The dam project to create a landscape in the center of Ha Giang city worth 330 billion VND will start construction in March 2023. The project includes the construction of dams and a traffic bridge measuring 123m long.
Recognizing PV at the end of May 5.2025, dozens of workers and equipment and equipment are being mobilized to implement the project. Some construction sites in the river bed are forced to create a water corridor. The nails, dams, the abutment of the traffic bridge have been completed. The contractor is focusing on the construction of the dome, building a traffic bridge.

Talking to reporters of Lao Dong Newspaper, Mr. Nguyen Song Tu - Deputy Director of the Ha Giang Province Construction Investment Project Management Board said that the dam project has so far reached nearly 70% of the workload. The goal is to be completed and put into use in 2025.
Currently, the construction unit is focusing on human resources to build bridge and arch items. The locations in the lower part of the river surface have basically been completed.
Once completed, the project will offer the Lo River at the location of 6m dam, creating a lake bed with an area of nearly 54ha and a capacity of 2.2 million m3. Not only keeping the water level of Lo River stable, the project also helps to regulate the climate, improve the ecological environment and develop tourism. Traffic bridge on the dam will connect QL2 to the southern ring road in the city.
3km from the center of Ha Giang City, the Provincial Sports and Cultural Complex worth 340 billion VND is also being urgently implemented.
The project with a 10,000-seat stadium has been formed. Currently, contractors are focusing on constructing the stands and courtyards, aiming to complete the entire project.

According to the construction unit, the project progress has reached about 90% of the workload, striving to complete in July 2025.
Meanwhile, the key project of Tuyen Quang - Ha Giang expressway, the 27km section through Ha Giang, with an investment of nearly VND3,200 billion, is also about to be completed.
According to the reporter, along the entire route, equipment and human resources are mobilized for construction day and night. In addition to the roadbed, bridge and underpass items are deployed synchronously.

According to the Ha Giang Province Traffic Construction Investment Project Management Board, this project has achieved and exceeded the schedule for many items. The project adjustment, raising from 2 lanes to 4 lanes, is being carried out and can be implemented in August 2025.
As expected, the Tuyen Quang - Ha Giang expressway will be completed by the end of 2025. Along with the section through Tuyen Quang, the project will help shorten travel time to Ha Giang and Thanh Thuy International Border Gate. Thereby, promoting the socio-economic development of Ha Giang.