200 billion VND headquarters in Lao Cai is at risk of missing the 2025 deadline

Đinh Đại |

Lao Cai - The administrative headquarters of the old Bao Thang district with an investment capital of 200 billion VND is at risk of not being completed in time in 2025.

On November 24, Lao Dong Newspaper's reporter in Bao Thang commune, standing from Pho Lu bridge, can easily observe the administrative headquarters of the old Bao Thang district gradually taking shape after 2 years of construction.

According to local people, the new construction is necessary because the old district headquarters has degraded, no longer meeting the working needs of cadres, civil servants and serving the people.

Trung tam hanh chinh xa Bao Thang, tinh Lao Cai dang do hoan thien. Anh: Dinh Dai
The Bao Thang Commune Administrative Center, Lao Cai Province is being completed. Photo: Dinh Dai

According to research, the new headquarters of the Bao Thang District Administrative Center (now Bao Thang Commune) was built on the old headquarters.

The architectural scale of the office is 15 stories high, with 3 floors of the base and 12 floors of the tower, the construction area is 3,370m2, the total floor area is 13,591m2. The investment cost of the project is 200 billion VND, with the old Bao Thang District Investment and Construction Project Management Board as the investor's representative.

The project is undertaken by a joint venture of Dong A Import-Export Production Joint Stock Company, 19-18 Construction Company Limited, Hong River Electromechanical Construction and Installation Joint Stock Company and Tinh Tho - Dys mid-diseasectrification Company Limited.

Cac hang muc dang duoc day manh thi cong. Anh: Dinh Dai
The construction of items is being accelerated. Photo: Dinh Dai

The project uses modern materials and lines in line with the world's development trend.

The 15-storey tower block is the workplace of functional departments and offices. The 3-storey base block has a 500-seat hall and reception and traditional rooms... The 5-storey guest house and dining block includes a service area, dining room and about 30 rooms.

At the time of recording, at the construction site, workers were carrying out construction activities and transporting materials to the project's floors. At the same time, the building is still being paved with walls and roughly built.

However, at the construction site, the equipment of protective equipment and labor safety for workers has not been guaranteed, such as lack of helmets, lack of safety belts for workers at the elevated level...

Cong nhan lam tren cao nhung thieu day bao ho. Anh: Dinh Dai
Workers work at high ground but lack protective ropes. Photo: Dinh Dai

Regarding this, Mr. Do Dinh Hai - Supervisor - Lao Cai Industrial Consulting Company Limited admitted - there are cases where workers are not fully equipped and do not ensure labor safety.

According to Mr. Hai, these errors are entirely due to workers and laborers. Because when the unit goes to inspect, the workers will be equipped with protective gear. But after checking, they dropped it.

"Every day, we still check the workers to see if labor safety has been ensured or not. Equipping safety helmets and shirts, working at a height of 2m or more must have a seat belt and be reminded regularly. The problem of workers not being equipped with enough protective equipment may be due to not being able to check closely, so such a situation has occurred," Mr. Do Dinh Hai explained.

Cong trinh co nguy co lo hen ve dich nam 2025. Anh: Dinh Dai
The project is at risk of missing the 2025 completion date. Photo: Dinh Dai

According to the Bao Thang Construction Investment Project Management Board, the completion and handover of the new administrative center to use in 2025 is very difficult due to many unfinished items, especially the interior packages that are still waiting for approval.

However, the construction unit will speed up the construction process, trying to basically complete the project soon.

Speaking to Lao Dong Newspaper, Deputy Director of the Bao Thang Construction Investment Project Management Board Vu Hong Ha said: "The commune administrative department is currently entering the completion stage. In the coming time, we will increase labor and equipment to speed up the progress. Expected to be put into use in the first quarter of 2026.

Đinh Đại
RELATED NEWS

Waiting for the 100 billion VND inter-commune traffic project in Lao Cai

|

Lao Cai - Quy Mong - Kien Thanh route with a total investment of 100 billion VND is under construction in the drainage phase to make it more convenient for people to travel.

Red River Festival 2025 opens brilliantly in Lao Cai

|

Lao Cai - The opening ceremony of the 2025 Red River Festival attracted a large number of delegates and thousands of people and tourists.

Reasons for the 50 billion VND anti-landslide embankment project in Lao Cai being behind schedule

|

Lao Cai - Up to now, the anti-landslide embankment project in Cam Duong ward has been behind schedule and the completion time has been extended to December 31.

Creating a legal corridor to protect the press from fake news and digital platforms

|

National Assembly deputies proposed creating a legal corridor to protect the press from fake news and digital platforms, and protect the safety of journalists during their work.

With assets increasing sharply, Mr. Pham Nhat Vuong is about to enter the top 100 richest people in the world

|

Billionaire Pham Nhat Vuong - Chairman of Vingroup Corporation climbed to the 102th richest people on the planet, according to the latest update from Forbes.

Welcoming storm No. 15 in the East Sea in the next 24 hours, the risk of strengthening to level 12

|

According to the meteorological agency, in the next 24 hours, the tropical depression is forecast to enter the East Sea and strengthen into storm No. 15.

Cattle are free to roam, lined up on the road to Cat Ba, Hai Phong

|

Hai Phong - Cat Hai Special Zone has just issued instructions to prevent traffic safety risks from free-range cattle.

Khanh Hoa announces 48 focal points for relief teams to help people after floods

|

Khanh Hoa - To promptly support people affected by the recent floods, the locality has provided information about 48 points of contact to receive relief goods.

Waiting for the 100 billion VND inter-commune traffic project in Lao Cai

Đinh Đại |

Lao Cai - Quy Mong - Kien Thanh route with a total investment of 100 billion VND is under construction in the drainage phase to make it more convenient for people to travel.

Red River Festival 2025 opens brilliantly in Lao Cai

Đinh Đại |

Lao Cai - The opening ceremony of the 2025 Red River Festival attracted a large number of delegates and thousands of people and tourists.

Reasons for the 50 billion VND anti-landslide embankment project in Lao Cai being behind schedule

Đinh Đại |

Lao Cai - Up to now, the anti-landslide embankment project in Cam Duong ward has been behind schedule and the completion time has been extended to December 31.