On May 19, according to information from the People's Committee of Thai Nguyen province, this unit has just issued a Decision to reclaim nearly 30,000m2 of land from Phuc Thai Industrial, Trade and Medical Services Joint Stock Company (Phuc Thai Company) for violating land laws.
This is the area assigned to implement the Phuc Thai General Hospital Construction Investment Project according to Decision No. 732 dated April 11, 2012.

However, after many years of land lease, the enterprise has not been able to arrange capital, leading to the project being behind schedule in land use.
In that situation, the Provincial People's Committee assigned the Department of Agriculture and Environment to preside over land recovery, organize handover on site, and revoke land use right certificates and ownership of assets attached to land.
In case the enterprise does not submit the relevant documents, the Department will advise the Provincial People's Committee to issue a decision to cancel the issued certificates.
The Song Cong City Land Fund Development Center is assigned to receive and manage recovered land funds in accordance with planning and legal regulations.
At the same time, the Tax Department of Region VII will coordinate with relevant departments and branches to inspect, determine and handle the financial obligations of the project in accordance with regulations.

The Phuc Thai Multi-Department Hospital project was first granted an investment certificate (IC) by the Thai Nguyen Provincial People's Committee on March 8, 2010.
Type 3 Hospital project with phase 1 being 100 beds and 1 nursing area. The total investment capital is more than 296 billion VND.
According to the schedule, the project will be implemented in the first quarter of 2010, completed and put into use in the fourth quarter of 2011.

However, by the end of 2011, Phuc Thai Company still did not implement it. On May 15, 2012, the People's Committee of Thai Nguyen province signed the first adjustment of the PIT, raising the investment capital to more than VND 2,000 billion. The scale of the project has also been increased to 600 hospital beds in 2 phases.
The progress was adjusted to the groundbreaking, construction phase 1 was completed in August 2012, and put into operation in the fourth quarter of 2013. Phase 2 will be built in the first quarter of 2016 and completed in the fourth quarter of 2018.
By the end of 2012, there was still no groundbreaking ceremony. Although Phuc Thai Company was allocated the site in January 2012 on site, in April 2012 it signed a land lease contract with the state.
It was not until the end of March 2013 that this project was started. However, after nearly a year, the construction suddenly stopped when the 5-storey building frame was just completed.