Giao Long Trade Union social housing must accelerate progress and ensure quality

HOÀNG LỘC |

Vinh Long - Accelerating the progress of social housing projects Giao Long Trade Union must ensure quality and safety is the requirement of the Vietnam General Confederation of Labor.

On July 9, Mr. Le Van Nghia - Vice President of the Vietnam General Confederation of Labor inspected the reality of the Giao Long Trade Union social housing project in Vinh Long province, and worked with the investor and construction unit on the project implementation progress.

At the working session, Mr. Ha Manh Cuong - Project Commander said that the project progress is currently under control thanks to proactiveness in construction organization and site management. To date, the realized value has reached about 31% of the package volume. Two blocks A2 and A3 have been unroofed in June, and the remaining items continue to be implemented according to plan.

According to the construction unit, the implementation process still faces many difficulties due to the sharp increase in fuel prices, construction materials and labor compared to the time of signing the contract. The supply of some types of materials such as sand, stone, and steel is scarce because many key projects are being implemented together, affecting the mobilization of resources and construction progress.

The contractor proposed that the investor consider adjusting prices for materials with large fluctuations, and at the same time support the disposal of waste dumps and soon complete arising procedures to create conditions to accelerate progress.

Ông Lê Văn Nghĩa - Phó Chủ tịch Tổng Liên đoàn Lao động Việt Nam kiểm tra thực tế Dự án nhà ở xã hội Công đoàn Giao Long tại tỉnh Vĩnh Long. Ảnh: Hoàng Lộc
Mr. Le Van Nghia - Vice President of the Vietnam General Confederation of Labor - inspects the reality of the Giao Long Trade Union social housing project in Vinh Long province. Photo: Hoang Loc

Speaking to direct, Mr. Le Van Nghia acknowledged the efforts of the investor, construction unit and forces at the construction site; requested units to organize synchronous construction throughout the project, not deploying individual blocks. In particular, it is necessary to focus manpower and equipment to accelerate progress in blocks A1 and A4, overcome the situation of slow construction, and ensure completion on schedule.

Mr. Le Van Nghia also requested to urgently complete the sample room; study plans to complete ceiling, walls, and tiles appropriately, ensuring quality, aesthetics and functionality. Construction must aim to create a comfortable living space, bringing comfort to union members and workers after each working day.

In addition, the Vice President of the Vietnam General Confederation of Labor requested to tighten the work of safety, occupational hygiene and environmental sanitation at the construction site; rectify the collection and treatment of construction waste, strictly implement the requirement "clean up to where done".

Units must focus maximum resources to accelerate progress but absolutely not trade quality and safety, ensuring the project is completed as committed.

Đoàn công tác Tổng Liên đoàn Lao động Việt Nam kiểm tra tiến độ thi công Dự án nhà ở xã hội Công đoàn Giao Long. Ảnh: Hoàng Lộc
The working delegation of the Vietnam General Confederation of Labor inspects the construction progress of the Giao Long Trade Union social housing project. Photo: Hoang Loc

The Trade Union Social Housing project in Vinh Long, invested by the Vietnam General Confederation of Labour with a capital of more than 554 billion VND, includes 699 apartments on an area of more than 3.2 hectares, with 4 7-story blocks and 2 parking blocks. The project is expected to be completed and put into use in the third quarter of 2027.

HOÀNG LỘC
RELATED NEWS

Workers expect to settle down as Giao Long social housing is gradually being completed

|

Vinh Long - Giao Long Trade Union Social Housing Project is gradually being completed, bringing joy and hope for settlement for workers in Giao Long Industrial Park.

Giao Long social housing ensures progress, tightens labor safety in construction

|

Vinh Long - Social housing of nearly 700 apartments is being accelerated, focusing on labor safety, creating a stable working environment, and limiting risks.

Workers work in the sun during holidays at the social housing project of Giao Long Commune Trade Union

|

Vinh Long - During the April 30 - May 1 holiday, workers voluntarily stayed at the construction site in the sun, continuously constructing, contributing to the early completion of the Trade Union social housing project.

Ship capsizes in Van Don sea area, Quang Ninh, 2 people missing

|

Quang Ninh - Functional forces are urgently searching for 2 people missing in the shipwreck that occurred in the Ban Sen sea area, Van Don special zone.

Exposing yourself to the hot sun, finding names for tens of thousands of martyrs

|

Quang Tri - Exposing themselves to the hot sun to take biological samples for DNA testing, forces are contributing to finding the names of tens of thousands of unidentified martyrs.

More than 20 Hoa Sen kindergarten students hospitalized suspected of digestive disorders

|

Hanoi - After lunch and afternoon snack on July 7 at Hoa Sen kindergarten (Hoai Duc commune), more than 20 young children had to be hospitalized due to suspected signs of digestive disorders.

Workers expect to settle down as Giao Long social housing is gradually being completed

HOÀNG LỘC |

Vinh Long - Giao Long Trade Union Social Housing Project is gradually being completed, bringing joy and hope for settlement for workers in Giao Long Industrial Park.

Giao Long social housing ensures progress, tightens labor safety in construction

HOÀNG LỘC |

Vinh Long - Social housing of nearly 700 apartments is being accelerated, focusing on labor safety, creating a stable working environment, and limiting risks.

Workers work in the sun during holidays at the social housing project of Giao Long Commune Trade Union

HOÀNG LỘC |

Vinh Long - During the April 30 - May 1 holiday, workers voluntarily stayed at the construction site in the sun, continuously constructing, contributing to the early completion of the Trade Union social housing project.