Progress of the Hoa Binh - Moc Chau Expressway project

Yên San |

After many months of construction, the Hoa Binh - Moc Chau expressway project, the section through Hoa Binh has achieved positive results in terms of progress.

The Hoa Binh - Moc Chau Expressway Project, the section passing through Hoa Binh, started construction in September 2024 with a total length of about 34km, a total investment of nearly 10,000 billion VND, invested by the Hoa Binh Provincial Traffic Construction Investment Project Management Board.

The starting point of the project is at Km19+000 in Da Bac town; the end point is at Km53+000 in Chieng Yen commune, Van Ho district, Son La.

As of March 2025, the construction site at the starting point of the project located in Cao Son commune, Da Bac district, Hoa Binh province, about 78% of the route length (17/21.75km) has been cleared, creating favorable conditions for construction units to mobilize vehicles and human resources to the construction site.

Anh: Khanh Linh
Hoa Binh - Moc Chau Expressway construction site through Cao Son commune, Da Bac district. Photo: Khanh Linh

Mr. Bui Chi Cong, Head of Project Management Department 2 - Traffic Construction Investment Project Management Board of Hoa Binh province, said: "The contractors are organizing continuous construction of 3 shifts per day. Although the weather in the highlands is harsh, officers, engineers and workers are trying to work overtime to ensure the machinery operates to the maximum extent, on schedule.

Thanks to that effort, many first sections of the roadbed have taken shape, creating a premise for entering the construction phase of the road surface in the coming months.

According to Mr. Cong, on the section passing through Da Bac district, the XL01 package contractor has organized 2 construction teams to build roadbeds at locations with available land and 1 construction team for bridge and culvert items (underpasses, box culverts, round culverts) at many locations on the route.

At the same time, the XL02 package contractor in charge of the construction of the two tunnels through the mountains has also completed the clearing and opened 4 new service routes with a total length of about 1.7km to access the tunnel gates and transport equipment and materials to the construction site.

Du an cao toc Hoa Binh - Moc Chau duoc ky vong  dat nen mong cho su phat trien but pha cua ca mot vung Tay Bac. Anh: Yen San
The Hoa Binh - Moc Chau Expressway project is expected to lay the foundation for the breakthrough development of an entire Northwest region. Photo: Yen San

Mr. Ly Van Henh (Cao Son commune) shared: "If the route is completed and put into operation, it will help shorten the time from the center of Hoa Binh city to Moc Chau district in particular and Son La in general".

According to Mr. Henh, because he often travels between Da Bac district (Hoa Binh) and Van Ho (Son La), having to go around Da Bac to National Highway 6 and cross many steep passes to Son La is extremely difficult.

Therefore, what people want most is for the expressway to be completed and put into operation soon, helping to shorten travel time.

Reporting to Deputy Prime Minister Nguyen Chi Dung during the survey of the construction progress of the Hoa Binh - Moc Chau Expressway Project, Mr. Quach Tat Liem - Vice Chairman of the People's Committee of Hoa Binh Province, Head of the Project Steering Committee, said that the capital and disbursement progress of the Hoa Binh - Moc Chau Expressway Project are a worrying issue. Due to the project starting construction late, construction packages will only be selected from the end of 2024, so the disbursement of investment capital is still slower than planned.

According to Mr. Liem, the capital pressure is very high, if not resolved promptly, it will be difficult for the project to ensure progress. Therefore, the province has proposed that the Government allow the extension of the disbursement period of capital under the socio-economic recovery program to the end of 2025 to continue to provide enough for the project.

Currently, the locality is working with relevant ministries and branches to strengthen guidance and support for the province in the project implementation process to speed up progress, ensure progress, quality and promote investment efficiency.

Yên San
TIN LIÊN QUAN

Hoa Binh Hydropower Reservoir Dry, Revealing Many Rocky Mountains

|

Hoa Binh - The water level of the Hoa Binh Hydropower Reservoir is currently about 20 m lower than at the time of flood discharge, revealing many cliffs along the coast.

Stone block suspected of dating trees worth nearly 20 billion VND in Hoa Binh

|

Hoa Binh - The block of stone suspected to be the origin of a fossil tree, weighing tens of tons in Hoa Binh City, attracted attention when someone was willing to pay nearly 20 billion VND.

Another apartment complex in Hoa Binh City is seriously degraded

|

Hoa Binh - In the center of Hoa Binh City, a long-standing apartment complex continues to fall into a state of serious degradation after more than 40 years of use.

Fire at a grocery store signboard and then spread to a fried chicken shop in Ho Chi Minh City

|

HCMC - The hang at Ly Thai To roundabout suddenly caught fire, then spread to the fried chicken restaurant next door.

For the first time, a Bollywood film was filmed in Son Doong Cave

|

SILAA is the first Bollywood film shot at Son Doong Cave. The film is also set in a series of other famous places such as Cao Bang, Ninh Binh...

Deputy Prime Minister agrees to merge 2 corporations into VNPT

|

Deputy Prime Minister Ho Duc Phoc agreed in principle to merge VNPT-Vinaphone, VNPT-Media into the parent company - VNPT Group.

Verifying the case of students paying for martial arts classes to get exercise in Dak Lak

|

Dak Lak - The provincial Department of Education and Training directed Phan Dang Luu High School to verify parents' feedback about students paying for martial arts classes to achieve physical education.

Disciplinary action to expel former Permanent Vice Chairman of Hung Yen Provincial People's Committee from the Party

|

The Secretariat decided to take disciplinary action by expelling Mr. Nguyen Bat Coi - former Permanent Vice Chairman of the People's Committee of Hung Yen province from the Party.

Hoa Binh Hydropower Reservoir Dry, Revealing Many Rocky Mountains

Minh Nguyễn |

Hoa Binh - The water level of the Hoa Binh Hydropower Reservoir is currently about 20 m lower than at the time of flood discharge, revealing many cliffs along the coast.

Stone block suspected of dating trees worth nearly 20 billion VND in Hoa Binh

Yên San |

Hoa Binh - The block of stone suspected to be the origin of a fossil tree, weighing tens of tons in Hoa Binh City, attracted attention when someone was willing to pay nearly 20 billion VND.

Another apartment complex in Hoa Binh City is seriously degraded

Yên San |

Hoa Binh - In the center of Hoa Binh City, a long-standing apartment complex continues to fall into a state of serious degradation after more than 40 years of use.