The Royal Yard BT Project in Nha Trang falls into a spiral of debt

Hữu Long |

The BT project of the Royal Yacht Wharf Center in Nha Trang is falling into a bad debt situation, and its assets are being tightly regulated by the bank.

In August 2025, the Department of Agriculture and Environment of Khanh Hoa conducted a review and handling of land plots that had been decided to be reclaimed by the Provincial People's Committee but had not been handed over to the Land Fund Development Center for management.

The name of the Royal Yard Center project is on this list. Specifically, in area D of the project, although the Decision to reclaim more than 19,142m2 of land was issued in 2017, Ben Duong Hotel Joint Stock Company has not yet handed over the land to the Provincial Land Fund Development Center.

The name La Luna Resort Nha Trang (legal name is the Royal Yard Center Project) was once a prominent project in the list of BT (build - transfer) projects that Khanh Hoa province implemented in the past decade.

La Luna Resort Nha Trang (ten phap ly la Du an Trung tam Ben Du thuyen Hoang Gia). Anh: Huu Long
The Royal Yard Center project has been abandoned for many years. Photo: Huu Long

After only a few years of implementation, this project fell into a bad debt situation, and its assets were simultaneously tightened by many banks.

This BT project originates from the policy of Khanh Hoa Provincial People's Committee on upgrading and expanding Mai Xuan Thuong Street (old Nha Trang City) with a total length of only 970m, with a total investment of about 47 billion VND.

a
This project is in a bad debt situation, and its assets are being held back by many banks at the same time. Photo: Huu Long

After the route came into operation (April 2015), Khanh Hoa Provincial People's Committee signed a BT contract with Ben Tuong Hotel Joint Stock Company, with a contract value of about 47.5 billion VND.

Also in 2015, Khanh Hoa province decided to hand over and lease more than 47,000m2 in Vinh Hoa ward, Nha Trang city (old) to Ben Du Thuyen Company.

After being allocated land, this enterprise implemented the Royal Yard Center project to recover capital for the BT project to upgrade Mai Xuan Thuong Street and the dormitory of Khanh Hoa Provincial Political School.

The Yates Hotel Joint Stock Company was allocated land including area A of nearly 6,000m2, area B of more than 3,800m2 in Vinh Hoa urban area for the project.

Nam 2017, tinh Khanh Hoa quyet dinh dieu chinh, thu hoi hon 19.000 m2 (khu D) vi khong nam trong du an hoan von BT tren. Anh: Huu Long
Khanh Hoa province has reclaimed more than 19,000m2 (area D) because it is not included in the above BT refund project. Photo: Huu Long

In 2016, Khanh Hoa province approved the price of land use fees for residential land (not forming residential units) for areas A and B (more than 9,800m2) at about VND4.7 million/m2 for investors to recover capital for the BT project.

In addition, this project has 2 other sub-areas, areas C and D. For area D alone, in 2017, Khanh Hoa province decided to adjust and reclaim more than 19,000 m2 because it was not included in the above BT refund project.

Since 2018, the investor has signed contracts to buy and sell luxury resort apartments in this project with many customers, collecting money but not yet handing over the houses to buyers.

From 2024 to present, the La Luna Resort project has been continuously advertised by banks for sale of collateral to recover bad debts.

Nhieu hang muc cong trinh tu lau bi bo hoang nen xuong cap, hoen gi theo thoi gian. Anh: Huu Long
Many construction items have been abandoned for a long time, so they have deteriorated and rusted over time. Photo: Huu Long

In June 2025, VietinBank Thanh An branch announced for the third time the auction of the debt of Ben Du Thuyen Hotel Joint Stock Company. Total outstanding loans as of May 8, 2025 were over VND 752 billion.

The secured assets include the right to use 5,965.5m2 of land and futurely formed assets attached to land in Area A.

All real estate of the Royal Shipbuilding Center Project - Swisstouches Laluna Resort - Area A and Property Rights of Ben Du Thuyen Company arose from 291 apartment sale and purchase contracts signed between Ben Du Thuyen Hotel JSC and the apartment buyer.

Continuing in early July 2025, area B of the project was advertised for sale by Agribank for the 19th time to recover the debt with a starting price of VND 948 billion of Ben Du Thuyen Hotel Joint Stock Company.

Ngan hang nhieu lan rao ban tai san
The bank has repeatedly auctioned the debt of Ben Du Thuyen Hotel Joint Stock Company but there have been no buyers. Photo: Huu Long

In Khanh Hoa, the BT (build - transfer) project type was once implemented with the goal of changing infrastructure for land fund. However, the implementation process has revealed many violations in planning, valuation and land allocation, causing budget losses.

In particular, many projects have been inspected, handled and reviewed. Thereby rectifying investment activities in this form to ensure transparency and compliance with the law.

Hữu Long
RELATED NEWS

Khanh Hoa reviews 19 reclaimed land plots but has not yet been handed over on site

|

Khanh Hoa has 19 land plots that have been decided to be reclaimed, but the handover has not been completed on site.

Regrets about a series of abandoned Bao Dai villas along the coast of Nha Trang

|

Khanh Hoa - 5 Bao Dai villas on the coast of Nha Trang are abandoned, causing public regret and proposing to soon restore them to welcome visitors.

Khanh Hoa prepares to start 4 major projects to celebrate the 80th anniversary of National Day

|

Khanh Hoa - The locality plans to organize a groundbreaking ceremony for 4 key projects to celebrate the 80th anniversary of the National Day of the Socialist Republic of Vietnam.

The largest cable-stayed bridge in Ho Chi Minh City has domestic enterprises proposing investment

|

HCMC - The 7.3 km long Can Gio bridge project, with a capital of more than VND 10,500 billion, has just been proposed by a domestic enterprise to participate in investment in a new form.

Latest forecast of the path of the tropical depression and bad weather

|

According to the meteorological agency, it is forecasted that in the next 24 hours, the tropical depression will gradually weaken into a low pressure area.

Personnel transfer and appointment in Nghe An, Phu Tho, Thanh Hoa

|

From August 4 to August 8, in Nghe An, Phu Tho, Dong Nai, Son La, Thai Nguyen, Thanh Hoa, Khanh Hoa provinces... decisions on election, transfer, and appointment of personnel will be implemented.

The Royal Yard BT Project in Nha Trang falls into a spiral of debt

|

The BT project of the Royal Yacht Wharf Center in Nha Trang is falling into a bad debt situation, and its assets are being tightly regulated by the bank.

1 Major General, 5 Colonels, 5 Colonel-level military officers receive new assignments

|

1 Major General, 5 Colonels, 3 Lieutenant Colonels, 2 Major Cants, 1 Army Captain have just been elected, appointed, transferred, and appointed to new assignments last week (August 4 - August 8).

Khanh Hoa reviews 19 reclaimed land plots but has not yet been handed over on site

Hữu Long |

Khanh Hoa has 19 land plots that have been decided to be reclaimed, but the handover has not been completed on site.

Regrets about a series of abandoned Bao Dai villas along the coast of Nha Trang

Hữu Long |

Khanh Hoa - 5 Bao Dai villas on the coast of Nha Trang are abandoned, causing public regret and proposing to soon restore them to welcome visitors.

Khanh Hoa prepares to start 4 major projects to celebrate the 80th anniversary of National Day

Bình Quý |

Khanh Hoa - The locality plans to organize a groundbreaking ceremony for 4 key projects to celebrate the 80th anniversary of the National Day of the Socialist Republic of Vietnam.