On February 16, according to information from the Dong Nai Province Land Fund Development Center, a land plot of more than 49 hectares in Phuoc Tan ward with 1,066 resettlement plots, up to now, Bien Hoa City has approved a detailed construction planning project at a scale of 1/500, the Dong Nai Provincial People's Committee has approved the feasibility study report, the Ministry of Natural Resources and Environment has approved the results of the environmental impact assessment report.
According to the plan, in June 2025, the infrastructure construction will start, the construction time will be 8 months, by the first quarter of 2026, the technical infrastructure will be basically completed to hand over resettlement land to people to build houses.
The resettlement area in Phuoc Tan ward has a total estimated investment of more than 1,127 billion VND.
As for the 31.5-hectare land in Tam Phuoc ward, according to calculations, there are 1,280 resettlement plots, up to now the project has had a detailed construction plan at a scale of 1/500, approved by the competent authority for feasibility study report as well as environmental license issuance.
According to the plan, this resettlement area will start construction in April 2025, with a construction period of about 6 months, basically completing the technical infrastructure and handing over the land to people to build houses in October 2025.
The resettlement area in Tam Phuoc ward has a total estimated investment of more than 717 billion VND.
Both resettlement areas in Phuoc Tan ward and Tam Phuoc ward are to arrange resettlement for people who have to relocate to implement component project 1 - Bien Hoa - Vung Tau expressway and are assigned to the Dong Nai Provincial Land Fund Development Center for investment.