Series of resettlement areas serving the super high-speed railway project through Hue reaches the finish line

ĐẠT LUÂN |

HUE - Some resettlement areas serving the North-South high-speed railway mega-project through Hue City have been completed, and many projects are in the final sprint stage.

The first completed works

The North-South high-speed railway project section passing through Hue City is more than 95km long, passing through 12 communes and wards. The route is expected to build Phu My passenger station in Phu Thuong ward with an area of about 367ha and the potential Chan May station in Chan May - Lang Co commune.

To serve the site clearance for the national key project, Hue City must relocate 9,278 households, of which 1,368 households need to be resettled and more than 7,400 graves must be moved. The total cost for site clearance is about 6,302 billion VND.

Among the infrastructure projects serving resettlement, Phu Da resettlement area (Phu Vang commune) is one of the first projects to reach the finish line. The project has a scale of nearly 5ha, arranging 89 resettlement land plots with a total investment of about 44 billion VND.

Quang cảnh tại khu tái định cư Phú Đa (xã Phú Vang) khi vừa hoàn thiện. Ảnh: Phúc Đạt
Scene at Phu Da resettlement area (Phu Vang commune) when it was just completed. Photo: Phuc Dat

After nearly a year of construction, infrastructure systems such as leveling, internal traffic, drainage, parking lots, water supply and green trees have been completed according to the approved design.

According to the leader of the Project Management Board for Construction Investment Area 3, the units have organized construction in accordance with the design documents, fully carried out acceptance work according to legal regulations and are completing procedures for specialized agencies to inspect and hand over the project for use.

Not only Phu Da resettlement area, Phu Vang cemetery and Phu Ho cemetery areas have also been completed. These are the first projects in the group of 8 technical infrastructure projects, resettlement area and cemetery in the southern area of Hue City invested by Area 3 Construction Investment Project Management Board, with a total cost of more than 362 billion VND.

Accelerate the progress of the remaining projects simultaneously

According to the Department of Construction of Hue City, the city is implementing 33 technical infrastructure projects including resettlement areas, schools, markets and cemeteries with a total cost of about 1,807 billion VND to meet the requirements of site clearance for the North-South high-speed railway project.

The first four projects started in August 2025 have been completed on schedule. For the remaining 29 projects started at the end of 2025, investors are accelerating construction to ensure progress.

Hạ tầng khu tái định cư thuộc xã Phú Hồ cũng đang dần về đích. Ảnh: Nguyễn Luân
Infrastructure of the resettlement area in Phu Ho commune is also gradually reaching the finish line. Photo: Nguyen Luan

In the northern area of Hue City, Area 2 Construction Investment Project Management Board is implementing 14 projects with a total capital of more than 466 billion VND, including 11 resettlement areas with an area of about 31.45ha and 3 cemeteries with an area of more than 10.7ha.

In which, Phong Hien People's Cemetery is one of the completed projects, which is completing dossiers for handover and put into use. The remaining projects currently reach about 30 - 80% of the construction volume, contractors are required to accelerate progress, striving to complete the landmark planting and subdivision by the end of July.

Công nhân, máy móc tập trung thi công tại khu tái định cư ở phường Vỹ Dạ. Ảnh: Phúc Đạt
Workers and machinery focus on construction at the resettlement area in Vy Da ward. Photo: Phuc Dat

Another notable project is resettlement residential area No. 6 in Zone B - An Van Duong new urban area (Vi Da ward), with an area of 2.5ha with 74 land plots, total investment of nearly 39 billion VND. Up to now, the main items such as drainage system, asphalt concrete road surface, green trees and land subdivision have been basically completed, only some auxiliary items have been completed.

Accelerating the synchronous construction of resettlement areas is considered an important preparation step for Hue City to be ready to deploy the North-South high-speed railway project, ensuring that people subject to relocation have new accommodation with full infrastructure and stable lives.

ĐẠT LUÂN
RELATED NEWS

Site clearance for high-speed railway project in Ninh Binh faces difficulties due to relics

|

Ninh Binh - Site clearance for the high-speed railway project section passing through the province is facing difficulties because the project's route passes through some relic works.

Request to adjust the direction of the high-speed railway line to avoid encroaching on Hoa Lai tower

|

Khanh Hoa - The locality has held a meeting to discuss the planning plan for the special national relic Hoa Lai tower related to the North-South high-speed railway project.

Removing difficulties in land embankment to serve high-speed railway resettlement in Lam Dong

|

Lam Dong is focusing on removing difficulties in land filling to accelerate the progress of resettlement areas serving the North-South high-speed railway project through the area.

Trade union news: Unemployment in Hanoi mainly focuses on workers aged 25-40

|

Workers aged 25-40 account for 62.36% of unemployed people in Hanoi; Improving legal knowledge to help workers protect their rights...

German fireworks paint a fire painting in the sky of Da Nang

|

Da Nang - The fourth night of DIFF 2026 with the theme "Creation" brought an impressive competition between the German team and Macau (China).

Landslides in Vinh Long diễn biến phức tạp, damage nearly 24 billion VND

|

Vinh Long - Landslides are developing complicatedly, stretching over 5.8km, affecting 146 households, causing damage of nearly 24 billion VND.

Russia controls 94 more buildings, eliminating 95 Ukrainian soldiers in Konstantinovka

|

Russia on June 20 said that forces of the Southern Operations Group have controlled 94 more buildings in Konstantinovka in the past 24 hours.

876m of road built for 11 years not completed, Quang Ngai provincial leaders direct removal

|

Quang Ngai - The Chu Van An road project section from Hai Ba Trung - Ngo Si Lien is 876m long, but after 11 years of implementation it has not been completed.

Site clearance for high-speed railway project in Ninh Binh faces difficulties due to relics

NGUYỄN TRƯỜNG |

Ninh Binh - Site clearance for the high-speed railway project section passing through the province is facing difficulties because the project's route passes through some relic works.

Request to adjust the direction of the high-speed railway line to avoid encroaching on Hoa Lai tower

Hữu Long |

Khanh Hoa - The locality has held a meeting to discuss the planning plan for the special national relic Hoa Lai tower related to the North-South high-speed railway project.

Removing difficulties in land embankment to serve high-speed railway resettlement in Lam Dong

Duy Tuấn |

Lam Dong is focusing on removing difficulties in land filling to accelerate the progress of resettlement areas serving the North-South high-speed railway project through the area.