Ho Chi Minh City sprints to disburse public investment

MINH QUÂN |

In the context of slow disbursement of public investment capital in the first 8 months of 2024, Ho Chi Minh City is having to speed up to achieve the target of 95% of public investment capital being disbursed by the end of the year.

Slow disbursement

According to a report by the Ho Chi Minh City People's Committee, by the end of August, the city's total public investment capital had only reached VND14,381 billion, equivalent to 18% of the total allocated capital of VND79,200 billion.

Mr. Tran Quang Lam - Director of the Ho Chi Minh City Department of Transport - said that although the city's leaders have regularly met to resolve problems, the disbursement progress has not had many positive changes.

Many units were warned for the 4th time.

Recently, the Chairman of the Ho Chi Minh City People's Committee issued a document reminding many departments, branches, districts and project management units when there were up to 60 petitions related to public investment projects that had expired but had not been processed. Notably, some units continued to be reminded for the third and fourth times because there was still no progress or response after the previous reminders. In particular, the Department of Finance and the Department of Transport along with the People's Committee of District 6 were reminded for the fourth time.

One of the main reasons for the slow disbursement is the adjustment of the 2024 Land Law, which will take effect from August 1, 2024, along with new regulations on how to calculate compensation prices. These changes require projects to adjust their compensation plans, causing delays. A typical example is the project to renovate the North bank of the Doi Canal (District 8), where the resettlement compensation for more than 1,600 households increased from VND 3,583 billion to more than VND 6,000 billion when applying the new land price.

In addition, some projects with large investment capital in Ho Chi Minh City are facing procedural problems and are in the process of coordinating with central ministries and branches to resolve them, so the allocated capital cannot be immediately disbursed, such as: Project to solve flooding caused by tides in Ho Chi Minh City area taking into account climate change factors (phase 1) with a disbursement plan of 6,800 billion VND; Metro project No. 1 (Ben Thanh - Suoi Tien) with a total disbursement capital of 3,717 billion VND...

According to the Ho Chi Minh City Department of Planning and Investment, about VND15,899 billion in public investment capital is unlikely to be disbursed in 2024 due to planning and procedural problems.

Sprint together

Mr. Luong Minh Phuc - Director of the HCM City Traffic Construction Investment Management Board - said that the board has been assigned VND12,380 billion but has only disbursed VND2,150 billion (20%). In the remaining months, the board will have to disburse an additional VND9,930 billion, including VND2,000 billion for site clearance, VND700 billion for newly started projects, VND300 billion in ODA capital, etc.

“These funds will be disbursed in the third and fourth quarters and the board is determined to maintain the disbursement target above 95%,” said Mr. Phuc.

Among the solutions, Mr. Phuc said that he is continuing to speed up the construction and installation group. In particular, the Ho Chi Minh City Ring Road 3 project (about 3,000 billion VND in construction and installation) will receive the first sand package from the West this week. Other large projects are also implementing construction in 3 shifts and 4 teams to ensure progress.

Mr. Phuc also called on localities to quickly hand over the land for important projects such as Tan Binh district (Tran Quoc Hoan road land worth 390 billion VND), District 4 (Nguyen Khoi bridge and road project worth more than 700 billion VND), Binh Chanh district (National Highway 50 expansion project)... These land areas all need to be handed over in September, if they are delayed, it will be too late.

To achieve a disbursement rate of at least 95%, Ho Chi Minh City is implementing many flexible solutions such as transferring capital from slow-disbursing projects to high-disbursing projects. For projects waiting for relevant ministries, branches and agencies to resolve problems, the city will temporarily transfer capital from these projects to arrange for other projects that can be disbursed immediately.

The city continues to shorten the time for handling procedures for public investment projects by 30%; tighten discipline in disbursing public investment capital; and resolutely and strictly handle cases of delay.

According to Mr. Bui Thanh Tan - Director of the HCM City Urban Infrastructure Construction Investment Project Management Board, the board was assigned more than VND 12,400 billion, of which VND 8,400 billion was for site clearance. However, the board has only disbursed VND 920 billion (7.4%).

MINH QUÂN
TIN LIÊN QUAN

5 cơ quan giải ngân vốn đầu tư công rất thấp

PHẠM ĐÔNG |

Bộ Tài chính cho biết, có 8 cơ quan giải ngân vốn đầu tư công trên mức bình quân của cả nước, 16 cơ quan giải ngân thấp, 5 cơ quan giải ngân rất thấp.

Kiên Giang kéo dài giải ngân kế hoạch đầu tư công

NGUYÊN ANH |

Kéo dài thời gian thực hiện và giải ngân kế hoạch đầu tư công nguồn vốn ngân sách địa phương năm 2023 sang năm 2024 cho 77 dự án, với số tiền hơn 87 tỉ đồng.

Hải Dương mới giải ngân được 2.025 tỉ đồng vốn đầu tư công

Hoàng Khôi |

Ngày 21.8, UBND tỉnh Hải Dương vừa tổ chức cuộc họp tháng 8 (lần 7) để xem xét, giải quyết các nội dung, tờ trình.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Nguyên chủ tịch xã ở Thái Bình bị tố lạm quyền để trục lợi

TRUNG DU |

Thái Bình - Nguyên Chủ tịch UBND xã Quỳnh Hải, huyện Quỳnh Phụ bị tố lợi dụng chức vụ quyền hạn để tư lợi, trục lợi cho bản thân, gia đình.

5 agencies with very low public investment disbursement

PHẠM ĐÔNG |

The Ministry of Finance said that there are 8 agencies that disburse public investment capital above the national average, 16 agencies that disburse low capital, and 5 agencies that disburse very low capital.

Kien Giang extends disbursement of public investment plan

NGUYÊN ANH |

Extend the implementation time and disbursement of the public investment plan from the local budget in 2023 to 2024 for 77 projects, with an amount of more than 87 billion VND.

Hai Duong has just disbursed 2,025 billion VND of public investment capital

Hoàng Khôi |

On August 21, Hai Duong Provincial People's Committee just held its August meeting (7th time) to review and resolve the contents and reports.