Dust of clean land in Phu Tho's largest industrial park

Tô Công |

Phu Tho - After many years of focusing on site clearance, Cam Khe Industrial Park - the largest industrial park in Phu Tho province has hundreds of hectares of clean land.

Cam Khe Industrial Park is located in Cam Khe town and Phong Thinh commune (before merging the administrative unit of Xuong Thinh commune), with a planned area of up to 450 hectares, this is the largest industrial park in Phu Tho province.

Khu cong nghiep Cam Khe. Anh: To Cong.
Cam Khe Industrial Park. Photo: To Cong.

The Cam Khe Industrial Park Infrastructure Investment, Construction and Business Project is a key project of Phu Tho province. The total planned area of 450 hectares includes 2 component projects: Road connecting National Highway 32C to the Industrial Park and Pumping Station (22.7 hectares); Investment and business in industrial park infrastructure (427.3 hectares).

Mat bang rong lon duoc san gat. Anh: To Cong.
The large area has been leveled. Photo: To Cong.

According to the reporter of Lao Dong Newspaper in mid-March, Cam Khe Industrial Park currently has many factories in operation, many of which are under construction. Along with that, the large premises have been leveled, ready to welcome the "eagle".

Mot nha may san xuat man hinh dang duoc xay dung. Anh: To Cong.
A screen factory is under construction. Photo: To Cong.

Ms. Le Thi Hien (a resident of Nhat Tien commune, Cam Khe district) - a worker in Cam Khe industrial park - shared: "Compared to previous years when it was somewhat desolate, the industrial park is now always bustling, bustling with the sound of excavators, trucks making the ground with the sound of welding machines, the sound of workers in factories under construction... I am happy because my hometown is developing industry, workers have more jobs".

However, to achieve the above, the project to build this industrial park has gone through many difficulties and problems in site clearance. As many articles have been reported by Lao Dong, many households and individuals do not cooperate in the work of counting, reviewing, receiving compensation, support, and resettlement funds for projects, and there are even cases of intentional expansion and installation of illegal constructions and architectural works to take advantage of policies...

Xung quanh cac mat bang, ha tang ky thuat dang duoc xay dung. Anh: To Cong.
Around the site, technical infrastructure is under construction. Photo: To Cong.

To speed up the site clearance progress, along with promoting propaganda and mobilizing people, thoroughly answering questions and meeting people's wishes within the framework of legal regulations, Cam Khe district has in recent years strongly implemented construction protection and forced land acquisition with many cases of deliberately sluggishness, opposing the State's policies.

According to the latest report of the Land Fund Development Center of Cam Khe district, up to now, 351.52/427.3 hectares of land have been cleared; the Provincial People's Committee has approved the change of land use purpose and allocated land to the investor for an area of 139.5 hectares; is completing the dossier to submit to the Provincial People's Committee for approval of the change of land purpose in phase 2 with an area of 193.8/211.75 hectares of land that have been cleared.

Cac mat bang cho “dai bang” ve “lam to“. Anh: To Cong.
The vast premises are ready to welcome investors. Photo: To Cong.

With an area of 183.4 hectares of " sticky rice and bean", up to now, 182.66 hectares of cleared land have been cleared, the remaining 0.74 hectares of the remaining 10 cases are concentrated in Phong Thinh commune - related to residential land and agricultural land (Phong Thinh Commune People's Committee organizes approval of land origin because these cases do not have land use right certificates) are currently in the process of implementation.

Tô Công
RELATED NEWS

Stewed ground, 11,000 billion VND expressway still bustling for construction

|

Lang Son - Despite many problems with the site clearance, the Huu Nghi - Chi Lang expressway is being vigorously implemented to reach the finish line on time.

Environmental survey in the oldest industrial park in Vietnam

|

Dong Nai - The Department of Agriculture and Environment surveyed and monitored Bien Hoa 1 Industrial Park (which is being relocated to change function) showing signs of high pollution.

Di An City will gradually transform the functions of 6 industrial parks

|

Binh Duong - Di An City has 6 industrial parks that will gradually change their functions to develop urban areas, services and create a better living space for people.

Vingroup has filed a lawsuit against Facebook account owner Hien Nguyen in a court in the US

|

Vingroup sued Facebooker Hien Nguyen in a US court for posting false information, demanding an end to his behavior and compensation for damages.

Young man was beaten to death by lightning while watching a phone in the house

|

Ha Tinh - A young man in Huong Xuan commune was suddenly hit by lightning while watching his phone.

Proposing the Government to strictly control gold prices and foreign exchange rates

|

The Standing Committee of the Petition and Supervision Committee recommended that the National Assembly Standing Committee propose that the Government strengthen the management and control of gold prices and foreign exchange rates.

Appointment of 4 members of the Board of Directors of the Social Policy Bank

|

The Prime Minister decided to appoint 3 deputy ministers and 1 secretary of the Central Youth Union to concurrently hold the position of member of the Board of Directors of the Bank for Social Policies.

Governor of the State Bank of Vietnam Nguyen Thi Hong is ranked A+ by Global Finance

|

The Central Bank Governor's Ranking Report has been published annually by Global Finance since 1994.

Stewed ground, 11,000 billion VND expressway still bustling for construction

Khánh Linh |

Lang Son - Despite many problems with the site clearance, the Huu Nghi - Chi Lang expressway is being vigorously implemented to reach the finish line on time.

Environmental survey in the oldest industrial park in Vietnam

HÀ ANH CHIẾN |

Dong Nai - The Department of Agriculture and Environment surveyed and monitored Bien Hoa 1 Industrial Park (which is being relocated to change function) showing signs of high pollution.

Di An City will gradually transform the functions of 6 industrial parks

ĐÌNH TRỌNG |

Binh Duong - Di An City has 6 industrial parks that will gradually change their functions to develop urban areas, services and create a better living space for people.