Legal problems, 1,000 billion VND wastewater project in Quang Ngai faces difficulties

Viên Nguyễn |

Expected to start implementation in 2024, but to date, the Wastewater Treatment System Project with a total investment of VND 1,000 billion in Quang Ngai has not been able to start construction due to legal procedures and lack of consensus from the people.

Waiting for the completion of legal procedures

To prevent flooding and treat environmental pollution due to the lack of a domestic wastewater treatment system, the Provincial People's Council approved an investment policy of 1,000 billion VND to build the Quang Ngai City Rainwater and Wastewater Treatment System Project (formerly known as the project) in the southern basin of the Tra Khuc River downstream (abbreviated as the project). The implementation period is from 2024-2027. However, it is expected that the project will not start construction until the end of the fourth quarter of 2025.

According to Mr. Nguyen Van Cuong - Deputy Director of the Quang Ngai Province Civil and Industrial Construction Investment Project Management Board (investor), currently, the project management board is organizing the preparation and approval of a contractor selection plan to organize bidding to select contractors to consult on construction design steps after basic design.

To implement the next steps, it is necessary to organize the preparation and promptly approve the contractor selection plan. However, according to the provisions of the Law on Bidding No. 22/2023/QH15, which amends and supplements a number of articles in Law No. 90/2025/QH15, some contents of the contractor selection plan have been changed compared to the previous regulations such as the time for organizing contractor selection because the Government has specified in detail the limit for applying bidding designations according to the Government's regulations, while the Government has not issued a Decree guiding the implementation of Law No. 90/2025/QH15, so there is not enough legal basis for implementation.

In addition, during the implementation process, many households in Nghia Dung commune (now An Phu commune) have not agreed with the location of the construction of a wastewater treatment plant on the southern bank of Tra Khuc river, causing the project's progress to be greatly affected. Although the investor and local authorities have organized many consultation meetings on planning, environment, site clearance, etc., they have not yet reached a high level of consensus among the people of villages 5 and 6.

Mr. Nguyen Van Cuong said that the project investor is organizing the preparation and approval of task outlines and estimates of construction consulting packages implemented after the basic design to serve as a basis for accelerating the implementation of contractor selection for the next steps as soon as the authority is granted to issue Decrees guiding the implementation of Law No. 90/2025/QH15 and Circulars guiding implementation according to regulations.

Nhieu tuyen duong o trung tam tinh Quang Ngai thuong xuyen bi ngap cuc bo khi xay ra mua lon keo dai. Anh: Le Tan
Many roads in the center of Quang Ngai province are often partially flooded during prolonged heavy rains. Photo: Le Tan

Speed up progress to create synchronization with the dam project

The investor is coordinating with agencies and localities to determine the scope and boundaries of land acquisition, inventory, compensation plans, site clearance, and mine clearance; at the same time, organize conferences to publicize information, resolve problems to create consensus among people and speed up project progress.

The project investor is continuing to review and proactively coordinate with competent authorities to ensure full preparation of construction licensing procedures, in time to implement synchronous construction according to the general progress of the project.

Notably, previously, sharing with reporters, Mr. Tran Hoang Tuan - former Permanent Vice Chairman of the People's Committee of Quang Ngai province said that the Tra Khuc River downstream dam project (total investment of 1,498 billion VND) will continue to be implemented, but it is necessary to create synchronization with other projects for the dam to be effective. In particular, the Quang Ngai City centralized wastewater collection and treatment system project is being focused on by the province.

According to the reporter's records, the Tra Khuc River downstream dam project is being accelerated, expected to be completed by the end of 2025. On the contrary, the project of the system to collect and treat rainwater and wastewater of Quang Ngai city in the southern basin of the Tra Khuc river downstream is still stuck in legal procedures and has not received consensus from the people. This means that even if the dam is completed on schedule, its function will be difficult to fully exploit.

Viên Nguyễn
RELATED NEWS

Inauguration of the VND932.4 billion drainage and wastewater treatment system in Son La

|

Son La - On the morning of August 19, Son La province held an inauguration ceremony for the Son La City Wastewater Drainage and Treatment System.

Wastewater reservoir in the center of Quang Ngai is revived after ten years of causing pollution and flooding

|

Quang Ngai - The Bau Ca Lake and Song Dao Canal dredging project aims to increase water capacity, treat odors, reduce flooding, improve the environment and urban beauty.

Wastewater drainage is one meter higher than the house, people in Hanoi temporarily travel

|

Hanoi - Dozens of households in Ha Dong (Hanoi) are suffering because the drainage improvement project is being constructed with a roadbed higher than their houses.

Young people "burning" themselves out at events spreading patriotism

|

Lao Dong Newspaper had a conversation with Ngo Duc Duy (C around) about the topic of young people spreading patriotism through community events.

"Red Rain" earns nearly 50 billion VND after 1 day of release

|

The film "Red Rain" became the film about war with the highest opening revenue in box office history.

Children gain weight quickly after summer vacation, doctors warn of the risk of obesity and consequences

|

After the summer vacation, many children gain weight quickly due to eating habits and lack of exercise. This has not only increased the risk of obesity but also affected the psychology.

Submitting to the National Assembly the Law amending and supplementing a number of articles of 10 laws related to security

|

Politburo member and National Assembly Chairman Tran Thanh Man has signed and issued Resolution No. 94/2025/UBTVQH15 Adjusting the 2025 Legislative Program.

Inauguration of the VND932.4 billion drainage and wastewater treatment system in Son La

NGUYỄN TRƯỜNG |

Son La - On the morning of August 19, Son La province held an inauguration ceremony for the Son La City Wastewater Drainage and Treatment System.

Wastewater reservoir in the center of Quang Ngai is revived after ten years of causing pollution and flooding

VIÊN NGUYỄN |

Quang Ngai - The Bau Ca Lake and Song Dao Canal dredging project aims to increase water capacity, treat odors, reduce flooding, improve the environment and urban beauty.

Wastewater drainage is one meter higher than the house, people in Hanoi temporarily travel

Nguyễn Linh - Thanh Hằng |

Hanoi - Dozens of households in Ha Dong (Hanoi) are suffering because the drainage improvement project is being constructed with a roadbed higher than their houses.