress.
After completing the surveying and mapping of land recovery, the City Land Fund Development Center Branch develops a land recovery plan, to be completed before August 5, 2026.
Before the land recovery notice is issued, the commune-level People's Committee where the land is recovered shall preside over and coordinate with the commune-level Vietnam Fatherland Front Committee and relevant agencies to organize meetings with land owners in the recovered area to disseminate and receive opinions.
The Chairman of the People's Committee of the commune where the land is recovered issues a land recovery notice. The content of the land recovery notice includes: reasons for land recovery; area, location of the recovered land area; land recovery progress; survey, survey, measurement, inventory plan; plan to relocate people out of the land recovery area; compensation, support, resettlement plan and complete before August 20, 2026.
The project to extend the Ben Thanh - Suoi Tien Metro line to the Dong Nai City Administrative Center and Long Thanh airport has a total estimated investment of about 65,573.8 billion VND and applies BT contracts paid by land fund and state budget (public investment source).
The project is about 44.6 km long and includes 2 sections. Section 1 from Suoi Tien station to the Provincial Administrative Center is about 7.4 km long and section 2 from the Provincial Administrative Center to Long Thanh International Airport is about 37.2 km long. The project is invested in building a terminal, Depot and works on the route.
Project implementation locations through wards and communes: Bien Hoa, Tran Bien, Long Hung, Phuoc Tan, Tam Phuoc, An Phuoc, Nhon Trach, Long Thanh; using about 192.5 hectares of land (excluding TOD areas)...
The compensation and site clearance of about 4,323 billion VND is implemented as an independent project using budget capital.
The investor proposing the project is Donacoop Infrastructure Investment Joint Stock Company.
This is a group A project, a special-class urban railway project, construction time from 2026 - 2030.