The project to restore and embellish the landscape infrastructure of the Hung Temple historical relic site has a total investment of 125 billion VND from the state budget; donations for the restoration and construction of the Hung Temple and other legally mobilized sources.
After the Hung Temple Historical Site approved the results of contractor selection for Package No. 10 of the project: Construction and equipment installation for the project items of the project to renovate and upgrade the landscape system in front of Gieng Temple, the contractor is carrying out construction of the items.
According to the reporter of Lao Dong Newspaper on the morning of January 24, the unit that won Package No. 10 of the project with a price of more than 19 billion VND - Tu Lap Construction Company Limited is implementing construction in the Den Gieng area.
It can be seen that the contractor has mobilized a lot of human resources and equipment to the area of the Gieng Temple Intersection, Lotus Ponds No. 1, No. 2, No. 3, No. 4, No. 5 and the infrastructure system in front of the Gieng Temple to renovate and upgrade the landscape.
Mr. Trieu Hoang Bien - a resident of Hy Cuong commune, Viet Tri city (near Hung Temple) - shared: "The area of Nga 5 Den Gieng is currently very beautiful because of the green landscape, many flowers and especially the relief of Uncle Ho talking to officers and soldiers of the Vanguard Army Corps which was inaugurated in early April last year. Hopefully, after the road to Den Gieng and the lotus ponds are completed, the landscape of the whole area will be even cleaner and more beautiful".
According to a leader of Tu Lap Construction Company, in order to ensure progress before the Hung Temple Festival, with a huge amount of remaining work and "stuck" during Tet holiday, the company's engineers and workers are having to work night shifts.
Some images recorded by reporters: