Panorama of the 800 billion VND underpass that will open to traffic at the end of December

Anh Tú |

HCMC - The HC1 tunnel branch of the Nguyen Van Linh - Nguyen Huu Tho intersection underpass project has reached 85% progress and is expected to be completed and open to traffic on December 31.

According to Mr. Luong Minh Phuc, Director of the HCM City Traffic Construction Investment Project Management Board (Traffic Board), construction package No. 1 (HC1) of the Nguyen Van Linh - Nguyen Huu Tho intersection underpass project is very close to completion. The HC1 underpass branch (from Binh Chanh district to District 7) is expected to open to traffic on December 31, 2024.

a
From above, the HC1 underpass branch has been basically completed. Photo: Anh Tu

"Construction Package No. 1, the construction of the HC1 underpass, has so far completed 85% of the work. The contractor has completed the temporary road; cut down and relocated affected trees within the project area and organized traffic to serve the construction; at the same time, completed the structure of the open tunnel segments and closed tunnel segments. It is expected that the entire work volume will be completed and the tunnel will be opened to traffic on December 31," said Mr. Phuc.

  Hien tai phan ket cau ham chui da co ban hoan thanh xong. Ảnh: Anh Tu
Currently, the tunnel structure has been basically completed. Photo: Anh Tu

According to reporters, at the construction site there are more than 120 officers, engineers, workers, and dozens of types of machinery urgently working day and night with 3 shifts and 4 teams to speed up progress.

a
At the construction site, hundreds of engineers and workers are working hard even though it is the weekend. Photo: Anh Tu
a
In parallel with the construction of the underpass, the contractor is re-establishing the ground level above the tunnel so that the project can be completed on schedule.

Previously, construction package No. 2, construction of HC2 underpass, was completed and put into use from October 2024.

In order for the entire Nguyen Van Linh - Nguyen Huu Tho underpass project to be completed on schedule, the Traffic Committee recommends that the Ho Chi Minh City Department of Transport consider approving the traffic organization plan and granting construction permits. At the same time, inspect and accept the remaining items to open the HC1 underpass branch to traffic and put the entire Nguyen Van Linh - Nguyen Huu Tho intersection underpass project into service of the people by December 31, 2024.

The Traffic Committee also recommended that the Department of Industry and Trade, Ho Chi Minh City Power Corporation, Ho Chi Minh City Power Distribution Project Management Board, and Tan Thuan Power Company urgently speed up the construction of a transformer station (capacity equivalent to 400kVA) to ensure a stable and long-term power supply to serve the operation of the project's pumping station, lighting, and camera systems.

Truoc do nhanh ham HC2 () cung da hoan thanh va thong xe. Ảnh: Anh Tu
Previously, the HC2 tunnel branch (from District 7 to Binh Chanh) was also completed and opened to traffic. Photo: Anh Tu

The Nguyen Van Linh - Nguyen Huu Tho underpass project is invested by the Ho Chi Minh City Traffic Construction Investment Management Board, with a total investment of 830 billion VND.

The project includes two tunnels in each direction of Nguyen Van Linh Street, each tunnel is 456 m long, has three lanes, and a speed of 60 km/h. In addition, the project also builds a pumping station and drainage system for the tunnel, a lighting system, traffic organization, and a number of other technical infrastructure works...

Once completed and put into operation, the project will help reduce traffic congestion at the southern gateway intersection of Ho Chi Minh City. At the same time, it will create ventilation for the main road connecting the center of Ho Chi Minh City with Nha Be district and Hiep Phuoc port.

Anh Tú
RELATED NEWS

8 years have passed since the construction of the underpass at the eastern gateway of Ho Chi Minh City was completed

|

HCMC - Construction began in 2016 on the underpass at Station 2 intersection on Hanoi Highway, from HCMC to Dong Nai, but has yet to be completed due to land acquisition issues.

Ho Chi Minh City opens important underpass in District 7, bans motorbikes

|

HCMC - On the morning of October 4, the Nguyen Van Linh - Nguyen Huu Tho tunnel branch (from District 7 to Binh Chanh) opened to traffic, only allowing cars to pass, banning motorbikes and pedestrians.

Woman spends nearly half her life clinging to the soul of Kinh Bac folk songs

|

For the past 35 years, a woman in Tu Son has persistently sung a response song, nurturing the aspiration to preserve and pass on the heritage of folk songs of her homeland.

Ho Chi Minh City starts construction of 4 key projects on April 30th

|

Ho Chi Minh City - Ben Thanh - Thu Thiem Metro, New Political - Administrative Center, Cai Mep Ha port and International University Urban Area will start construction on April 30 this year.

The opening night of Tran Temple festival in Hung Yen attracted thousands of people and tourists

|

Hung Yen - On the evening of March 1st, in Long Hung commune, the opening ceremony of the Tran Temple Festival took place solemnly and bustlingly, attracting a large number of people and tourists from all over.

Tien Linh continues to be silent, Ho Chi Minh City Police loses minimally to Becamex Ho Chi Minh City

|

On the evening of March 1st, Ho Chi Minh City Police Club suffered a 0-1 defeat to Becamex TPHCM in round 13 of LPBank V.League 2025-2026 on Tien Linh's lackluster day.

Live Football Man United vs Crystal Palace in Premier League

|

Live football match Man United - Crystal Palace in round 28 of the Premier League, taking place at 9:00 PM on March 1st (Vietnam time).

Iran launches missile hitting a series of Dubai's iconic buildings

|

A series of missiles and drones from Iran attacked Dubai, causing fires at the most luxurious economic and tourist symbols in the country.

8 years have passed since the construction of the underpass at the eastern gateway of Ho Chi Minh City was completed

MINH QUÂN |

HCMC - Construction began in 2016 on the underpass at Station 2 intersection on Hanoi Highway, from HCMC to Dong Nai, but has yet to be completed due to land acquisition issues.

Ho Chi Minh City opens important underpass in District 7, bans motorbikes

MINH QUÂN |

HCMC - On the morning of October 4, the Nguyen Van Linh - Nguyen Huu Tho tunnel branch (from District 7 to Binh Chanh) opened to traffic, only allowing cars to pass, banning motorbikes and pedestrians.