Finding solutions to resolve basic construction debt in Quang Binh

CÔNG SÁNG |

Basic construction debt in Ba Don town (Quang Binh province) is more than 318 billion VND, localities are reporting to find payment solutions when the merger of communes and the removal of district levels is approaching.

According to Lao Dong Newspaper, in Quang Tan commune, one of the localities in Quang Binh province, the situation of basic construction debt is causing difficulties in infrastructure development. The commune's Multi-purpose Gymnasium project currently owes about 2.5 billion VND. This is just one of the projects that are undergoing basic construction in this locality.

According to Mr. Phan Thanh Tam, Chairman of the People's Committee of Quang Tan commune, the total amount of basic construction debt in the area is currently over 12 billion VND, with about 30 projects under construction. More than half of these projects are under construction, affecting the completion and handover progress. In particular, the Multi-purpose Gymnasium project, although largely completed, still owes a large sum of money.

Among the unpaid projects, there are some completed projects that have not been able to fully repay the debt such as the commune's kindergarten (although this project has been completed and put into use, there is still a debt of more than 1 billion VND). These debts are mainly due to the commune budget not being enough to pay.

To solve the problem of basic construction debt, one of the proposed options is to conduct land auctions. However, according to Mr. Tam, due to the administrative merger situation, the current bidding implementation cannot be implemented, leading to delays in resolving these debts.

The commune's current budget mainly relies on support from superiors, but there is no significant additional revenue. Local tax revenue each year is not enough to meet regular spending needs, causing the commune to not be able to use the budget for basic construction but only focus on paying small debts related to works such as flower gardens, ornamental plants, lighting equipment, maintaining clean and beautiful green landscapes, as well as supporting the construction of new rural models.

The commune has reported in detail and fully to the People's Committee of the town and the District Finance Department according to the prescribed form.

Mr. Dinh Thieu Son - Chairman of Ba Don Town People's Committee - said that the outstanding debt for basic construction in the town is currently over 318 billion VND. Of which, the capital from the provincial budget is more than 5.8 billion VND, the town budget is more than 94.8 billion VND, and the commune and ward budget is more than 217 billion VND. The town is currently focusing only on debt repayment, ensuring the completion of public investment projects by 2025.

Mr. Son also shared that the town is not currently starting a new project but is only focusing on repaying debts to ensure the progress of public investment completion. Currently, basic construction debt is still within the allowable threshold. The town has collected full information and reported to the Department of Finance to be able to continue to repay debts after the district-level government no longer exists, ensuring financial stability in the future.

CÔNG SÁNG
TIN LIÊN QUAN

A locality in Quang Binh owes hundreds of billions of VND in basic construction

|

Quang Binh - Before removing the district level, Ba Don town focused on paying off debts to build old projects, not starting new ones.

Cars and motorbikes stalled in series after heavy rain in Lang Son

|

Lang Son - Prolonged heavy rain caused many central streets to be deeply flooded, many vehicles stalled.

Questions about the fate of the Beautiful brothers, sisters, and children

|

The success of Anh trai say hi, Call Me by Fire has created miracles, including the explosion of concerts attracting tens of thousands of audiences.

A locality in Quang Binh owes hundreds of billions of VND in basic construction

CÔNG SÁNG - NGUYỄN LUÂN |

Quang Binh - Before removing the district level, Ba Don town focused on paying off debts to build old projects, not starting new ones.

Kiểm toán Nhà nước chỉ ra nhiều bất cập trong quản lý nợ đọng xây dựng cơ bản ở Thanh Hóa

Xuân Hùng |

Trong kết quả báo cáo kiểm toán gần đây, Kiểm toán Nhà nước (KTNN) đã chỉ ra hàng loạt hạn chế, vi phạm trong công tác quản lý nợ đọng xây dựng cơ bản trên địa bàn tỉnh Thanh Hóa.

Giải ngân vốn xây dựng cơ bản thấp, Bí thư Bạc Liêu chỉ đạo nóng

NHẬT HỒ |

Bạc Liêu - Tổng nguồn vốn toàn tỉnh đã giải ngân đạt gần 1.367 tỉ đồng bằng 35,04% so kế hoạch vốn đã phân bổ. Trước tình trạng này, Bí thư Tỉnh ủy Bạc Liêu đề nghị cắt nhà thầu làm ăn không đàng hoàng, chủ đầu tư phải chịu trách nhiệm nếu để kéo dài, không thể để tình trạng công trình dây dưa, làm mãi không xong.

Tập trung thanh tra các lĩnh vực đầu tư, đất đai, xây dựng cơ bản

PHẠM ĐÔNG |

Quốc hội đề nghị các cơ quan có liên quan tăng cường công tác thanh tra, kiểm tra, kiểm toán, điều tra, truy tố, xét xử. Tập trung vào các lĩnh vực: đầu tư, tài chính, tài sản, đất đai, xây dựng cơ bản thông qua đấu thầu, đấu giá.