Bac Ninh Provincial People's Committee has just issued a decision on approving the progress monitoring table for the implementation of investor selection activities for the Thai Ha urban area project, Nenh ward.
The decision clearly states that the bidding party is the Bac Ninh Provincial Civil and Urban Development Project Management Board No. 1.
The form and method of investor selection is open bidding in the country.
Investor selection method: One phase, one dossier bag.
Time to start organizing investor selection: January 2026.
According to the People's Committee of Bac Ninh province, the Thai Ha urban area project aims to gradually complete urban infrastructure for the locality to meet socio-economic development requirements.
At the same time, solving housing needs, creating commercial and service spaces, entertainment associated with attractive artificial green water surface landscape areas, gradually building and forming modern architectural landscape spaces for the area, ensuring harmonious connection with the urban infrastructure of surrounding areas.
Project scale: The project has a land use scale of about 38.9 ha; Population scale of about 8,672 people.
Total investment capital is expected to be more than 7,822 billion VND.
Project operating term: 50 years from the date of investor approval. Project implementation progress: Completing land and construction procedures; completing construction 72 months from the date of investor approval to implement the project.
Previously, in October 2025, Bac Ninh Provincial People's Committee also issued an official letter requesting the Ministry of National Defense and the Ministry of Public Security to give opinions on issues related to national defense and security for the project investment policy approval dossier according to regulations.