Progress of a series of dam projects in the northern border provinces

Việt Bắc |

A series of dams with a total investment of hundreds of billions of VND in Ha Giang and Cao Bang are currently in the final stage and will be put into operation in 2025.

After more than 2 years of construction, the water-up dam on the Lo River in Ha Giang City has entered the completion stage of the bridge arch span, one of the important items of the project.

Meanwhile, the foundation and body of the dam have been completed to a height of 105. In the coming time, construction will be carried out, with the installation of floodgates and equipment for lifting and lowering dams using a hydraulic cylinder system to regulate the water level of the Lo River.

It is currently the dry season, the low water level of the Lo River has created favorable conditions to speed up the project's progress. There are about 40 workers and many construction vehicles on duty at the project site.

Cong trinh dap dang nuoc tren song Lo tai TP Ha Giang. Anh: Viet Bac.
Water-up dam project on Lo River in Ha Giang City. Photo: Viet Bac.

According to the Ha Giang Province Construction Investment Project Management Board, the project's progress has been nearly 70%, striving to complete in 2025. The dam has been basically completed, and the arch bridge is currently under construction.

The dam project to create a landscape in the center of Ha Giang City started construction in February 2023 with a total investment of 330 billion VND. The project includes the construction of dams, management and operation bridges combined with traffic of more than 123 meters long, and approach roads at both ends of the bridge nearly 63 meters.

When completed, the project will help raise and maintain the water level of the Lo River. Climate regulation, ecological environment improvement, tourism development. The bridge on the dam will connect National Highway 2 with the southern beltway of the city.

In Cao Bang province, the dam on the Bang River through Cao Bang city with a total investment of more than 150 billion VND is also entering the completion stage.

Recorded at the end of March 2025, 3 out of 4 main pillars of the dam have been constructed, forming floodgates. The dam dam dam roof and related items are expected to be constructed in April. The construction volume of the project is currently over 80%.

Dap dang nuoc tren song Bang, TP Cao Bang du kien hoan thanh dip 30.4.2025. Anh: Tan Van.
The dam on the Bang River, Cao Bang City is expected to be completed on April 30, 2025. Photo: Tan Van.

Talking to reporters, Mr. Nguyen The Hoan - Chairman of Cao Bang City People's Committee - said: "The city has just had a direct meeting at the project site with all contractors to speed up the progress and ensure the quality of the project. Strive to complete the project on April 30 this year".

In addition to setting a goal of completing the project soon, Cao Bang city is continuing to develop a project to manage and exploit experiential tourism on the river after the dam is completed.

The dam on the Bang River through Cao Bang City was started in mid-2024. The project has a steel valve structure with about 3 compartments, which will help keep the water level stable for the Bang River, provide water for daily life, production and create a landscape for tourism development.

Việt Bắc
TIN LIÊN QUAN

Revealing the rate of Russian people's trust in Mr. Putin

|

Russian President Vladimir Putin has received the unwavering trust of the Russian people in the midst of turmoil.

Current status of the largest cemetery in Ho Chi Minh City about to build a school

|

Ho Chi Minh City - Binh Tan District will start construction of Tran Dai Nghia Primary School in the area of Binh Hung Hoa cemetery relocation phase 1 in April 2025.

Mr. Pham Quang Linh is a member of the Central Committee of the Vietnam Fatherland Front

|

The Standing Committee of the Central Committee of the Vietnam Fatherland Front issued a Decision on the dismissal of Mr. Pham Quang Linh from the Central Committee of the Vietnam Fatherland Front.

Hanoi prepares to fence off Dong Kinh - Nghia Thuc Square

|

Hanoi - On April 4, the Hanoi Department of Construction announced the pilot adjustment of traffic organization in the Dong Kinh - Nghia Thuc Square area (Hoan Kiem district).

Comrade Do Van Chien attends the 70th anniversary of the founding of the Vietnam Lawyers Association

|

On April 4, the Vietnam Lawyers Association solemnly held a ceremony to celebrate the 70th anniversary of its founding (April 4, 1955 - April 4, 2025).

Hà Nội nghiên cứu xây đập dâng trên sông Tô Lịch

KHÁNH AN |

Chủ tịch UBND TP Hà Nội giao Sở Xây dựng nghiên cứu phương án xây dựng đập dâng trên sông Tô Lịch để đồng bộ với dự án bổ cập nước từ sông Hồng.

Loạt tỉnh biên giới chi hàng trăm tỉ chặn sông xây đập dâng nước

Nhóm PV |

Điện Biên, Hà GiangCao Bằng đã quyết định chi hàng trăm tỉ đồng chặn dòng sông xây dựng đập dâng giữ nước tạo cảnh quan cho các thành phố.

Đập dâng 1.500 tỉ đồng ở Quảng Ngãi có nguy cơ “đắp chiếu”

VIÊN NGUYỄN |

Dự án đập dâng hạ lưu sông Trà Khúc ở Quảng Ngãi sau nhiều năm chậm tiến độ, lại đứng trước nguy cơ “đắp chiếu” vì phải đợi dự án hệ thống thu gom xử lý nước thải tập trung TP Quảng Ngãi hoàn thành, thì đập dâng mới phát huy công năng. Tuy nhiên, hiện dự án hệ thống thu gom xử lý nước thải tập trung TP Quảng Ngãi với tổng vốn đầu tư 1.000 tỉ đồng đang nằm trên… giấy, thậm chí còn chưa thông qua được bảng thiết kế.