876m of road built for 11 years not completed, Quang Ngai provincial leaders direct removal

ĐÔNG GIANG |

Quang Ngai - The Chu Van An road project section from Hai Ba Trung - Ngo Si Lien is 876m long, but after 11 years of implementation it has not been completed.

On June 20, Mr. Do Tam Hien - Vice Chairman of Quang Ngai Provincial People's Committee - chaired a meeting to listen to reports on the progress of projects invested by the Provincial Land Fund Development Center.

According to the report at the meeting, the Chu Van An Street and Residential Area project (section from Hai Ba Trung street to Ngo Sy Lien street, Nghia Lo ward) was approved in 2013.

Ông Đỗ Tâm Hiển yêu cầu bắt buộc phải thông tuyến dự án Đường Chu Văn An và Khu dân cư (đoạn từ đường Hai Bà Trưng đến đường Ngô Sỹ Liên) trong năm 2026. Ảnh: Tăng Thư
Vice Chairman of Quang Ngai Provincial People's Committee Do Tam Hien requested the opening of the Chu Van An Road and Residential Area project (section from Hai Ba Trung street to Ngo Sy Lien street) in 2026. Photo: Tang Thu

By 2024, through inspection, some violations were discovered in the planning work. In which, the inspection agency pointed out the retention of 6 self-renovation areas not included in the plan, with an area of more than 1 hectare.

The Provincial Land Fund Development Center is reviewing all land plots in the plan to have a basis for advising competent authorities to handle according to the recommendations of the inspection agency.

For the Hai Ba Trung South Residential Area project (phase 1), Nghia Lo ward, the project was approved in 2016 with a total investment of 246 billion VND.

To date, the project has cleared 7/11.4 hectares of land. The Center recommends that for compensation plans that have been approved and households that have received money, continue to accelerate the implementation progress according to the inspection conclusion.

For households that have not received compensation, the Center proposes to consider developing a plan to cancel and finalize the completed volume to implement a new project.

Mr. Do Tam Hien said that because the projects have been implemented through many periods, with many different mechanisms, it is necessary to carefully study and apply the compensation mechanism in the direction that is most beneficial to the people. Regarding the Chu Van An Road and Residential Area project (section from Hai Ba Trung street to Ngo Sy Lien street), it is required to open the route in 2026.

If capital is lacking, the Provincial Land Fund Development Center must report to the Provincial People's Committee in June 2026 for the province to direct the Department of Finance to propose timely allocation of capital.

Dự án đường Chu Văn An, đoạn từ đường Hai Bà Trưng - Ngô Sĩ sau hàng chục năm triển khai vẫn dang dở. Ảnh: Đông Giang
The Chu Van An road project, the section from Hai Ba Trung - Ngo Si street, is still unfinished after decades of implementation. Photo: Dong Giang

The Chu Van An road project (section from Hai Ba Trung street to Ngo Sy Lien street) is 876 m long, but after 11 years of implementation, it is still unfinished. Currently, the road is always in a dusty and muddy situation, causing people to be very upset.

The project was initially assigned to the People's Committee of Quang Ngai City (old) as the investor. In 2015, the People's Committee of Quang Ngai province transferred both the road and residential area to Quang Ngai Construction Investment and Service Business Co., Ltd. (QISC) as the investor.

After officially starting in 2016, the 876m long road began to be constructed. However, by 2020, Quang Ngai Provincial People's Committee again assigned the project to Quang Ngai City (old) People's Committee as the investor.

According to the conclusion of the Quang Ngai Provincial Inspectorate in 2023, the reason for the slow progress of the project is that there is no regulation allowing QISC Company to be assigned to manage and use state budget capital to invest in building works and residential areas that the company will manage and exploit later.

Therefore, the transfer by the Chairman of the Provincial People's Committee from the People's Committee of Quang Ngai City (old) to QISC Company as the investor of the Southern Residential Area project of Hai Ba Trung street and the Chu Van An Street project (section from Hung Vuong street to Hai Ba Trung street) is without legal basis and not in accordance with the functions and tasks of the company.

QISC Company's self-organization of the work of preparing compensation plans without experience and limited professional capacity has led to delays in compensation work, causing the project to not ensure progress and having to adjust the implementation time.

ĐÔNG GIANG
RELATED NEWS

Chairman of Quang Ngai Provincial People's Committee directs to remove obstacles and accelerate construction of schools in border areas

|

Quang Ngai - Despite facing difficulties in manpower and weather, the projects of ethnic minority boarding schools in the border area are still being accelerated.

Accelerate completion of 4 inter-level boarding schools in border communes of Quang Ngai

|

Quang Ngai is urgently completing facilities to put 4 ethnic minority boarding schools in border communes into operation from the 2026 - 2027 school year.

Reviewing and removing difficulties for 111 projects in Quang Ngai

|

Quang Ngai is focusing on removing obstacles for 111 backlog and prolonged projects, of which 61 projects are expected to apply special mechanisms.

Trade union news: Unemployment in Hanoi mainly focuses on workers aged 25-40

|

Workers aged 25-40 account for 62.36% of unemployed people in Hanoi; Improving legal knowledge to help workers protect their rights...

German fireworks paint a fire painting in the sky of Da Nang

|

Da Nang - The fourth night of DIFF 2026 with the theme "Creation" brought an impressive competition between the German team and Macau (China).

Landslides in Vinh Long diễn biến phức tạp, damage nearly 24 billion VND

|

Vinh Long - Landslides are developing complicatedly, stretching over 5.8km, affecting 146 households, causing damage of nearly 24 billion VND.

Russia controls 94 more buildings, eliminating 95 Ukrainian soldiers in Konstantinovka

|

Russia on June 20 said that forces of the Southern Operations Group have controlled 94 more buildings in Konstantinovka in the past 24 hours.

876m of road built for 11 years not completed, Quang Ngai provincial leaders direct removal

|

Quang Ngai - The Chu Van An road project section from Hai Ba Trung - Ngo Si Lien is 876m long, but after 11 years of implementation it has not been completed.

Chairman of Quang Ngai Provincial People's Committee directs to remove obstacles and accelerate construction of schools in border areas

ĐÔNG GIANG |

Quang Ngai - Despite facing difficulties in manpower and weather, the projects of ethnic minority boarding schools in the border area are still being accelerated.

Accelerate completion of 4 inter-level boarding schools in border communes of Quang Ngai

ĐÔNG GIANG |

Quang Ngai is urgently completing facilities to put 4 ethnic minority boarding schools in border communes into operation from the 2026 - 2027 school year.

Reviewing and removing difficulties for 111 projects in Quang Ngai

ĐÔNG GIANG |

Quang Ngai is focusing on removing obstacles for 111 backlog and prolonged projects, of which 61 projects are expected to apply special mechanisms.