HCMC is about to start construction of 3 bridges worth nearly VND5,000 billion to relieve traffic jams

MINH QUÂN |

HCMC - Nguyen Khoi Bridge, Rach Tom Bridge and Ong Nhieu Bridge with a total investment of nearly VND5,000 billion are expected to start construction in the second or third quarter of 2025.

Nguyen Khoi Bridge and Road

Nguyen Khoi Bridge and Road is the most anticipated project because of its important role in connecting the South of Ho Chi Minh City with the center.

Currently, people from Nha Be area, District 7 want to move to the center, there are only two main roads: Nguyen Huu Tho - Kenh Te bridge and Huynh Tan Phat - Tan Thuan bridge - Nguyen Tat Thanh.

However, both routes are often overloaded, especially during rush hour, making the congestion serious.

The Nguyen Khoi Bridge and Road project was approved by the Ho Chi Minh City People's Council in 2016 with an initial investment capital of VND1,250 billion, later adjusted to more than VND2,800 billion due to expanding scale. However, due to lack of capital, the project was stalled for 7 years.

By the end of 2023, the Ho Chi Minh City People's Council approved an adjustment to the investment policy, raising the total to more than VND 3,700 billion from the city budget.

Khu vuc di qua cua du an cau duong Nguyen Khoai. Anh: Anh Tu
The area of the Nguyen Khoi bridge and road project. Photo: Anh Tu

The project is nearly 5 km long, including 2.5 km of bridge and 2.3 km of road, starting from D1 road (District 7), crossing Te canal and Ben Nghe canal, connecting to Vo Van Kiet Avenue (District 1). In addition to the main route, the project also has branches connecting Tran Xuan Soan, Ton That Thuyet and Vo Van Kiet.

District 4 People's Committee is speeding up compensation work, expected to reclaim 1.7 hectares of land, affecting 148 cases with a budget of more than 1,000 billion VND.

The Ho Chi Minh City Traffic Construction Investment Project Management Board is completing technical procedures and selecting contractors to start the project in September 2025, and complete it in 2027.

Rach Tom Bridge

Rach Tom Bridge is located on Le Van Luong Street (Nha Be District), an iron bridge built before 1975. After nearly half a century, the bridge has seriously degraded but still has to "carry" a large volume of traffic.

Cau Rach Tom (huyen Nha Be) tuy da xuong cap nhung van co xe tai chay qua. Anh: Anh T
Rach Tom Bridge (Nha Be District) is degraded but still has trucks passing through. Photo: Anh Tu

The project to build the new Rach Tom bridge was approved in 2019 with a total investment of nearly 497 billion VND. The project is more than 683 m long, of which the bridge is 171 m long and 15 m wide; the approach road is 512 m long and 29 m wide. However, due to lack of capital, the project cannot be implemented.

By the end of 2024, the Ho Chi Minh City People's Council had approved the policy of reclaiming 3.1 hectares of land to serve the project. Currently, preparations are being urgently completed to start construction in 2025.

If there are no obstacles, Rach Tom Bridge will be completed and put into operation in 2026, contributing to changing the appearance of traffic on the Le Van Luong axis - one of the main arteries in the South of Ho Chi Minh City.

Ong Nhieu Bridge

The Ong Nhieu Bridge project is located on Nguyen Duy Trinh Street, across Ong Nhieu Canal (Thu Duc City), connecting Phu Huu and Long Truong Wards.

Cau Ong Nhieu hien huu tren duong Nguyen Duy Trinh (TP Thu Duc).  Anh: Anh Tu
Ong Nhieu Bridge exists on Nguyen Duy Trinh Street (Thu Duc City). Photo: Anh Tu

The project started in December 2017 with an initial investment capital of 425 billion VND. The bridge has a total length of 725 m and a width of nearly 20 m.

However, after only 1.5% of the construction volume was completed, the project was "suspended" due to land clearance problems.

By July 2022, the total investment was adjusted to increase to more than 763 billion VND due to increased compensation, site clearance and relocation of technical infrastructure costs.

The Thu Duc City People's Committee is urgently implementing compensation and resettlement support to hand over the site to the construction unit.

When completed, Ong Nhieu Bridge will increase the clearance of the waterway, meet the needs of water transportation and synchronize the load on Nguyen Duy Trinh Street, connect Ho Chi Minh City with Phu Huu Industrial Park and Ho Chi Minh City - Long Thanh - Dau Giay Expressway.

MINH QUÂN
TIN LIÊN QUAN

Starting construction of a project worth over 17,000 billion VND to renovate the most polluted canal in Ho Chi Minh City on May 10

|

HCMC - After many missed deadlines, the Xuyen Tam canal renovation project - one of the most polluted canals in the city - will officially start construction on May 10.

HCMC finalizes the opening of the 341 billion VND underpass at An Phu intersection after many delays

|

HCMC - The 341 billion VND underpass at An Phu intersection (Thu Duc City) will be moved to June 30, 2025, after not being completed in time for the April 30 holiday.

Strengthening decentralization and delegation of authority in planning and investment

|

The draft Law amending and supplementing a number of articles of the Planning Law has many new points, including strengthening decentralization and delegation of authority in state management of planning.

Breaking down the surrounding wall, reopening the path for families of meritorious people in Ninh Binh

|

Ninh Binh - On the morning of May 9, the People's Committee of Ninh An commune mobilized machinery and human resources to demolish the surrounding wall, reopening the path for Mr. Vu Quoc Dang's family.

Journalist Truong Anh Ngoc commented on the Champions League final between PSG and Inter Milan

|

In the Sports Perspective program No. 214, journalist Truong Anh Ngoc commented on the hot spots in the Champions League final between Inter Milan and PSG.

Resolutely declaration of the President of Ukraine before the Victory Day parade

|

Right before the parade to celebrate the 80th anniversary of the P combatively victorious day, Ukrainian President Volodymyr Zelensky suddenly declared his readiness to immediately cease unconditional fighting.

Man United meet Tottenham in Europa League final

|

Man United and Tottenham will meet in the 2024-2025 Europa League final.

World gold price lost momentum, fell to nearly 3,300 USD/ounce

|

World gold prices fell sharply last night, down to $3,304.9/ounce due to US employment data positively exceeding expectations and the Bank of England cutting interest rates.

Starting construction of a project worth over 17,000 billion VND to renovate the most polluted canal in Ho Chi Minh City on May 10

MINH QUÂN |

HCMC - After many missed deadlines, the Xuyen Tam canal renovation project - one of the most polluted canals in the city - will officially start construction on May 10.

HCMC finalizes the opening of the 341 billion VND underpass at An Phu intersection after many delays

MINH QUÂN |

HCMC - The 341 billion VND underpass at An Phu intersection (Thu Duc City) will be moved to June 30, 2025, after not being completed in time for the April 30 holiday.

Cầu Nguyễn Khoái 3.700 tỉ "kẹt" quy hoạch, nguy cơ trễ hẹn

MINH QUÂN |

TPHCM - Dự án cầu đường Nguyễn Khoái hơn 3.700 tỉ đồng, nối Quận 7, 4 và 1, đang gặp khó do chậm trễ điều chỉnh quy hoạch và giải phóng mặt bằng.