Khanh Hoa has been slow to establish a master plan for Nha Trang for more than 2 years

Hữu Long |

The Government Inspectorate (GIA) has just concluded that Khanh Hoa province has prepared a project to adjust the general planning of Nha Trang City 2 years and 6 months behind schedule.

delays in planning and appraisal

According to TTCP, the project to adjust the general planning of Nha Trang City by 2040 has an area of about 25,422 hectares, of which Dien Khanh district is about 1,314 hectares.

The goal of the project is to develop Nha Trang City into a national and international beach resort tourism urban area, with an expected population of about 630,000 - 640,000 people by 2030.

The planning also requires ensuring objectivity and transparency in implementation, adjustment of zoning plans, detailed plans, land use planning and legal procedures related to the 42 reviewed projects.

However, the implementation process shows that the Ministry of Construction has appraised the project to adjust the general planning of Nha Trang City 7 months later than the time specified in Article 32 of Decree No. 37 of the Government.

At the same time, Khanh Hoa Provincial People's Committee has prepared a project to adjust 2 years and 6 months later than the deadline prescribed in Decision No. 1456 of 2020 of the Prime Minister.

The conclusion of the JSC also clearly shows that the Ministry of Construction regularly appraises the delay in planning tasks and planning projects.

The People's Committees of localities set up planning tasks and long-term planning projects, not within the prescribed time limit. Notably, in the period of 2015-2019, the Ministry of Construction did not issue a decision to establish an appraisal Council, violating Article 42 of the 2009 Law on Urban Planning.

The Ministry of Construction has not yet properly implemented the process of appraising the conditions for meeting the requirements of the planning consulting organization, and has not closely followed the content of the planning task as well as data on population and land.

For the People's Committee of Khanh Hoa province and related units, the JSC pointed out violations such as slow announcement and disclosure of planning projects as prescribed in Clause 1, Article 53 of the Law on Urban Planning 2009; not yet implementing the marking of planning projects according to Article 57 of this law.

Request to review and handle responsibilities

From the above violations, the Government Inspector General proposed the Prime Minister to direct the Ministry of Construction to review and clarify the collective and individual responsibilities of the Ministry's leaders in the occurrence of shortcomings and limitations in the management and implementation of construction plannings.

In addition, the TTCP proposed Khanh Hoa Provincial People's Committee to review and clarify the responsibilities of the provincial leaders and related individuals to occur the above shortcomings. At the same time, the Ministry of Construction and the People's Committee of Khanh Hoa province must be responsible for handling relevant individuals and units according to their competence.

TTCP emphasized that the delay in planning and appraisal not only affects the progress of urban development but also reduces the effectiveness of state management in the planning and construction sector in Nha Trang City and Khanh Hoa Province.

Hữu Long
TIN LIÊN QUAN

Khanh Hoa affirms its role as a marine economic center

|

After 50 years of liberation and 40 years of implementing the renovation guidelines, Khanh Hoa province has made strong progress, affirming its position as an important marine economic center of the country.

More than 1,600 people attended the Flag-raising ceremony to celebrate the Liberation of Khanh Hoa

|

On the morning of April 2, Khanh Hoa province held a flag-raising ceremony to celebrate the 50th anniversary of the Provincial Liberation Day and the 50th anniversary of the Liberation of the South and National Reunification Day.

3 unfinished BT projects of Phuc Son Group in Khanh Hoa

|

Phuc Son Group currently has 3 BT (build - transfer) projects in Nha Trang, of which only the Ngoc Hoi Intersection project has determined the construction roadmap. The remaining two projects are currently on hold due to legal problems.

Hang Son Doong is called a surreal wonder by an American magazine

|

Travel+Leisure has a new article praising the natural landscape and diversity of the world in the heart of Son Doong - the world's largest cave.

Urgently evacuate households from "death hole" in Muong Hoa commune

|

Phu Tho - On the morning of July 11, the authorities evacuated two households from the "death hole" area formed by landslides and subsidence in Tham hamlet, Muong Hoa commune.

Gold price today 11.7: Strong increase

|

Gold prices today, July 11, increased simultaneously in both domestic and international markets.

The 2026 World Cup TV copyright price is a challenge for Vietnamese broadcasters

|

Owning the 2026 World Cup TV copyright in Vietnam is becoming a hot issue, as the expected price could exceed 15 million USD.

Mr. Trump sends more letters to many countries, promotes tariff agreements

|

President Trump continues to put trade pressure on many countries with letters announcing new tax rates expected to be applied.

Khanh Hoa affirms its role as a marine economic center

Hữu Long |

After 50 years of liberation and 40 years of implementing the renovation guidelines, Khanh Hoa province has made strong progress, affirming its position as an important marine economic center of the country.

More than 1,600 people attended the Flag-raising ceremony to celebrate the Liberation of Khanh Hoa

Hữu Long |

On the morning of April 2, Khanh Hoa province held a flag-raising ceremony to celebrate the 50th anniversary of the Provincial Liberation Day and the 50th anniversary of the Liberation of the South and National Reunification Day.

3 unfinished BT projects of Phuc Son Group in Khanh Hoa

Hữu Long |

Phuc Son Group currently has 3 BT (build - transfer) projects in Nha Trang, of which only the Ngoc Hoi Intersection project has determined the construction roadmap. The remaining two projects are currently on hold due to legal problems.