Starting construction of a project worth over 17,000 billion VND to renovate the most polluted canal in Ho Chi Minh City on May 10

MINH QUÂN |

HCMC - After many missed deadlines, the Xuyen Tam canal renovation project - one of the most polluted canals in the city - will officially start construction on May 10.

On May 8, according to information from the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board (investor), the groundbreaking ceremony for the Xuyen Tam canal renovation project will take place on the morning of May 10 with the XL-03 construction package (section through Go Vap district).

This package includes a section from Luong Ngoc Quyen Street to Vam Thuat River, about 1.4 km long, with a total investment of about 597 billion VND.

Quan Go Vap da giai phong mat bang cho du an cai tao rach Xuyen Tam. Anh: Anh Tu
Go Vap District has cleared land for the Xuyen Tam canal renovation project. Photo: Anh Tu

Initially, the XL-03 package was scheduled to start construction in August 2024, then postponed to November 2024 and continued to be postponed to April 19, 2025. However, for many reasons, the plan continued to be delayed until now to finalize the start date.

In addition to the XL-03 package, the project also has two other construction packages in Binh Thanh District including: XL-01 package (renovation of the section from Nhieu Loc - Thi Nghe canal to Bui Dinh Tuy bridge) and XL-02 package (renovation of the section from Bui Dinh Tuy bridge to Luong Ngoc Quyen street, including the branches of Binh Loi, Binh Trieu canals and Son bridge canals).

It is expected that these two packages will start construction on the occasion of National Day, September 2, 2025.

Rach Xuyen Tam hien nay. Anh: Minh Quan
Xuyen Tam Canal today. Photo: Minh Quan

Xuyen Tam Canal has a total length of nearly 9 km, flowing through Binh Thanh and Go Vap districts. Of which, the main canal is 6.7 km long, connecting from Nhieu Loc - Thi Nghe canal to Vam Thuat river; the remaining three branch lines are about 2.2 km long.

The Xuyen Tam canal renovation project is expected to solve the pollution problem that has lasted for many years, seriously affecting the lives of thousands of households on both banks.

After the Ho Chi Minh City People's Council approved the investment policy in October 2023, the project initially had a total capital of more than 9,664 billion VND, of which compensation, support and resettlement costs accounted for nearly VND 6,400 billion.

However, by September 2024, the Ho Chi Minh City People's Council had adjusted the total investment to more than 17,200 billion VND - an increase of more than 7,500 billion VND, mainly to serve site clearance.

The total area of recovered land according to the new adjustment is 197,349 m2, affecting 2,215 cases - an increase of more than 330 cases compared to the original plan.

This adjustment comes from the application of new regulations in the 2024 Land Law and the 2023 Housing Law, causing compensation, support and resettlement costs to increase sharply, to more than 14,000 billion VND.

2.215 truong hop bi anh huong boi du an rach Xuyen Tam. Anh: Anh Tu
2,215 cases are affected by the Xuyen Tam canal project. Photo: Anh Tu

In Go Vap district, the project affects 138 cases, including 137 households and Van Lang University; of which, 40 households were completely cleared, 98 households were partially cleared.

In Binh Thanh District, there are up to 2,077 cases of land acquisition, including 1,230 households and 23 organizations that were completely cleared; the remaining 824 cases were partially cleared.

The project includes items: dredging a canal bed 3.5 m deep, widening the canal surface by 20-30 m, building a synchronous wastewater - rainwater collection system to improve the environment and prevent pollution.

On both sides of the canal, there will be a 6 m wide road with two lanes on each side, a 3-4 m wide sidewalk, a complete park system, trees and lighting.

Phoi canh rach Xuyen Tam sau khi duoc cai tao. Anh: Ban Ha tang do thi TPHCM
Perspective of Xuyen Tam canal after being renovated. Photo: Ho Chi Minh City Urban Infrastructure Board

The Xuyen Tam canal renovation project is expected to not only contribute to improving living conditions for thousands of households, but also create ecological space, green - clean - beautiful urban landscape in the heart of the city. The entire project is expected to be completed in 2028.

MINH QUÂN
RELATED NEWS

Relocating a series of houses along the canal in Ho Chi Minh City to do more than 17,200 billion VND project

|

Ho Chi Minh City - Many households have houses along the canal, Xuyen Tam canal, in Go Vap district, have dismantled houses, handing over the ground, preparing to start the project to renovate the canal.

Evacuation of 1,270 households in Binh Thanh and Go Vap, where will they be resettled?

|

HCMC - 1,270 households completely cleared in Binh Thanh and Go Vap districts to renovate Xuyen Tam canal will be resettled in many different locations.

The 17,000 billion VND project to renovate the most polluted canal in Ho Chi Minh City is delayed

|

HCMC - The project to renovate Xuyen Tam Canal - the most polluted canal in the city, is expected to start construction in November 2024 but is delayed because the site has not been handed over yet.

Fire at Safira Khang Dien apartment building, residents flee

|

Ho Chi Minh City - In the afternoon of May 19, a fire suddenly broke out in the 7th floor apartment building of Safira Khang Dien apartment building (Ho Chi Minh City), causing many residents to panic and flee.

Bringing studying and following Uncle Ho among union members to become more and more substantive

|

Mr. Nguyen Anh Tuan - Member of the Party Central Committee, Vice Chairman of the Central Committee of the Vietnam Fatherland Front, Chairman of the Vietnam General Confederation of Labor proposed that, in the face of the requirements of the new situation, trade union levels need to continue to promote further, bringing the study and following of Uncle Ho among cadres, union members, and workers to become more and more substantive.

Northern region is about to have widespread heavy rain from tonight, warning of over 250mm in some places

|

The meteorological agency warns that the North, Thanh Hoa and Nghe An are about to welcome a widespread heavy rain; warning of the risk of flash floods and landslides, especially in mountainous areas.

Lack of support, stocks fall due to strong profit-taking pressure

|

Oil and gas and rubber stocks were sold for profit-taking in the afternoon session of May 19, causing the stock market to adjust sharply.

Relocating a series of houses along the canal in Ho Chi Minh City to do more than 17,200 billion VND project

NHƯ QUỲNH - NGỌC ÁNH |

Ho Chi Minh City - Many households have houses along the canal, Xuyen Tam canal, in Go Vap district, have dismantled houses, handing over the ground, preparing to start the project to renovate the canal.

Evacuation of 1,270 households in Binh Thanh and Go Vap, where will they be resettled?

MINH QUÂN |

HCMC - 1,270 households completely cleared in Binh Thanh and Go Vap districts to renovate Xuyen Tam canal will be resettled in many different locations.

The 17,000 billion VND project to renovate the most polluted canal in Ho Chi Minh City is delayed

MINH QUÂN |

HCMC - The project to renovate Xuyen Tam Canal - the most polluted canal in the city, is expected to start construction in November 2024 but is delayed because the site has not been handed over yet.