Positive signals about land acquisition and site clearance for Ring Road 2.5

SÓNG HỮU |

Hanoi - 2 sections of Ring Road 2.5 through Cau Giay ward recorded many positive results in land acquisition and site clearance.

Cau Giay Ward People's Committee (Hanoi) has just announced the progress of land acquisition and site clearance for the Ring Road 2.5 project, the section from Cau Giay Street to Dich Vong New Urban Area and the section from Dich Vong New Urban Area to Duong Dinh Nghe Street.

The section from Cau Giay street to Dich Vong New Urban Area is 420m long with a land area to be cleared of 21,459.7m2 (land acquisition from 329 households and 9 organizations with a total of 338 compensation and support plans).

The section from Dich Vong - Duong Dinh Nghe New Urban Area has a length of 710m with a total land area to be cleared of about 30,520m2 (land is recovered from 123 organizations, households, individuals and 359 graves must be relocated).

Up to now, site clearance work in the ward has achieved many positive results.

The section from Cau Giay street - Dich Vong New Urban Area basically completed site clearance, approved, and received and handed over 337/338 sites, reaching a rate of 99.7% of the volume.

The section from Dich Vong - Duong Dinh Nghe New Urban Area is implemented according to the Emergency Construction Order of the Hanoi City People's Committee.

The ward has mobilized the entire political system to participate; drastically and synchronously implemented many solutions to implement with the motto "going to each alley, knocking on each house"; "working without days off, without office hours".

In 3 months from the date of the urgent order, along with the sharing of families with graves in need of relocation and the companionship, listening to all opinions and aspirations of the people and promptly having solutions to remove obstacles, Cau Giay ward has completed the entire relocation of 359 graves (completed 7 days before the City Party Committee's direction); completed and handed over 24,656m2 of land (about 81% of the area to be cleared of the project) to the Hanoi Traffic Construction Investment Project Management Board (the investor) to deploy commencement and construction.

Currently, there is still 19% of the volume to be implemented (about 123 plans with an area of 5,864m2 of land), the ward has completed all investigation and measurement work, and is urgently implementing site clearance steps according to regulations.

The Party Committee and government of Cau Giay ward continue to focus on directing and implementing the removal of difficulties and obstacles, determined to complete the project site clearance work in accordance with the direction of the City Party Committee and the City People's Committee, ensuring legitimate rights and interests and the consensus of the people.

SÓNG HỮU
RELATED NEWS

Hanoi recovers about 96,500m2 of land to build Ring Road 2.5

|

Hanoi - About 96,500m2 of land in Cau Giay, Yen Hoa and Thanh Xuan wards will be recovered for the construction of 3 sections of Ring Road 2.5.

Hanoi starts construction of the last pieces of Ring Road 2.5

|

Hanoi - 3 sections of Ring Road 2.5 with a length of 2.26km started construction this morning with a total investment of about 8,402 billion VND, expected to be completed in 2026.

Tomorrow, Hanoi starts construction of 3 sections of Ring Road 2.5, 40-50m wide

|

Hanoi - 3 sections of Ring Road 2.5 with a total length of about 2.26km, cross-section 40-50m will be started tomorrow (March 20).

For the first time, National Assembly deputies have representatives of the O Du ethnic group, born in 2002

|

For the first time, National Assembly deputies have representatives of the O Du ethnic group, one of the smallest ethnic groups in Vietnam.

Japan women's team wins 2026 Women's Asian Cup

|

On the evening of March 21, the Japanese women's team won the 2026 Women's Asian Cup championship after defeating the Australian women's team in the final.

Entangled with 19 households, Hang Bang canal in Ho Chi Minh City missed the finish line

|

Ho Chi Minh City - Hang Bang canal cannot be completed due to 19 households, causing the unfinished renovation appearance, people regret and hope to soon reach the finish line synchronously.

Wage policy is more realistic thanks to surveying workers' living standards

|

Experts believe that investigating workers' living standards will create real data, helping wage policies to be closer to workers' lives.

Iran's largest nuclear facility attacked by the US and Israel

|

Iran's Natanz nuclear facility attacked by the US and Israel on March 21.

Hanoi recovers about 96,500m2 of land to build Ring Road 2.5

HỮU CHÁNH |

Hanoi - About 96,500m2 of land in Cau Giay, Yen Hoa and Thanh Xuan wards will be recovered for the construction of 3 sections of Ring Road 2.5.

Hanoi starts construction of the last pieces of Ring Road 2.5

HỮU CHÁNH |

Hanoi - 3 sections of Ring Road 2.5 with a length of 2.26km started construction this morning with a total investment of about 8,402 billion VND, expected to be completed in 2026.

Tomorrow, Hanoi starts construction of 3 sections of Ring Road 2.5, 40-50m wide

SÓNG HỮU |

Hanoi - 3 sections of Ring Road 2.5 with a total length of about 2.26km, cross-section 40-50m will be started tomorrow (March 20).