Possibility to reuse the pair of super drills after excavating the Nhon - Hanoi station metro tunnel

Tô Thế |

Hanoi - After completing the excavation of the Nhon - Hanoi station metro tunnel, the TBM duo is being dismantled. Reusability depends on many technical factors.

After completing the entire tunnel excavation of the underground section of the Nhon - Hanoi station urban railway line (Nhon - Hanoi railway), two TBM tunnel excavators (Tunnel Boring Machine) are being dismantled by units and brought to the ground at station S12.

sss
Nhon - Hanoi station metro tunnel drilling machine is being dismantled at station S12. Photo: MRB

Along with that, many opinions are interested in whether this pair of "super drills" can continue to be used for other metro projects in the future.

Hanoi Urban Railway Management Board (MRB) said that, in principle, TBM tunnel excavators can be completely reused after completing their tasks at a project.

However, this is a high-tech equipment designed based on very specific conditions of each project. Two TBM1 and TBM2 machines are invested separately for the construction of the tunnel section of the Nhon - Hanoi urban railway line project, based on technical requirements, geological conditions and the riêng design of the line.

According to MRB, in order to be able to continue to be used for a new project, TBM machines must undergo a comprehensive inspection and evaluation process. If necessary, the equipment will be converted to meet the technical, quality, safety and reliability requirements of the next project.

In fact, reusability depends on many factors. These include the level of wear and lifespan of equipment after construction (especially the cutting head and main electromechanical systems); the compatibility between geological and hydrological conditions of the projects;

Technical requirements, subsidence and deformation control standards of each route, as well as overall economic efficiency between the renovation, transportation, and re-installation plans compared to new equipment investment", MRB informed.

sss
The main part of the TBM machine weighs about 500 tons. Photo: MRB
ss
TBM machine components are being dismantled and lifted to the ground to be taken to the storage warehouse. Photo: MRB

MRB added that, according to the practice of implementing urban railway projects, TBM is equipment under the management of the contractor. Based on specific technical and economic efficiency assessments, the contractor will propose a plan to continue using or investing in new equipment.

The investor only considers and approves the proposed plan when it fully meets the technical requirements of the project as well as the related contract conditions.

sss
Nhon metro tunnel - Hanoi station. Photo: MRB

Previously, two TBM machines named "Speed" and "Drifty" had completed the excavation of more than 4km of underground tunnel of the Nhon - Hanoi station metro line.

MRB also informed that currently, the construction volume of the underground section of the Nhon - Hanoi Metro line has reached about 79.3%.

In the coming time, MRB will continue to coordinate with relevant units to urge contractors to ensure progress, project quality, labor safety and environmental sanitation, while minimizing the impact on people's lives in the project area.

Tô Thế
RELATED NEWS

Nhon - Hanoi station metro underground section reaches nearly 80% progress, project accelerates to the finish line

|

Hanoi - To date, the Nhon - Hanoi subway section has reached nearly 80% progress, accelerating completion to be put into operation by the end of 2027.

Close-up of dismantling and lifting the "super drill" of Nhon - Hanoi station metro tunnel to the ground

|

Hanoi - After completing tunnel excavation, TBM machine No. 2 of the Nhon - Hanoi station metro line was dismantled under station S12 with high technical requirements.

4 options to take the metro from Tan Son Nhat airport to Long Thanh

|

Ho Chi Minh City has been and is studying 4 options to connect Tan Son Nhat and Long Thanh airports by metro, aiming to form a rapid transit network between the two airports.

Voices from the grassroots to the 14th Vietnam Trade Union Congress

|

Gia Lai - Chairman of Quy Nhon Bac Ward Trade Union proposed that the 14th Congress of the Vietnam Trade Union pay more attention to jobs, income, housing and the lives of workers.

Factory in Hanoi catches fire fiercely

|

Hanoi - A fire broke out at a factory in Hoai Duc commune, functional forces mobilized many vehicles and officers and soldiers to the scene.

Tighten high-tech fraud before the 2026 high school graduation exam

|

Before the 2026 high school graduation exam, localities are recommended to use police technical equipment to detect high-tech equipment cheating on exams.

Ho Chi Minh City seeks expert opinions for 100-year vision master plan

|

Ho Chi Minh City is building a master plan with a 100-year vision, aiming for a 1,200 billion USD megacity, to be included in the group of 100 most livable cities in the world.

Russia launches fierce attack on Kiev

|

Kiev suffered a wave of fierce attacks from Russia, many people are believed to be trapped under the rubble of an apartment building.

Nhon - Hanoi station metro underground section reaches nearly 80% progress, project accelerates to the finish line

Tô Thế |

Hanoi - To date, the Nhon - Hanoi subway section has reached nearly 80% progress, accelerating completion to be put into operation by the end of 2027.

Close-up of dismantling and lifting the "super drill" of Nhon - Hanoi station metro tunnel to the ground

Tô Thế |

Hanoi - After completing tunnel excavation, TBM machine No. 2 of the Nhon - Hanoi station metro line was dismantled under station S12 with high technical requirements.