Overnight at Dai Ngai 1 bridge construction site in the rainy season

PHƯƠNG ANH |

Dai Ngai Bridge - Hundreds of workers work day and night to urgently construct Dai Ngai 1 Bridge, ensuring progress, expected to be completed in June 2028.

After 1 year of construction, Dai Ngai 1 bridge under the Dai Ngai bridge construction project on National Highway 60 in Tra Vinh and Soc Trang provinces (now Vinh Long province and Can Tho city) is gradually taking shape.

Although it is the peak of the rainy season, high tides cause difficulties for construction, the construction site is still bustling day and night, showing determination to complete the project on schedule.

Hinh dang cau Dai Ngai 1 sau 1 nam thi cong. Anh: Phuong Anh
The shape of Dai Ngai 1 bridge after 1 year of construction. Photo: Phuong Anh

Dai Ngai 1 Bridge is the main item of the 15XL package, with a total construction value of VND 3,907 billion. The project is designed according to a special cable-stayed structure with a total length of more than 3 km; in which the main bridge is 2.59 km long, 21.5 m wide, spanning Dinh An channel (Hau river). The two main towers are 110 m high, shaped like an A. The main span is 450 m long, the second largest in Vietnam after Can Tho Bridge and is the first cable-stayed bridge directly designed and implemented by a domestic consultant.

The package is headed by the Deo Ca Group consortium for 1,250 days, expected to be completed in June 2028.

Tai tru P17 (ben phia Vinh Long), nha thau dang do be tong tru, cac cong nhan tien hanh dam be tong - day la cong doan giup ket cau cong trinh tro nen kien co, vung chac va han che duoc kha nang sut lun ve sau.
Workers pour concrete at pillar P17 (Vinh Long side), ensuring a solid bridge piers structure. Photo: Phuong Anh

Recorded at pillar P17 (on the Vinh Long side), the contractor is pouring concrete for the pillar, the workers are conducting concrete mines, the step helps the structure of the project become solid, sturdy and limits the possibility of subsidence later.

According to the Management Board, all 60 1.5 m diameter bored piles of the approach bridge have been completed, along with 6 piers, 2 pillars, 1 hat bar, 25/28 SuperT girders. It is expected that by the Lunar New Year 2026, the entire body of the pillars and beams will be completed to switch to the construction of the above structure.

Anh: Phuong Anh
Workers' team constructing the P17 pillar pedestal. Photo: Phuong Anh

Similarly, at the main pillar of 2024, more than 150 engineers and workers are constructing with the goal of completing all deposits 2 months ahead of schedule.

Because the location near the estuary often has strong winds and tides, the contractor used large cranes and 5,000-ton barges to keep it stable. The plan to close the construction floor has been approved by the investor and consultant to reduce the impact of the water level.

Thiet bi khoan coc nhoi co lon va sa lan 5.000 tan duoc huy dong tai cong truong cau Dai Ngai de ung pho thuy trieu va gio manh. Anh: Phuong Anh
5,000 tons of barges were mobilized at the Dai Ngai 1 bridge construction site to cope with high tides and strong winds. Photo: Phuong Anh

Mr. Cao Ngoc Nam - Deputy General Director of Deo Ca Group - informed that the construction site mobilized more than 400 officers, engineers, workers and 150 modern equipment such as large-sized pile drilling machines, 300-ton cranes, 5,000-ton barges, and organized 30 simultaneous construction teams.

Cong nhan thi cong tai cau Dai Ngai 1. Anh: Phuong Anh
Workers constructing at Dai Ngai 1 bridge. Photo: Phuong Anh

Mr. Phan Van Y - Deputy Executive Director of Dai Ngai 1 Bridge Project - said that construction must be flexible according to the tide. At night, maintain 40 - 50 employees working from 6pm to 6am to take advantage of the time when the water recedes. The area near the estuary is affected by strong tides, so the construction unit had to use large barges, arrange rain shelters and safe laborers. Up to now, the progress has met the requirements set by the investor.

Doi cong nhan lam viec xuyen dem khi thuy trieu xuong, tan dung “gio vang” thi cong. Anh: Don vi cung cap
The team of workers worked all night when the tide came down, taking advantage of the "golden hour" of construction. Photo: Provided by the unit

According to Project Management Board 85, the entire Dai Ngai Bridge construction project is currently implementing 44 construction teams, including 24 teams of Dai Ngai 1 bridge; 4 small bridge teams; 10 roadbed teams; 2 construction teams of Tran De canal embankment and 4 auxiliary works. A total of 488 people and 207 equipment were used.

To date, the volume of many important items has been completed. The Project Management Board said that the project meets the requirements of progress, ensuring quality, labor safety and environmental sanitation.

PHƯƠNG ANH
RELATED NEWS

The shape of Dai Ngai 1 Bridge, Vietnam's second largest cable-stayed bridge, is gradually revealed

|

More than 400 cadres, engineers, workers, 150 machines and equipment are urgently constructing Dai Ngai 1 bridge, expected to be completed in 2028.

Overcoming difficulties in the rainy season, speeding up the construction of Vietnam's second largest cable-stayed bridge

|

Despite the peak of the rainy season, Dai Ngai Bridge construction site is still bustling with construction day and night, determined to complete on schedule.

Image of the highest cable-stayed bridge in Vietnam about to reach the finish line

|

HCMC - Binh Khanh Bridge is basically completed and is currently being paved with asphalt. It is expected that the entire project will be completed by the end of August this year.

The 14th Congress of the Vietnam General Confederation of Labor is scheduled to be held in June 2026

|

On the morning of November 20, the Vietnam General Confederation of Labor held the 14th Conference of the Presidium of the Vietnam General Confederation of Labor (term XIII). The conference was held to discuss the organization of the 14th Congress of the Vietnam General Confederation of Labor...

Worried about drug resistance, many parents refuse to buy antibiotics for their children

|

Hanoi - Instead of rushing to signal to buy antibiotics every time their child coughs or has a runny nose, more and more parents are increasingly aware of the risk of drug abuse.

Hundreds of billion-dollar cars in the center of Nha Trang submerged in floodwaters

|

Khanh Hoa - Floods rose rapidly at night, causing hundreds of cars parked in the Go supermarket area, Tay Nha Trang ward, to be deeply submerged in water.

Army and Navy marched overnight to rescue people trapped in Khanh Hoa flood

|

Khanh Hoa - Many forces stationed in the area have marched to flooded areas to support people still trapped in the flood.

Houses in alleys worth 3 billion VND are considered rare goods, experts predict a stable market

|

Once a segment that suits real needs and meets all financial capabilities, but houses in alleys are still increasing in price "dizzily".

The shape of Dai Ngai 1 Bridge, Vietnam's second largest cable-stayed bridge, is gradually revealed

PHƯƠNG ANH |

More than 400 cadres, engineers, workers, 150 machines and equipment are urgently constructing Dai Ngai 1 bridge, expected to be completed in 2028.

Overcoming difficulties in the rainy season, speeding up the construction of Vietnam's second largest cable-stayed bridge

PHƯƠNG ANH |

Despite the peak of the rainy season, Dai Ngai Bridge construction site is still bustling with construction day and night, determined to complete on schedule.

Image of the highest cable-stayed bridge in Vietnam about to reach the finish line

Anh Tú |

HCMC - Binh Khanh Bridge is basically completed and is currently being paved with asphalt. It is expected that the entire project will be completed by the end of August this year.