Progress of site clearance for a 120-180m wide road project in Hanoi

SÓNG HỮU |

Hanoi - The progress of site clearance for a 6.7km long, 120-180m wide road is being accelerated by the locality according to the city's direction.

The investment project to build the Thang Long Avenue expressway, the section connecting National Highway 21 to the Hanoi - Hoa Binh expressway, started in October 2023.

The project has a total investment of 5,249 billion VND, invested by the Hanoi Civil Works Construction Investment Project Management Board. The city plans to complete a 6.7km long road with a cross-section of 120-180m in 2026.

According to the assessment of the Hanoi People's Committee, the project implementation will gradually complete the entire Hanoi - Hoa Binh expressway; develop and expand Hanoi Capital to the West, meeting the increasing transportation demand; and be a driving force for the development of Hoa Lac satellite city and the Western satellite city chain.

Hoa Lac Commune People's Committee said that the project to build the Thang Long Avenue expressway, the section connecting National Highway 21 to the Hanoi - Hoa Binh expressway through the commune, has a total of 688 land plots to be recovered, with a total area of about 60.56 ha.

In which, before the implementation of the 2-level local government model, site clearance work had been deployed and completed by all levels of government for 188 land plots.

From July 1, 2025, after implementing the 2-level local government model, the remaining 500 land plots of the project will be directly assigned by the City to Hoa Lac Commune People's Committee to organize site clearance work, with the required completion schedule before February 15, 2026.

This is a very large workload, urgent time, high requirements for progress and legality, requiring the synchronous and drastic involvement of the entire socio-political system.

a
Leaders of Hoa Lac commune regularly go to the field to inspect the current situation, direct the removal of obstacles; meet, propagate, mobilize, and dialogue with households in site clearance. Photo: TTĐT Hoa Lac commune

By January 29, Hoa Lac commune had completed 100% counting of all 500/500 allocated land plots, contributing to completing the counting of 688/688 plots of the entire project, clearly showing the spirit of responsibility, determination and drastic action of the commune Party Committee and government in performing the tasks assigned by the City.

In the process of implementation, many households have shown a high consensus spirit, proactively handing over the site before approving the compensation plan, with 6.63 ha/43 plots of 36 households, showing consensus and support for the policy of land recovery to serve the capital's key project.

In parallel with the inventory work, the commune's specialized agencies are urgently completing dossiers, publicizing plans, pricing, and paying compensation, support, and resettlement according to regulations, ensuring the progress of site clearance as required by the City.

SÓNG HỮU
RELATED NEWS

Land clearance for National Highway 6: Hanoi sets deadline to complete in 3 wards

|

Hanoi requests Yen Nghia, Duong Noi, and Kien Hung wards to complete site clearance for National Highway 6, Ba La - Xuan Mai section, in accordance with the progress commitment.

Long Bien accelerates site clearance for Tran Hung Dao bridge

|

Hanoi - Long Bien Ward strengthens dialogue and specific explanations so that people understand clearly, feel secure and agree to implement the site clearance of Tran Hung Dao bridge.

Iran publicly confirms Russia's major support amid war with US - Israel

|

Iranian Foreign Minister publicly talks about Russia's role for the first time as conflict with the US and Israel enters its second week.

Nghe An still has more than 1,700 billion VND of capital for national target programs to be disbursed

|

Nghe An - Provincial People's Committee reviews and urges disbursement of capital for national target programs for the period 2021 - 2025 extended to 2026.

Determining voting areas in elections

|

Each constituency has from 300 to 4,000 voters. The constituency has an administrative scope smaller than the constituency and is determined by constituency.

Workers calculate how to save travel costs when gasoline prices rise

|

Gasoline prices increased by more than 27 thousand VND/liter, causing travel costs for many workers to increase significantly.

Russia unexpectedly benefits from sharp oil price increase

|

In just the first week of the Iran war, Russia emerged as an "early winner", when it could take advantage of the economic and geopolitical consequences of the conflict.

From the Xoi Lac TV case, it is necessary to tighten the issue of sports copyright

|

According to analysis from experts, revenue from a pirated football website like Xoi Lac TV can reach over 10 billion VND/month, along with very high traffic.

Land clearance for National Highway 6: Hanoi sets deadline to complete in 3 wards

Minh Hạnh |

Hanoi requests Yen Nghia, Duong Noi, and Kien Hung wards to complete site clearance for National Highway 6, Ba La - Xuan Mai section, in accordance with the progress commitment.

Long Bien accelerates site clearance for Tran Hung Dao bridge

KHÁNH AN |

Hanoi - Long Bien Ward strengthens dialogue and specific explanations so that people understand clearly, feel secure and agree to implement the site clearance of Tran Hung Dao bridge.

Phường Thanh Xuân chưa hoàn thành giải phóng mặt bằng dự án đường Nguyễn Tuân

SÓNG HỮU |

Hà Nội - Dự án mở rộng đường Nguyễn Tuân (phường Thanh Xuân) đang vướng một nhà tập thể 2 tầng liên quan đến 6 hộ dân.