Progress of site clearance for a 120-180m wide road project in Hanoi

SÓNG HỮU |

Hanoi - The progress of site clearance for a 6.7km long, 120-180m wide road is being accelerated by the locality according to the city's direction.

The investment project to build the Thang Long Avenue expressway, the section connecting National Highway 21 to the Hanoi - Hoa Binh expressway, started in October 2023.

The project has a total investment of 5,249 billion VND, invested by the Hanoi Civil Works Construction Investment Project Management Board. The city plans to complete a 6.7km long road with a cross-section of 120-180m in 2026.

According to the assessment of the Hanoi People's Committee, the project implementation will gradually complete the entire Hanoi - Hoa Binh expressway; develop and expand Hanoi Capital to the West, meeting the increasing transportation demand; and be a driving force for the development of Hoa Lac satellite city and the Western satellite city chain.

Hoa Lac Commune People's Committee said that the project to build the Thang Long Avenue expressway, the section connecting National Highway 21 to the Hanoi - Hoa Binh expressway through the commune, has a total of 688 land plots to be recovered, with a total area of about 60.56 ha.

In which, before the implementation of the 2-level local government model, site clearance work had been deployed and completed by all levels of government for 188 land plots.

From July 1, 2025, after implementing the 2-level local government model, the remaining 500 land plots of the project will be directly assigned by the City to Hoa Lac Commune People's Committee to organize site clearance work, with the required completion schedule before February 15, 2026.

This is a very large workload, urgent time, high requirements for progress and legality, requiring the synchronous and drastic involvement of the entire socio-political system.

a
Leaders of Hoa Lac commune regularly go to the field to inspect the current situation, direct the removal of obstacles; meet, propagate, mobilize, and dialogue with households in site clearance. Photo: TTĐT Hoa Lac commune

By January 29, Hoa Lac commune had completed 100% counting of all 500/500 allocated land plots, contributing to completing the counting of 688/688 plots of the entire project, clearly showing the spirit of responsibility, determination and drastic action of the commune Party Committee and government in performing the tasks assigned by the City.

In the process of implementation, many households have shown a high consensus spirit, proactively handing over the site before approving the compensation plan, with 6.63 ha/43 plots of 36 households, showing consensus and support for the policy of land recovery to serve the capital's key project.

In parallel with the inventory work, the commune's specialized agencies are urgently completing dossiers, publicizing plans, pricing, and paying compensation, support, and resettlement according to regulations, ensuring the progress of site clearance as required by the City.

SÓNG HỮU
RELATED NEWS

Land clearance for National Highway 6: Hanoi sets deadline to complete in 3 wards

|

Hanoi requests Yen Nghia, Duong Noi, and Kien Hung wards to complete site clearance for National Highway 6, Ba La - Xuan Mai section, in accordance with the progress commitment.

Long Bien accelerates site clearance for Tran Hung Dao bridge

|

Hanoi - Long Bien Ward strengthens dialogue and specific explanations so that people understand clearly, feel secure and agree to implement the site clearance of Tran Hung Dao bridge.

Thanh Xuan Ward has not completed site clearance for Nguyen Tuan street project

|

Hanoi - The Nguyen Tuan road expansion project (Thanh Xuan ward) is facing a 2-story apartment building related to 6 households.

Fans come to the stadium from 1 pm to watch the match of the Vietnamese team

|

Thousands of fans were present at Thai Nguyen Stadium early, even some came from 1 pm to wait to watch the match between Vietnam and Myanmar.

A nearly 3-year-old boy in critical condition after studying at an intervention facility

|

Thanh Hoa - After a class at an intervention facility, a nearly 3-year-old boy was found to have many serious injuries and had to be hospitalized in critical condition.

2026 World Cup Final: The battle of wits begins with personnel choices

|

Before the 2026 World Cup final, Luis de la Fuente and Lionel Scaloni both faced difficult personnel problems.

After organizing the civil servant exam, Cao Bang Department of Education and Training received instructions to reduce 596 staff positions

|

Cao Bang - The Department of Education and Training has a document requesting to temporarily suspend the recruitment of public employees in the Education sector due to a reduction of nearly 600 staff positions.

Binh Duong MB is pointed out for many shortcomings from lending to bad debt handling

|

The State Bank Inspectorate pointed out many shortcomings at MB Binh Duong in lending, post-loan monitoring, bad debt handling and foreign exchange operations.

Land clearance for National Highway 6: Hanoi sets deadline to complete in 3 wards

Minh Hạnh |

Hanoi requests Yen Nghia, Duong Noi, and Kien Hung wards to complete site clearance for National Highway 6, Ba La - Xuan Mai section, in accordance with the progress commitment.

Long Bien accelerates site clearance for Tran Hung Dao bridge

KHÁNH AN |

Hanoi - Long Bien Ward strengthens dialogue and specific explanations so that people understand clearly, feel secure and agree to implement the site clearance of Tran Hung Dao bridge.

Thanh Xuan Ward has not completed site clearance for Nguyen Tuan street project

SÓNG HỮU |

Hanoi - The Nguyen Tuan road expansion project (Thanh Xuan ward) is facing a 2-story apartment building related to 6 households.