Red book wrong with current status causes difficulties in site clearance in Phu Tho

Xuyên Đông |

Phu Tho - Many localities have not completed the inventory and site clearance work. One of the reasons is that the area in the red book is not consistent with the current situation.

According to the Phu Tho Provincial Portal, on April 10, Mr. Tran Duy Dong - Chairman of Phu Tho Provincial People's Committee - inspected the progress of a number of projects in Hoa Binh area.

The working delegation inspected the road project connecting Tran Hung Dao street to Dan Chu ward connecting to National Highway 6, now belonging to Hoa Binh and Thong Nhat wards.

The project is expected to be completed in 2026, however, so far the volume has only reached 53.3% of the contract value. The main reason is that the relocation of technical infrastructure is still problematic.

The contractor is deploying the construction of road surface items, completing curbs, sidewalk curbs, clean water supply pipes, green trees, and sidewalks.

However, site clearance work is still slow, only 1.7/2km has been handed over. The reason is that the locality has not publicly posted the expected plan, and some households have not determined the origin of land and type of land.

The working delegation also inspected the project to connect traffic and irrigation in Hoa Binh province with the national transport infrastructure system using ODA loans from Korea, in the wards: Hoa Binh, Ky Son, Thong Nhat.

With a total investment of 2,600 billion VND (of which, ODA loan capital is 1,150 billion VND), the project includes 2 components: component 1 upgrading National Highway 6 section from km64+500 to through Chi Lang intersection, ending point at km73 + 450.1 with a total length of 8.95km; component 2 strengthening flood prevention capacity combined with urban infrastructure of Hoa Binh city with 4 items.

Up to now, wards have issued notices of land recovery, and have been and are conducting inventory and counting of land and assets on land.

It is expected that the construction drawing design and post-verification estimate will be completed in 2026; in the third quarter of 2026, bidding will be held to select construction contractors.

However, to date, localities have not completed the inventory work because organizations, households, and individuals have not coordinated; locations and areas are overlapping due to deductions from cadastral maps, plot numbers, areas deviating from land use right certificates and current status deductions.

Chairman of Phu Tho Provincial People's Committee Tran Duy Dong also listened to representatives of investors report on the progress of the Trung Minh A, Trung Minh B new urban area project.

The Trung Minh A and Trung Minh B new urban area projects, in Hoa Binh ward, have basically completed site clearance and procedures in investment preparation.

The investor is waiting to complete land allocation procedures to implement the project and will proceed with construction. However, there are still obstacles in land clearance for residential land and perennial crop land of households; overlapping planning at the Trung Minh B New Urban Area project; land clearance for 35kV, 22kV, 0.4kV power lines and transformer stations...

At project inspection points, Chairman of Phu Tho Provincial People's Committee Tran Duy Dong requested localities with projects and routes passing through to urgently accelerate the progress of site clearance work.

For the 2 connecting road projects, the Chairman of the Provincial People's Committee assigned the Provincial Police to preside over and coordinate with relevant units to have a plan to ensure security and order and measures for cases of intentional delay, obstruction, and opposition in site clearance work.

For other obstacles, assign the Hoa Binh Regional Project Management Board and the Hoa Binh Regional Land Fund Development Center to preside over and coordinate with localities to urgently complete the compensation and support for relocation and resettlement for people in accordance with legal regulations.

Chairman of Phu Tho Provincial People's Committee Tran Duy Dong assigned departments, branches, and localities to closely coordinate with investors to focus on removing difficulties and obstacles, striving to start the project by April 30, 2026.

Before May 30, complete the relocation and site clearance for organizations and businesses located on the project area, ensuring progress, promoting investment efficiency, contributing to promoting urban development and social security in the province.

Xuyên Đông
RELATED NEWS

Phu Tho has 354 people terminating unemployment insurance benefits in the first quarter of 2026

|

Phu Tho - In the first quarter of 2026, the whole province had 236 people temporarily suspended, 354 people terminated unemployment insurance benefits.

Ministry of Agriculture and Environment answers about first-time red book issuance after merger

|

The Ministry of Agriculture and Environment answers citizens about the first-time issuance of red books after the merger.

Measles increases, many people actively get vaccinated before pregnancy

|

Faced with the increasing trend of suspected measles cases, many women planning to become pregnant have proactively vaccinated against the disease, protecting a safe pregnancy.

The case of the former principal collecting 15,000 VND for tutoring and being sentenced to 3 years in prison makes National Assembly deputies heartbroken

|

Referring to the case of the former principal collecting 15,000 VND for tutoring and being sentenced to 3 years in prison, delegate Pham Khanh Phong Lan (Ho Chi Minh City delegation) said that this is a "very painful" case.

Overnight control of forest fires in Lam Dong

|

Lam Dong - Dozens of people were mobilized overnight to extinguish the fire, promptly controlling the forest fire that occurred in Tan Hoi commune.

Iran wants oil tankers passing through the Strait of Hormuz paid by electronic money

|

Iran's new move shows efforts to adapt to financial sanctions pressure and global geopolitical volatility.

Stock market regains green color in last week's session

|

Cash flow returned with the focus being bank stocks, which helped the stock market regain its green color.

Live futsal selection Vietnam vs Indonesia in the semi-finals of the Southeast Asia tournament

|

Live football match of Vietnam futsal team vs Indonesia in the semi-finals of the 2026 Southeast Asian Futsal Championship at 5:00 PM today (April 10).

Thêm 1 lãnh đạo bị bắt vụ xã hội đen đội lốt doanh nghiệp ở Phú Thọ

Tô Công |

Phú Thọ - Một vị lãnh đạo của UBND TP Phúc Yên, tỉnh Vĩnh Phúc cũ đã bị bắt do dính líu đến vụ án xã hội đen đội lốt doanh nghiệp.

Phu Tho has 354 people terminating unemployment insurance benefits in the first quarter of 2026

Xuyên Đông |

Phu Tho - In the first quarter of 2026, the whole province had 236 people temporarily suspended, 354 people terminated unemployment insurance benefits.

Ministry of Agriculture and Environment answers about first-time red book issuance after merger

Nhóm PV |

The Ministry of Agriculture and Environment answers citizens about the first-time issuance of red books after the merger.