Progress of 2 intersection projects worth more than 1,460 billion VND in Hai Phong

Hoàng Khôi |

Hai Phong - Two intersection projects in the city are facing difficulties due to high material prices and scarcity of supply.

The investment project to build a traffic intersection between Bui Vien street and Le Hong Phong street has a total investment of 785.986 billion VND, using city budget capital, implementation time from 2024-2027. The project does not have to carry out site clearance.

To date, the contractor has demolished existing structures reaching 10,461.1/13,711.95m3; excavated the roadbed foundation 26,811.5/113,833.63m3; constructed cement piles 110,278.31/110,278.31m; tunnel concrete 726.2/21,749.15m3; tunnel steel 59.65/2,177.45 tons. The completed value reached 66.413/518.169 billion VND, equivalent to 14% of the contract value.

Regarding disbursement, the project disbursed 131.071 billion VND, reaching 55.38% of the annual capital plan; accumulated allocated capital reached 386.695/707.1678 billion VND (54.68% of total investment), accumulated disbursement reached 283.699/386.695 billion VND, equivalent to 73.37% of the capital plan.

According to the Management Board, the project is facing difficulties due to high material prices, scarcity of supply and the impact of heavy rain weather, and also generating a large volume of excavated material during the process of treating weak soil foundations and constructing tunnel sections. The Project Management Board has issued document No. 1029/BQL-DA1 dated July 6, 2026, reporting to the City People's Committee on the policy of management, coordination, and reuse of excavated material and requesting early approval for implementation.

As for the investment project to build a traffic intersection between Bui Vien street and Vo Nguyen Giap street with a total investment of 675.011 billion VND, it has now completed the relocation of technical infrastructure works on the route and treated weak soil foundation with cement pile soil; is deploying excavation and dismantling of existing structures, pouring concrete into tunnel sections and ensuring traffic safety. The estimated completed value is 100.941/467.651 billion VND, equivalent to about 21.58% of the contract value.

Chủ tịch UBND TP Hải Phòng Đỗ Thành Trung kiểm tra tiến độ dự án nút giao. Ảnh: Cổng TTĐT Hải Phòng
Chairman of Hai Phong City People's Committee Do Thanh Trung inspects the progress of the intersection project. Photo: Hai Phong e-Portal

Similar to the Bui Vien and Le Hong Phong intersection project, the project mainly faces difficulties due to sharp increases in material prices and scarce supply, while the contract is based on fixed unit prices; The Project Management Board proposed considering applying force majeure clauses to adjust unit prices for construction volume from March 1, 2026. Regarding disbursement progress, in 2026, the project was allocated VND 280.818 billion, with disbursement of VND 167.437 billion, reaching 59.62% of the annual capital plan; accumulated disbursed capital reached VND 433.449/675.01077 billion (63.82% of total investment), accumulated disbursement reached VND 320.068/433.449 billion, equivalent to 73.84% of the capital plan.

According to the report of the Hai Phong Transport Construction Investment Project Management Board, the implementation of projects to date basically ensures progress according to the set requirements.

Inspecting the reality at key construction projects on July 11, Chairman of Hai Phong City People's Committee Do Thanh Trung requested the Project Management Board, heads of relevant departments and branches and local authorities to strengthen close coordination, proactively review and thoroughly resolve difficulties and obstacles arising during the implementation process; drastically urge construction progress and ensure the disbursement rate of public investment capital in accordance with the set plan.

According to the report of the Hai Phong Transport Construction Investment Project Management Board, the implementation of projects to date basically ensures progress according to the set requirements.

Hoàng Khôi
RELATED NEWS

Hai Phong deploys socialist trade union model in units with nearly 500 workers

|

Hai Phong - July 11, the Trade Union of Da Do Irrigation Works Exploitation Co., Ltd. launched the "Socialist Grassroots Trade Union" model for the period 2026-2030.

Paying nearly 146 billion VND for compensation for the Ngu Phuc Industrial Park project, Hai Phong

|

Hai Phong - Nghi Duong commune has just paid compensation to households in Xuan Mai village for land acquisition to implement the Ngu Phuc Industrial Park Project (phase 1).

People in Hai Phong landslide risk area receive resettlement land after many years of waiting

|

Hai Phong - Households in dangerous landslide risk areas in Do Son ward are handed over resettlement land to stabilize their lives.

Close-up of the hundred billion Ring Road 2.5 section Trung Kinh - Hoang Quoc Viet

|

Ring Road 2.5 section from Trung Kinh to Hoang Quoc Viet (Hanoi) is expected to contribute to reducing traffic pressure for the Cau Giay area.

Sophisticated activities of inter-provincial gambling ring during the 2026 World Cup season

|

Quang Tri - Provincial police dismantled an inter-provincial gambling ring operating during the 2026 World Cup season, initially determining the transaction amount to be about 400 billion VND.

People prepare red books, officials will bring photocopiers to their homes to scan land data

|

Hanoi - Some localities are deploying land data scanning right at home, people need to prepare red books and CCCDs.

Hai Phong deploys socialist trade union model in units with nearly 500 workers

Mai Dung |

Hai Phong - July 11, the Trade Union of Da Do Irrigation Works Exploitation Co., Ltd. launched the "Socialist Grassroots Trade Union" model for the period 2026-2030.

Paying nearly 146 billion VND for compensation for the Ngu Phuc Industrial Park project, Hai Phong

Hoàng Khôi |

Hai Phong - Nghi Duong commune has just paid compensation to households in Xuan Mai village for land acquisition to implement the Ngu Phuc Industrial Park Project (phase 1).

People in Hai Phong landslide risk area receive resettlement land after many years of waiting

Hoàng Khôi |

Hai Phong - Households in dangerous landslide risk areas in Do Son ward are handed over resettlement land to stabilize their lives.