Song Bung 4 Hydropower Plant ahead of schedule for major repairs of Unit H2

Hùng Trinh |

Song Bung 4 Hydropower Plant, major repair of Unit H2 exceeded the schedule by 7 days compared to the plan, ensuring quality and safety.

Song Bung Hydropower Company said that from August 23, 2026, the unit has completed major repairs of Unit H2 – Song Bung 4 Hydropower Plant, exceeding the schedule by 7 days compared to the approved plan, ensuring quality and safety. The unit has been restored to a usable state, ready to serve power generation, reservoir regulation and disaster prevention and control in the 2026 rainy and storm season.

Major repair of Unit H2 is one of the important items in the 2026 repair plan of Song Bung Hydropower Company. The unit was grid-separated and isolated from August 1, 2026. With the requirement to complete it within a limited time of isolation, the Company has proactively deployed preparations, from building construction plans, surveying the current status of equipment to preparing materials, specialized equipment and technical personnel.

From the beginning, the Company's Board of Directors directed professional departments and workshops to closely coordinate with the contractor unit, organize scientific construction, and control the progress of each item. The team of technical staff and workers directly involved in construction have promoted the spirit of responsibility, proactively handling arising problems, ensuring strict requirements on technology and labor safety. During the overhaul, many important items of the H2 unit were inspected, maintained and tested, including: turbines, generators, accelerator systems, magnifying systems, protective relays, disc valves, unit cooling systems, single-way and rotating self-use power supply systems, vibration - stir monitoring systems and related measuring and protective equipment.

Đội ngũ công nhân kỹ thuật đang thực hiện kiểm tra các thiết bị cơ điện trong chương trình sửa chữa lớn tổ máy H2 – Nhà máy Thủy điện Sông Bung 4. Ảnh: Hùng Trinh
Technical workers are inspecting electromechanical equipment in the major repair program of unit H2 – Song Bung 4 Hydropower Plant. Photo: Hung Trinh

The inspection work is carried out according to each system and equipment, combining measurement and evaluation of technical parameters. The defects arising during the inspection are promptly handled, thereby contributing to improving the reliability and stable operation of the unit after repair.

Đội ngũ công nhân đang thực hiện công tác kiểm tra, vệ sinh, bảo dưỡng máy phát tổ máy H2 – Nhà máy Thủy điện Sông Bung 4. Ảnh: Hùng Trinh
Workers are performing inspection, cleaning, and maintenance of generator unit H2 – Song Bung 4 Hydropower Plant. Photo: Hung Trinh

A consistent requirement throughout the overhaul process is that safety must be put first. The work is organized and supervised closely, complying with technical procedures, regulations on labor safety and requirements of each item. The coordination between the Company's forces and the contractor unit is maintained regularly, contributing to ensuring progress without affecting the quality of work.

After completing the installation, the H2 unit was organized for unloaded and loaded test runs and overall experiments and adjustments were carried out according to the process. Technical parameters were checked and evaluated before the unit was connected to the grid. Based on the test results meeting requirements, the Company coordinated with the National Power System and Electricity Market Operation Unit (NSMO) to carry out the necessary procedures to restore the H2 unit to its usable state.

Đội ngũ công nhân kỹ thuật đang thực hiện kiểm tra máy biến áp T1 – Nhà máy Thủy điện Sông Bung 4. Ảnh Hùng Trinh
Technical workers are inspecting transformer T1 – Song Bung 4 Hydropower Plant. Photo by Hung Trinh

Completing major repairs of unit H2 – Song Bung 4 Hydropower Plant ahead of schedule by 07 days is a remarkable result, demonstrating the management capacity, sense of responsibility and effective coordination of the collective of officials and employees of Song Bung Hydropower Company and participating units. More importantly, this result contributes to improving the reliability of Unit H2, consolidating the power generation capacity of Song Bung 4 Hydropower Plant and creating conditions for the Company to proactively perform operational tasks in the coming time.

In the context of the 2026 rainy and storm season approaching, bringing the H2 unit back to safe and stable operation is of practical significance for reservoir regulation, power generation and disaster prevention and control. This is also proof of the spirit of proactiveness, discipline, coordination and responsibility of the collective of workers of Song Bung Hydropower Company, contributing to the good implementation of production and business tasks and ensuring energy security.

Hùng Trinh
RELATED NEWS

Water levels of hydropower reservoirs nationwide on August 28th

|

Many hydropower reservoirs across the country on August 28th were still below normal water levels, and the water flow to some large reservoirs in the North, Central and Central Highlands was high.

Water level of some hydropower reservoirs in the Central - Central Highlands region on August 28th

|

Hydropower reservoirs in the Central - Central Highlands on August 28th were mostly lower than the normal water level, while some reservoirs had high inflows and discharges.

An Khe - Ka Nak Hydropower Company supports digital transformation at the grassroots level

|

Gia Lai - An Khe - Ka Nak Hydropower Company supports the purchase of computers for people to implement administrative reform and digital transformation more conveniently.

Fire at a row of car repair shops on Le Quang Dao street in Hanoi

|

Hanoi - The fire occurred at a row of temporary shacks and a car repair shop on Le Quang Dao street, Tu Liem ward, with a smoke column tens of meters high.

National Highway 13 section passing through old Binh Duong province is congested on the first day of the September 2nd holiday

|

Ho Chi Minh City - On August 29, the number of vehicles returning to their hometowns for holidays began to increase, National Highway 13, the section passing through Binh Duong province before, was congested for a long time.

The joyful atmosphere throughout Hanoi streets, towards National Day September 2nd

|

Hanoi - These days, the Capital is wearing a brilliant coat of flags, flowers, posters... towards the 81st anniversary of National Day 2. 9.

Son Tung MTP, Hoa Minzy and how Vietnamese music attracts attention from the world

|

According to Assoc. Prof. Dr. Nguyen Huy Phuong, the success of Son Tung M-TP and Hoa Minzy is thanks to the combination of Vietnamese materials with modern music language.

Opportunity for Vietnam to become a global manufacturing center

|

FDI capital flows along with production and export growth are opening up opportunities for Vietnam to rise to become a global manufacturing center.

Water levels of hydropower reservoirs nationwide on August 28th

Minh Nguyễn |

Many hydropower reservoirs across the country on August 28th were still below normal water levels, and the water flow to some large reservoirs in the North, Central and Central Highlands was high.

Water level of some hydropower reservoirs in the Central - Central Highlands region on August 28th

Minh Nguyễn |

Hydropower reservoirs in the Central - Central Highlands on August 28th were mostly lower than the normal water level, while some reservoirs had high inflows and discharges.

An Khe - Ka Nak Hydropower Company supports digital transformation at the grassroots level

THANH TUẤN |

Gia Lai - An Khe - Ka Nak Hydropower Company supports the purchase of computers for people to implement administrative reform and digital transformation more conveniently.