What is the progress of the My Thuy port project with a capital of 15,000 billion VND in Quang Tri

HƯNG THƠ |

Quang Tri - My Thuy Port Area Project is under construction phase 1 with many key items, expected to open wharf No. 1 in April 2026.

Early operation of wharf No. 1

The My Thuy Port Area project, invested by My Thuy International Port Joint Stock Company (MTIP), has gone through many difficult stages, especially in site clearance (GPMB), and is currently entering an important construction phase.

The My Thuy Port Area project is not only a simple transport infrastructure project but also brings great economic development opportunities for Quang Tri province. When completed, My Thuy port will be able to receive ships with a tonnage of up to 100,000 DWT, increasing the operating capacity to 12 million tons/year in phase 1, with a total completion capacity of up to 30 million tons/year by 2036.

Thi công các hạng mục ở Dự án Khu bến cảng Mỹ Thủy. Ảnh: Hưng Thơ
Construction of items at the My Thuy Port Area Project. Photo: Hung Tho

According to information from MTIP, as of the present time, the total cost paid for site clearance has reached 148.34 billion VND. The project has completed land lease and issuance of land use right certificates for 133.46 ha (phase 1). The conversion of forest use purposes and replacement forest planting has also been completed, an important step for the project to continue construction without legal obstacles.

In the days after the Lunar New Year, the project construction site is bustling with vehicles and workers urgently constructing items. Currently, phase 1 of the project is being implemented with main items, including the eastern breakwater, wharf, embankment behind wharves No. 1 and No. 2, dredging of the channel, turning basin, water area in front of the wharf, and construction of post-wharf technical infrastructure. The investor's goal is to complete wharves No. 1 and No. 2 by March 2026, and put wharf No. 1 into operation in April 2026.

Early removal of obstacles to ensure project completion on schedule

The My Thuy Port Area project not only creates great momentum for the sea transport industry but also opens up new potential for the logistics industry in the North Central region. With the efforts of the investor and timely support from all levels of government, the project is moving closer to the goal of becoming a key seaport of the region.

Lãnh đạo tỉnh Quảng Trị kiểm tra tiến độ Dự án Khu bến cảng Mỹ Thủy. Ảnh: H.Nguyên
Quang Tri provincial leaders inspect the progress of the My Thuy Port Area Project. Photo: H.Nguyen

However, one of the difficulties that has not been removed is that currently 20.02ha of turning basin and 15ha of storage yard have not been cleared. Phase 2 of the Hai An Resettlement Area phase 2 and Hai An Resettlement Area phase 3 have not been implemented, so they do not meet the needs for resettlement land. The scope of site clearance for phases 2 and 3 of the project includes many churches, communal houses, pagodas, tombs, and the area of the people's cemetery within the project is about 10ha. In particular, construction and expansion of houses violating construction order are still continuing to occur in the project area.

Mr. Le Duc Tien, Vice Chairman of Quang Tri Provincial People's Committee, said that provincial leaders always closely monitor the construction progress and directly inspect the site to resolve arising difficulties and obstacles. On February 24, Quang Tri Provincial Party Secretary Nguyen Van Phuong also came to inspect the project and requested functional agencies to continue to support the investor, especially in site clearance work.

HƯNG THƠ
RELATED NEWS

Dinh Bac receives penalty from AFC

|

AFC issued a penalty to VFF and striker Nguyen Dinh Bac after violations at SEA Games 33 and the 2026 AFC U23 Championship.

It takes more than 30 minutes to get to the end of Lang street during rush hour

|

Hanoi - Rush hour morning of February 26, Lang street was congested for a long time in the area near intersections, vehicles moved slowly.

Loneliness on the sofa", "The day before the storm" and ACB Bank's strategy

|

The songs "Lonely on the Sofa" and "Day Without Storm" are considered communication strategies to help Asia Commercial Bank (ACB) connect closer with customers.

Hanoi's largest fabric market is sluggish at the beginning of the year, purchasing power decreases sharply

|

Hanoi - After the Lunar New Year, the trading atmosphere at Ninh Hiep market becomes unusually quiet.

Determining the cause of a railway accident that killed 1 person in Hanoi

|

Hanoi - A serious railway accident in Ngoc Hoi commune occurred because a truck driver tried to overtake the barrier when the North-South train was approaching.

Social housing project after 5 years, delivery delayed more than 10 times

|

5 years with more than 10 delays in handover, the Sao Hong social housing project (Que Vo ward, Bac Ninh province) caused much frustration for workers and laborers who had spent hundreds of millions of VND to buy houses.

Students line up to rent for the God of Wealth Day, 150,000 VND/session

|

On God of Wealth Day, gold shops are bustling from the early morning. Many students take advantage of hiring to queue, earning 150,000 VND per turn.

Cambodia announces 50% elimination of online scams

|

Cambodia said that the campaign to crack down on online scams has helped reduce activity by half since the beginning of this year.

Đường khẩn cấp sau bão lũ thành... dự án treo

Hoàng Bin |

Gần 400 tỉ đồng được chi để tái thiết 30km đường vùng cao sau bão lũ năm 2020 ở Đà Nẵng. Thế nhưng, hơn 4 năm trôi qua, dự án vẫn dang dở, người dân tiếp tục sống trong cảnh chia cắt.

Sau 3 năm khởi công rồi nằm yên, cảng Mỹ Thủy ở Quảng Trị rục rịch khởi công lại

HƯNG THƠ |

Dự án Khu bến cảng Mỹ Thủy (tỉnh Quảng Trị) có tổng vốn đầu tư 14.234 tỉ đồng khởi công cách đây 3 năm rồi rơi vào tình trạng im ắng, nay nhà đầu tư quyết tâm khởi công lại và thi công vào cuối tháng 3.2024 này.

Đại gia nào đứng sau Cảng Mỹ Thủy hơn 14.000 tỉ sắp khởi công tại Quảng Trị?

Lục Giang |

Từ giai đoạn 2015 - 2018, chủ đầu tư Cảng Mỹ Thủy tăng mạnh vốn điều lệ từ 500 tỉ đồng lên 2.500 tỉ đồng. Đáng chú ý, công ty này có sự tham gia đầu tư, góp vốn của SAM Holdings với tỉ lệ sở hữu 36%.