Nhon metro tunnel shell - Hanoi station weighs 4 tons/round

Tô Thế |

With a tunnel length of more than 4km, metro Nhon - Hanoi station needs 3,488 tunnel shells. Each tunnel shell weighs 4 tons.

To prepare conditions for the Nhon - Hanoi railway station tunnel boring machine to operate at the end of July 2024, the Hanoi Urban Railway Project Management Board (MRB) is increasing the transportation of tunnel lining concrete slabs. especially from the factory in Ha Nam to station S9 (Kim Ma, Hanoi).

Information from MRB, with a tunnel length of more than 4km, the project must produce 3,488 tunnel rounds. In terms of size, the tunnel shell is a universal type, consisting of 6 pieces with an inner diameter of 5.7m, an outer diameter of 6.3m, a ring width of 1.5m and a shell thickness of 0.3m, weighing 4 ton.

The tunnel shell is prefabricated at the factory, then transported to the project site to be placed in the chamber containing the TBM machines. When the TBM tunneling machine operates and digs up the soil, the tunnel lining will be completed.

The tunnel shell is produced at a factory in Ha Nam. Photo: Le Khanh
The tunnel shell is produced at a factory in Ha Nam. Photo: Le Khanh
Each tunnel shell weighs 4 tons. Photo: Le Khanh
Each tunnel shell weighs 4 tons. Photo: Le Khanh

According to the leader of the tunnel lining production unit, raw materials for production include: Cement, steel reinforcement, aggregates (stone, sand), water, additives and tunnel lining accessories.

After the preparation process, concrete is mixed by an automatic mixing plant according to the determined mixing ratio, then poured into reinforced molds, using vibration compaction techniques to remove air bubbles and Make sure the concrete is evenly distributed.

Next, the tunnel lining panels will be covered with closed chambers to perform steam curing work until the concrete of the tunnel lining panels reaches 60% of the prescribed compressive strength, in the range of 4 - 6 language.

Nhon metro tunnel shell - Hanoi station goes through many rigorous production stages. Photo: Le Khanh
Nhon metro tunnel shell - Hanoi station goes through many rigorous production stages. Photo: Le Khanh

"Completing the above stages, the tunnel shell panels will be moved to the water maintenance area within 7 days. Finally, the product will be moved to the storage area. Here, the product is painted with a protective layer. epoxy protection, marking each tunnel segment to serve installation and construction", the leader of the tunnel lining production unit shared.

It is known that to date, the factory has produced more than 800 rounds out of a total of 3,488 tunnel lining rounds of the project. From the night of July 19, the first tunnel shells were transported to Hanoi.

The tunnel shell began to be transferred from the manufacturing plant to the underground station in Hanoi. Photo: Century
The tunnel shell began to be transferred from the manufacturing plant to the underground station in Hanoi. Photo: Le Khanh
The tunnel shell will be arranged inside the TBM tunneling machine before the machine starts digging. Photo: Century
The tunnel shell will be arranged inside the TBM tunneling machine before the machine starts digging. Photo: Le Khanh

Regarding the progress of tunneling, Mr. Nguyen Ba Son - Deputy Head of Hanoi Urban Railway Management Board said that currently, experts are conducting the final inspection to proceed with tunneling, expected to start from July 30.

"Tunnel drilling will take place within 15 months. To minimize the pressure impact, 2 machines will drill staggered. Every day, 10m to 12m will be drilled. Households are identified to be affected during the process. The tunneling process has now begun to relocate.", Mr. Nguyen Ba Son said.

At the second meeting of the Working Group to assist the Steering Committee in implementing urban railway projects in Hanoi and Ho Chi Minh City, which took place on the morning of July 17, Vice Chairman of Hanoi People's Committee Duong Duc Tuan said that currently Hanoi has Test operation of the elevated section of the Nhon - Hanoi station metro project , expected to be in commercial operation at the end of July.

Tô Thế
TIN LIÊN QUAN

Đường sắt đô thị Nhổn - Ga Hà Nội sẽ hoạt động từ cuối tháng 7

PHẠM ĐÔNG |

Dự kiến, cuối tháng 7.2024 sẽ hoàn thành và đưa vào sử dụng đoạn trên cao tuyến đường sắt đô thị Nhổn - Ga Hà Nội.

Cận cảnh vị trí rào chắn thi công dốc hạ ngầm metro Nhổn - ga Hà Nội

Thế Kỷ |

Từ ngày 6.7, nhà thầu bắt đầu rào chắn đoạn dưới gầm cầu vượt nút giao Nguyễn Chí Thanh - Kim Mã phục vụ thi công dốc hạ ngầm tuyến metro Nhổn - ga Hà Nội.

Metro Nhổn - Ga Hà Nội và những lần lỡ hẹn

Thế Kỷ |

Việc xây lắp, lắp đặt và thử nghiệm tích hợp hệ thống đoạn trên cao thuộc Tuyến đường sắt đô thị thí điểm thành phố Hà Nội, đoạn Nhổn - ga Hà Nội (Metro) đến nay đã hoàn thành. Tuy vậy, việc đưa dự án đi vào khai thác vẫn chưa thể thực hiện.

32 bàn thắng ở 7 trận đầu lượt trận thứ hai Champions League

tam nguyên |

32 bàn thắng được ghi trong loạt 7 trận đấu mở màn lượt trận thứ hai UEFA Champions League 2024-2025.

Hà Nội trang hoàng dịp kỉ niệm 70 năm Giải phóng Thủ đô

Nhật Minh |

Hà Nội - Nhiều tuyến phố, địa điểm công cộng tại Hà Nội được trang trí cờ, hoa, pano để chào mừng kỉ niệm 70 năm ngày Giải phóng Thủ đô.

Cháy lớn ở Long Biên, 7 xe chữa cháy được huy động đến hiện trường

Khánh An |

Đám cháy lớn xảy ra tại một cửa hàng bán dụng cụ làm vườn tại đường Nguyễn Văn Linh (phường Gia Thuỵ, quận Long Biên, Thành phố Hà Nội).

Bé trai 6 tuổi cấp cứu ở TPHCM nghi bị ba ruột bạo hành

Minh Anh |

TPHCM - Liên quan đến thông tin phản ánh nghi ba ruột bạo hành con trai nhập viện cấp cứu, Công an Phường 16, Quận 8 đang vào cuộc làm rõ.

Nước Sông Hồng dâng cao, cầu phao Phong Châu tạm đóng

Tô Công |

Phú Thọ - Chiều tối 1.10, cầu phao Phong Châu phải tạm ngừng phục vụ người dân do nước sông Hồng dâng cao.

Đường sắt đô thị Nhổn - Ga Hà Nội sẽ hoạt động từ cuối tháng 7

PHẠM ĐÔNG |

Dự kiến, cuối tháng 7.2024 sẽ hoàn thành và đưa vào sử dụng đoạn trên cao tuyến đường sắt đô thị Nhổn - Ga Hà Nội.

Cận cảnh vị trí rào chắn thi công dốc hạ ngầm metro Nhổn - ga Hà Nội

Thế Kỷ |

Từ ngày 6.7, nhà thầu bắt đầu rào chắn đoạn dưới gầm cầu vượt nút giao Nguyễn Chí Thanh - Kim Mã phục vụ thi công dốc hạ ngầm tuyến metro Nhổn - ga Hà Nội.

Metro Nhổn - Ga Hà Nội và những lần lỡ hẹn

Thế Kỷ |

Việc xây lắp, lắp đặt và thử nghiệm tích hợp hệ thống đoạn trên cao thuộc Tuyến đường sắt đô thị thí điểm thành phố Hà Nội, đoạn Nhổn - ga Hà Nội (Metro) đến nay đã hoàn thành. Tuy vậy, việc đưa dự án đi vào khai thác vẫn chưa thể thực hiện.