The trillion-dong overpass in Hue will open in March 2025

PHÚC ĐẠT |

HUE - It is expected that on March 26, 2025, the overpass project worth more than 2,280 billion VND across the Huong River will be opened to traffic.

On January 6, Chairman of Hue City People's Committee Nguyen Van Phuong went to the field to inspect the progress of site clearance and construction of the Huong River overpass project.

At the inspection, provincial leaders listened to detailed reports from construction units and investors on the project implementation status, difficulties, obstacles as well as progress of important items.

According to the report, the project is now basically on schedule. However, there are still some obstacles related to site clearance and weather conditions affecting the progress.

“Up to this point, we have completed about 90% of the work. The remaining work, although not much, is of an aesthetic nature and depends on the weather. Therefore, we have to take advantage of favorable weather to organize the construction,” said Mr. Nguyen Dinh Quyen - Deputy Director of the City Traffic Project Management Board.

Cau vuot Nguyen Hoang la cong trinh trong diem trong ke hoach phat trien ha tang giao thong va ket noi do thi cua TP Hue. Anh: Nguyen Phong.
Nguyen Hoang overpass is a key project in the transport infrastructure development and urban connectivity plan of Hue City. Photo: Nguyen Phong.

During the inspection, Chairman of Hue City People's Committee Nguyen Van Phuong emphasized the importance of the project to the city's socio-economic development. He requested relevant units to strengthen coordination, speed up progress, ensure project quality as well as comply with requirements on labor safety and environmental protection.

The Chairman of the Hue City People's Committee also requested construction units and investors to focus on resolving problems in site clearance, especially paying attention to supporting resettled people, ensuring legitimate rights for affected people. At the same time, units need to review the entire construction plan, arrange human resources and machinery reasonably to ensure the committed progress. For items that are still behind schedule, there must be a specific roadmap and additional shifts to complete on time.

The Perfume River Overpass is an important project that not only helps reduce traffic pressure but also creates a highlight for Hue's urban landscape. Chairman of Hue City People's Committee Nguyen Van Phuong requested that the project be completed on time on March 26, 2025 to put into operation soon and serve the people.

The Nguyen Hoang Street and Huong River Overpass Project is part of the Ring Road 3 - the main traffic axis through the city, connecting two satellite towns, Huong Tra and Huong Thuy, with Phu Xuan and Thuan Hoa districts. The project has a total investment of VND 2,281 billion, mobilized from the central and local budgets.

According to the design, the bridge is a steel arch, 380m long, including 5 spans, 43m wide, with 6 lanes and 210m long approach roads at both ends. In particular, the bridge also has a 3m wide pedestrian lane. The bridge structure is made of reinforced concrete, with a minimum navigation capacity of 30m wide and 6m high.

PHÚC ĐẠT
RELATED NEWS

Overpass near the estuary in Soc Trang

|

Soc Trang - On January 5, Dai Ngai 2 bridge officially closed, about 6 months ahead of schedule.

The bridge over Hau River near the estuary was completed

|

Soc Trang - Dai Ngai 2 Bridge officially closed on January 5, shortening the distance connecting the mainland with the island in the middle of the Hau River.

Opening of 487 billion VND railway overpass in Vinh Phuc

|

On January 1, the People's Committee of Vinh Phuc province organized the opening of the Nguyen Tat Thanh railway overpass in Dinh Trung ward, Vinh Yen city.

Vice President of the Central Committee of the Vietnam Fatherland Front Ha Thi Nga works in Tuyen Quang

|

On October 14, Ms. Ha Thi Nga - Member of the Party Central Committee, Vice Chairwoman of the Central Committee of the Vietnam Fatherland Front (VFF) had a working session with the Vietnam Fatherland Front Committee of Tuyen Quang province.

Gold price update on the morning of October 15: Prolonged increase, no signs of reversal

|

Gold price update on the morning of October 15: Continue to increase. The precious metal has shown no signs of turning around and falling.

Coach Kim Sang-sik praises young players of the Vietnam team

|

Coach Kim Sang-sik gave many compliments to the U23 players of the Vietnam national team after a narrow 1-0 victory over Nepal.

Notice of traffic diversion to serve the Hanoi Party Congress

|

Hanoi - Some routes will be temporarily banned and vehicles will be restricted from October 15 to 17, 2025.

Overpass near the estuary in Soc Trang

PHƯƠNG ANH |

Soc Trang - On January 5, Dai Ngai 2 bridge officially closed, about 6 months ahead of schedule.

The bridge over Hau River near the estuary was completed

PHƯƠNG ANH |

Soc Trang - Dai Ngai 2 Bridge officially closed on January 5, shortening the distance connecting the mainland with the island in the middle of the Hau River.

Opening of 487 billion VND railway overpass in Vinh Phuc

An Vi |

On January 1, the People's Committee of Vinh Phuc province organized the opening of the Nguyen Tat Thanh railway overpass in Dinh Trung ward, Vinh Yen city.