Trillion-VND cancer hospital in Can Tho continues to wait for supplies

Nhóm PV |

Can Tho - The investment project to build Can Tho City Oncology Hospital (scale of 500 beds) is restarted, contributing to the realization of a specialized medical center in the Mekong Delta.

In March 2025, Lao Dong newspaper started publishing a series of articles "Prolonged Consequences of the billion-dollar abandoned Oncology Hospital Project", directly reflecting the inadequacies at the Can Tho City Oncology Hospital Construction Investment Project (scale of 500 beds). After a long period of efforts to remove bottlenecks in mechanisms and capital, the project has now been restarted.

Along with that is the fact that facility 1 is invested with a modern accelerator radiation therapy machine, facility 3 has just been inaugurated, clearly demonstrating the political determination of Can Tho City, creating motivation for the city to bring the project to completion by the end of November 2026, in accordance with the direction of the Prime Minister.

Exterior paint

Under the harsh sun of March, we returned to the construction site of the Can Tho City Oncology Hospital construction investment project (scale of 500 beds). Different from the wild and quiet appearance of a year ago, the atmosphere here has changed greatly, with brighter colors.

a
The yard is quite cleaned up. Photo: PV Group.

Dozens of workers have sprayed high-intensity water to remove long-term moss, then proceeded to paint the outer surface.

According to observations, removing the "scars of time" left behind is quite laborious.

a
Image of the hospital in early March when construction resumed. Photo: PV Group.

Talking to Lao Dong Newspaper, Mr. Le The Vinh - Project Management Board (under Bach Dang Construction Corporation) said that the investor and the contractor consortium finalized contract appendix No. 9, basically completed, and started deploying the next part.

a
Applying exterior paint in mid-March. Photo: PV Group.

In the near future, after the contract appendices and legal procedures are completed, the construction unit can deploy them massively. At this time, the parties need to have close and close contact, go into completion and not overlap with each other" - Mr. Vinh said.

On the side of Bach Dang Contractor, the rough part has been basically completed, and is currently continuing to clean and carry out covering and painting the outer surface. As of March 31, the construction unit is constructing the water supply and drainage road from the roof of building C to the ground and cutting the wall to bury pipes.

Waiting for supplies to speed up progress

According to research, by mid-April 2026, the project had signed Appendix No. 10 (addendum on changes to materials, construction materials and core contents of the project). However, it is still necessary to continue waiting for materials to arrive. Meanwhile, the progress of the construction unit must completely depend on the supply of materials.

Previously, the related parties informed Mr. Truong Canh Tuyen, Chairman of Can Tho City at the construction site survey on March 12, 2026. Mr. Tuyen requested the investor (Department of Health) to have solutions and be resolute with the parties so as not to affect the project progress.

Chủ tịch Cần Thơ Trương Cảnh Tuyên rất “sốt ruột” với tiến độ Dự án đầu tư xây dựng Bệnh viện Ung bướu TP Cần Thơ (quy mô 500 giường). Ảnh: Phong Linh.
Can Tho Chairman Truong Canh Tuyen said he was very "impatient" about the project progress. Photo: Phong Linh.

Chairman of Can Tho City People's Committee Truong Canh Tuyen requested Director of Can Tho Department of Health Hoang Quoc Cuong, in addition to Appendix No. 10 mentioned above, "any appendix that needs to be signed must be done in one go to finish".

a
The appearance of the Hospital when painting the exterior in early April 2025. Photo: PV Group.

Most recently, when exchanging with Lao Dong Newspaper, an official at the construction site worried that if there are materials, they will still deploy powder bait and anti-alkaline primer for both inside and outside, and the coating can be pushed back to perform other tasks related to wall chiseling and cutting before painting to ensure quality and aesthetics.

Invest in modern equipment

At the end of March 2026, in the bustling atmosphere of the handover ceremony of the accelerated radiation therapy system at facility 1, patient Huynh Hoang Hai (Vinh Long province) expressed: "Hearing the news of having a radiation therapy machine is very happy, happy for me and many other patients. So now I just hope the new hospital will put it into use so that people will be less worried" - .

a
Patient Huynh Hoang Hai being treated at Can Tho City Oncology Hospital. Photo: PV Group.

Representatives of the Can Tho City Department of Health - said that the accelerated radiation therapy system being handed over will contribute to improving the quality of treatment, approaching advanced standards; reducing the burden on central-level hospitals; more importantly, shortening the distance to access high-quality medical services between regions, ensuring fairness in people's health care.

After the handover ceremony, the accelerated radiation therapy system will be put into pilot operation by Can Tho City Oncology Hospital, in order to complete the technical inspection, radiation dose standardization, operation process evaluation and complete human resource training.

As Lao Dong newspaper reported, on November 14, 2025, at the 6th session (specialized session), the Can Tho City People's Council passed a resolution on adjusting the investment policy of the project.

Accordingly, adjusting the capital structure of the project includes: ODA loans from the Hungarian Government (more than 272 billion VND), central budget capital (1.334 billion VND), counterpart capital from local budget sources (more than 465 billion VND). At the same time, adjusting to increase the total investment (due to exchange rate differences) by about 344 billion VND. The total investment after adjustment is expected to be 2,071 billion VND.

Nhóm PV
RELATED NEWS

Can Tho Oncology Hospital officially receives the transfer of accelerated radiation therapy system

|

Can Tho - Can Tho Oncology Hospital receives the handover of the accelerated radiation therapy system, thereby helping patients in the area access advanced radiation therapy techniques.

Mr. Truong Canh Tuyen continues to be elected as Chairman of Can Tho City People's Committee

|

Mr. Truong Canh Tuyen has just been elected by the City People's Council to hold the position of Chairman of Can Tho City People's Committee, term 2026 - 2031.

Long-term consequences of the abandoned trillion-dollar oncology hospital project

|

Can Tho - The shortage of conditions at the City Oncology Hospital makes patients tired of treatment, doctors and nurses suffer heavy psychological suffering...

Launching Workers' Month in the Textile and Garment industry

|

Ho Chi Minh City - Vietnam National Textile and Garment Union launches Workers' Month and Action Month on Occupational Safety and Health in 2026.

Teachers and students exhausted from chasing achievements and scores

|

Believing that there is still a disease of achievement in education, Delegate Dang Ngoc Huy proposed to change the assessment of students in the direction of valuing competence and substantive progress.

Night-long journey to search for missing male student in Tam Dao

|

Phu Tho - Regarding the case of a male student missing in Tam Dao, functional forces said they have mobilized more than 100 people and flycams to search all night.

10th grade registration in Ho Chi Minh City starts tomorrow

|

According to the plan, from April 22, students in Ho Chi Minh City will officially register their aspirations for 10th grade online.

Tim Cook will resign as Apple CEO

|

Apple announced on April 20 that Tim Cook will resign as CEO in September and hand over the highest position to veteran personnel John Ternus.

Can Tho Oncology Hospital officially receives the transfer of accelerated radiation therapy system

Phong Linh |

Can Tho - Can Tho Oncology Hospital receives the handover of the accelerated radiation therapy system, thereby helping patients in the area access advanced radiation therapy techniques.

Mr. Truong Canh Tuyen continues to be elected as Chairman of Can Tho City People's Committee

Phong Linh |

Mr. Truong Canh Tuyen has just been elected by the City People's Council to hold the position of Chairman of Can Tho City People's Committee, term 2026 - 2031.