The 500kV circuit 3 line will be completed before September 2

TRẦN TUẤN |

Ha Tinh - Mr. Bui Cong Cuong - Deputy Director of the Central Region Power Project Management Board - affirmed that the 500kV circuit 3 line will be completed before September 2.

On the afternoon of August 21, talking with a reporter from Lao Dong Newspaper, Mr. Bui Cong Cuong - Deputy Director of the Central Region Power Project Management Board (under the National Power Transmission Corporation) - said that currently, the The contractor is focusing maximum human, material and machinery resources to speed up progress in the last "sprint" days on the 500kV circuit 3 construction site to reach the finish line.

In addition, many forces to strengthen support for construction units on the construction site are also being actively mobilized and supported by localities.

Ha Tinh soldiers support pulling wires for the 500kV circuit 3 project in Cam Lac commune, Cam Xuyen district. Photo: Hoang Duc.
Ha Tinh soldiers support pulling wires for the 500kV circuit 3 project in Cam Lac commune, Cam Xuyen district. Photo: Hoang Duc

Construction was carried out simultaneously, working overtime at night, continuously regardless of sun or rain. In the most difficult locations, construction is currently underway at the same time in the sprint phase. Progress is increasing continuously day by day, even hour by hour, so according to Mr. Cuong, it is difficult to statistically get accurate data on progress.

However, Mr. Cuong affirmed: "We are trying to make it possible to turn on power on August 25, to hold the inauguration on August 29. Thus, it is expected to meet the completion schedule before National Day September 2 as directed by the Prime Minister."

Workers tighten the screws on the electric pole in Ha Tinh and have finished pulling the wires. Photo: Tran Tuan.
Workers tighten the screws on the electric pole in Ha Tinh and have finished pulling the wires. Photo: Tran Tuan
The group of workers in charge of the rope winch at column number 40 in Ha Tinh is working hard during the sprint period. Photo: Tran Tuan.
The group of workers in charge of the rope winch at column number 40 in Ha Tinh is working hard during the sprint period. Photo: Tran Tuan

Also according to Mr. Cuong, leaders of the National Power Transmission Corporation also continuously urged and affirmed that they will complete the 500kV circuit 3 line project before September 2.

“The technical staff and workers have been working hard and trying to speed up the progress for many months, but now there are only a few final sprint days left, so they continue to make their best efforts to complete the project. ”, Mr. Cuong further shared.

Workers focused on construction despite the scorching hot weather. Photo: Tran Tuan.
Workers focused on construction despite the scorching hot weather. Photo: Tran Tuan

Previously, on August 19, the National Power Transmission Corporation and the Northern Power Project Management Board in coordination with relevant units successfully energized 2 circuits of the 500kV 3-segment transmission line. Nam Dinh 1 thermal power plant - Pho Noi.

The 500kV circuit 3 line project from Quang Trach to Pho Noi has a total length of about 519km, passing through 9 provinces including: Quang Binh, Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, Hung Yen.

The project is invested by the National Power Transmission Corporation (EVNNPT) under Vietnam Electricity Group (EVN). The project has 1,177 column foundations, total investment of about 22,300 billion VND.

The 500kV circuit 3 line project from Quang Trach to Pho Noi has a particularly important meaning in improving the transmission capacity of the national power system, ensuring proactiveness and flexibility in direction, operation, and balance. electricity supply between regions, ensuring national energy security, contributing to ensuring sufficient and stable electricity supply for production and business and serving people's lives in localities.

According to Vietnam Electricity Group, it is expected that the project inauguration ceremony will be held before September 2, 2024, in 9 provinces in an online form.

TRẦN TUẤN
TIN LIÊN QUAN

Đồng lòng hoàn thành dự án 500kV mạch 3 đúng tiến độ

NHÓM PHÓNG VIÊN |

Công đoàn Điện lực Việt Nam đã có nhiều hoạt động tích cực đồng hành, hỗ trợ, động viên các đơn vị thi công dự án đường dây 500kV.

Tinh thần quyết tâm cao nhất trên công trình đường dây 500kV mạch 3

QUANG ĐẠI - DUY CHƯƠNG |

Chiều 21.8, Chủ tịch Tổng LĐLĐ Việt Nam Nguyễn Đình Khang cùng đoàn công tác đã đến thăm, động viên người lao động thi công dự án đường dây 500kV mạch 3 tại Nghệ An.

Đội nắng thi công nước rút công trình đường dây 500kV mạch 3

TRẦN TUẤN |

Ngày 21.8, thời tiết nắng nóng gay gắt nhưng trên công trường 500kV mạch 3 ở Hà Tĩnh, cán bộ, công nhân vẫn miệt mài thi công đẩy nhanh tiến độ để sớm về đích.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Nút giao 4 tầng sắp xây trên đại lộ Phạm Văn Đồng ở Thủ Đức

MINH QUÂN |

TPHCM - Nút giao Phạm Văn Đồng với Vành đai 2 tại TP Thủ Đức sẽ được thiết kế 4 tầng, bao gồm một hầm chui và ba cầu vượt.

INEOS đúng hay sai khi cắt hợp đồng đại sứ của Sir Alex Ferguson?

VIỆT HÙNG |

Nhìn về góc độ kinh tế, Sir Jim Ratcliffe đã đúng nhưng về mặt thương hiệu câu lạc bộ, có thể ông đã tính sai khi chấm dứt hợp đồng đại sứ thương hiệu của Sir Alex Ferguson.

Quảng Ngãi khuyến cáo không ồ ạt trồng cau

VIÊN NGUYỄN |

Giá cau ở Quảng Ngãi đạt mức kỷ lục 80.000 đồng/kg. Tuy nhiên, ngành chức năng khuyến cáo nên đa dạng hóa cây trồng, trong bối cảnh giá cau rất khó lường.

The highest spirit of determination on the 500kV circuit 3 line project

QUANG ĐẠI - DUY CHƯƠNG |

On the afternoon of August 21, Chairman of the Vietnam General Confederation of Labor Nguyen Dinh Khang and the working group visited and encouraged workers to construct the 500kV circuit 3 line project in Nghe An .

Sun team executes sprint construction of 500kV circuit 3 line project

TRẦN TUẤN |

On August 21, the weather was extremely hot, but on the 500kV circuit 3 construction site in Ha Tinh , officials and workers were still diligently working to speed up the construction progress to reach the finish line soon.