Waiting for the 100 billion VND inter-commune traffic project in Lao Cai

Đinh Đại |

Lao Cai - Quy Mong - Kien Thanh route with a total investment of 100 billion VND is under construction in the drainage phase to make it more convenient for people to travel.

The Quy Mong - Kien Thanh route is more than 13km long, with a total investment of 100 billion VND these days, always bustling with the sound of the engine.

When the site was handed over, the construction unit mobilized machinery to speed up the progress of each item.

It is known that as soon as the commune officials informed that the road would pass through the family's garden, Ms. Ha Thi Ly in Kien Lao village did not hesitate to agree to donate more than 500m2 of land, dismantle fences and trees to make the project go smoothly.

Ms. Ly's story is also the common sentiment of more than 300 households here, who have voluntarily donated more than 300,000m2 of land to the project.

"The state has built a road to the commune, we are very excited. The land is both convenient for construction and makes our hometown more beautiful, making travel easier," Ms. Ly happily said.

Nguoi dan xa Quy Mong, tinh Lao Cai dong thuan hien dat de mo duong to dep. Anh: Thanh Hung
People in Quy Mong commune, Lao Cai province agreed to donate land to open a large and beautiful road. Photo: Thanh Hung

From those rustic thoughts, the land donation movement spread quickly, like a warm spark in the hearts of the people of Quy Mong.

Some contributed a few hundred meters, some demolished the gate, some cut down trees, some moved the barn. No one told anyone but everyone shared the same desire to make the road more straight, wider, cleaner and more beautiful.

Thanks to the support of the people, the site clearance of the traffic project worth more than 100 billion VND was completed quickly.

At the construction site, dozens of vehicles are working continuously. The soil is tightly rolled, the roadbed is flattened, and every corner is straightened.

Not only the sound of the machines, but also the people's rhythm, the rhythm of perseverance, of the desire to soon complete the project to serve the people.

Nhieu may moc cung lao dong thi cong de som hoan thien du an. Anh: Thanh Hung
Many machines and workers are working to complete the project soon. Photo: Thanh Hung

Mr. Tran Tinh Phuong - Construction Team Leader of Yen Bai Traffic Construction Joint Stock Company - said: "The women voluntarily donated land, so when we entered, there was a site for immediate implementation".

According to the representative of Luong Gia Company Limited, the construction volume is currently about 60%, the unit aims to hand over its work before December 15 so that the entire route can be put into use before the Lunar New Year 2026.

For people, the new route not only shortens travel distance but also opens up hope for economic development.

Ms. Nguyen Thi Lan (residing in Kien Lao village) said: "We did not dare to go fast on this route, because the road was very bad. Now that there is a new road, the people are extremely excited and very supportive because in the future, traveling or transporting goods will be more convenient and safer."

Tuyen giao thong to dep, dong bo se giup phat trien kinh te dia phuong. Anh: Thanh Hung
The large and beautiful, synchronous traffic route will help develop the local economy. Photo: Thanh Hung

When completed, the Quy Mong - Kien Thanh route will be an important traffic route, creating conditions to attract investment in the thousands of hectares of Bat Do cinnamon and bamboo shoots production area.

According to Mr. Luong Cong Hien - Head of the Economic Department of Quy Mong commune, after being put into use, with a small slope, a wider road will attract investors to implement projects to process cinnamon and Bat Do bamboo shoots. Currently, a number of investors have conducted surveys to implement the project.

Mot so hinh anh ghi nhan vao thang 5.2024 ve tuyen duong Quy Mong–Kien Thanh xuong cap, hu hong truoc khi nang cap. Anh: Dinh Dai
Some images recorded in May 2024 of the Quy Mong - Kien Thanh route were degraded and damaged before upgrading. Photo: Dinh Dai

Previously, on May 20, 2024, Lao Dong Newspaper published an article "An inter-commune road in Yen Bai is deteriorating, people are tired of waiting for repairs", reflecting that the road from Quy Mong commune to Kien Thanh commune has been seriously degraded after a long period of no restoration or repair, endangering people's travel.

According to the reporter's records at that time, the road has many sections of the road with all the asphalt layer, some locations have exposed dangerous slippery soil, a series of potholes and potholes with stagnant water after the rain, vehicles have to struggle to move here.

Đinh Đại
RELATED NEWS

Lao Cai grassroots trade union starts new term with the goal of innovation

|

Lao Cai - At the 2025 - 2030 term conference, the grassroots trade union of the Provincial Federation of Labor deployed the task of focusing on the grassroots and improving the rights of union members.

Current status of 2 hundred-billion-dong embankment projects to prevent landslides in Lao Cai

|

Lao Cai - Two embankment projects in Cam Duong ward with a total investment of more than 100 billion VND are being accelerated to ensure the safety of the people.

Information on the results of the 14th Conference of the 13th Party Central Committee

|

The Party Committee of the Fatherland Front (FFF) and Central organizations quickly announced the results of the 14th Central Conference.

Draft US 28-point peace plan for Russia - Ukraine

|

The US 28-point peace plan is not easy for Ukraine because Kiev must give up more territory and never join NATO.

Forecast of provinces and cities continuing to have heavy to very heavy rain, warning of dangerous weather

|

From November 21 to the end of the night of November 22, the eastern provinces from Da Nang City to Dak Lak and the northern part of Khanh Hoa province will have some places with very heavy rain.

Retail businesses in Ho Chi Minh City increase supply assurance before floods

|

HCMC - Retail systems in HCMC are simultaneously activating solutions to stabilize supply and strong subsidy to share spending pressure with people.

Establishing a station to receive and distribute flood relief in Gia Lai

|

Today, the authorities continue to increase human resources to rescue people in flooded areas of Gia Lai, Dak Lak, Khanh Hoa, and deploy relief as a necessity.

Many hotels and schools in Nha Trang welcome people fleeing floods

|

Some units, hotels and schools in Nha Trang have opened their doors for people to evacuate for free.

Lao Cai grassroots trade union starts new term with the goal of innovation

Huyền Thúy |

Lao Cai - At the 2025 - 2030 term conference, the grassroots trade union of the Provincial Federation of Labor deployed the task of focusing on the grassroots and improving the rights of union members.

Current status of 2 hundred-billion-dong embankment projects to prevent landslides in Lao Cai

Đinh Đại |

Lao Cai - Two embankment projects in Cam Duong ward with a total investment of more than 100 billion VND are being accelerated to ensure the safety of the people.

Một đường liên xã ở Yên Bái xuống cấp, người dân mỏi mòn đợi tu sửa

Đinh Đại |

Con đường từ xã Quy Mông đến xã Kiên Thành, huyện Trấn Yên, Yên Bái, sau thời gian dài không được tu bổ, sửa chữa đã bị xuống cấp trầm trọng, gây nguy hiểm cho việc đi lại của người dân.