9/11 multi-level boarding schools in Cao Bang are behind schedule

Long An |

Cao Bang - Manpower shortages and unfavorable weather are the reasons hindering construction at boarding schools.

Slow progress

Although required to be completed before August 30, 2026, many projects to build inter-level boarding schools in border communes of Cao Bang province are still slow in construction progress, and some projects have only completed more than 10% of the volume.

According to research, in phase 1, Cao Bang province is deploying the construction of 11 primary and secondary boarding schools in border communes.

In which, 10 projects use state budget capital, especially Phuc Hoa Primary and Secondary Boarding School is invested from funding from Hanoi City. Each project has an average investment level of 100 - over 200 billion VND.

Dự án tại xã Đức Long đang thi công chậm nhất với 12,4%. Ảnh: Trọng Lộc
The project in Duc Long commune is being constructed the slowest with 12.4%. Photo: Trong Loc

Real-world records in early June 2026 show that only 4 projects achieved construction volumes of over 20%, including Tra Linh (55%), Ha Lang (38%), Quang Trung (27%) and Tong Cot (22%).

The remaining projects such as Lung Nam, Quang Han, Duc Long, Truong Ha, Dam Thuy, Dinh Phong and Phuc Hoa have only reached 12-20% of the volume.

Most projects with progress of less than 20% are currently only completing ground leveling, foundation construction or preparing to deploy the body of the project.

At the Duc Long Primary and Secondary Boarding School project - the project with the slowest progress, by June 9, it had only reached about 12.4% of the construction volume.

There are more than 140 people participating in construction at the construction site, including reinforcements from Military Region 1 and contractor workers.

According to the Investment and Construction Project Management Board of Cao Bang province, the project progress is affected by many objective and subjective reasons.

Dự án tại xã Lũng Nặm gặp khó khi thi công trong điều kiện đá bủa vây, phải đào, phá đi khối lượng lớn. Ảnh: Trọng Lộc
The project in Lung Nam commune faces difficulties when constructing in conditions of surrounding rocks, having to excavate and destroy large volumes. Photo: Trong Loc

These are urgent public investment projects, but so far there are no detailed instructions for this type, so the process of completing legal procedures still faces many obstacles.

The supply of materials and supplies for construction is not timely, while the construction drawing design documents, estimates and acceptance and payment procedures in some projects are still slow to complete, affecting the organization of construction and planning for the implementation of items.

Contractor lacks manpower and machinery

Another difficulty is the sharp increase in fuel and construction material prices in 2026, causing project implementation costs to far exceed initial estimates.

Meanwhile, the province's proposal to supplement investment capital has not yet been approved by competent authorities, putting great pressure on construction units.

Cao Bang is currently simultaneously implementing many key projects such as the Dong Dang - Tra Linh expressway, Bao Lac Medical Center or the Provincial Traditional Medicine Hospital.

Nguyên nhân khiến dự án tại xã Đức Long chậm tiến độ. Ảnh: Trọng Lộc
The reason why the project in Duc Long commune is behind schedule. Photo: Trong Loc
Dự án tại xã Phục Hòa - dự án được đầu tư bằng vốn hỗ trợ. Ảnh: Trọng Lộc
Project in Phuc Hoa commune - a project invested with support capital. Photo: Trong Loc

This causes the demand for construction labor to increase, leading to a shortage of labor, especially skilled labor, making it difficult to mobilize construction forces for boarding schools.

Some projects when implemented encountered difficulties when there was no water source, the project was implemented on a high hill (in Tong Cot commune). "Brothers had to go downstairs to buy and collect each water truck to bring up here to serve construction," a representative of the contractor shared.

Regarding the project in Duc Long commune, functional agencies determined that the main reason for the slow progress is that the contractor has not fully arranged manpower and equipment according to the contract. The prolonged ground leveling work makes many items unable to be deployed synchronously.

Dự án trường nội trú liên cấp Quang Trung đạt khối lượng thi công 27% trong lần báo cáo gần nhất. Ảnh: Trọng Lộc
Quang Trung Inter-level Boarding School project achieved a construction volume of 27% in the most recent report. Photo: Trong Loc

Faced with the above situation, the Management Board of Investment and Construction Projects of Cao Bang province requested contractors to urgently supplement manpower and equipment, rebuild the detailed progress for each item, organize multi-pronged and multi-shift construction to ensure the goal of completion and putting the works into use before August 30, 2026.

The investor agency also requested supervision consulting units to strengthen on-site inspection, promptly detect and handle existing problems, ensure quality, labor safety and project progress.

Trường nội trú liên cấp Trà Lĩnh là dự án đạt tiến độ tốt nhất, có thể về đích đúng hẹn vào ngày 30.8. Ảnh: Trọng Lộc
Tra Linh Inter-level Boarding School is the project with the best progress, which can be completed on schedule on the 30th. 8. Photo: Trong Loc

It is known that, in the face of the slow progress of projects, Cao Bang Provincial People's Committee has proposed to mobilize maximum forces, focusing on definitively resolving 2 projects with completed volumes on schedule to "reach the finish line" on August 30, including schools in Tra Linh and Ha Lang communes.

For projects at risk of delay, priority should be given to some essential items such as classroom areas, dining halls, and dormitories to meet the immediate learning and living needs of students, especially students in remote communes.

Long An
RELATED NEWS

Lang Son urgently builds 7 multi-level boarding schools in border commune

|

Lang Son - 7 boarding schools in border communes are being urgently deployed.

Overview of 11 boarding school projects in Cao Bang ahead of schedule

|

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.

Lao Cai announces enrollment plan for 4 boarding schools in border areas

|

Lao Cai - The province has just approved the enrollment plan for boarding primary and secondary schools in 4 border communes.

Gold rings attract customers, many people are still waiting to buy

|

Domestic gold prices on June 16 remained stable compared to yesterday. At some stores in Hanoi, the number of customers coming to trade is still quite large, mainly buying gold rings.

Driver steps out of cabin after truck overturns

|

HUE - After a collision with a car, the male driver stepped out of the truck cabin in a state where the car's glass was broken and it overturned at the highway access road intersection.

Bad news

|

Lao Dong Newspaper and the family are deeply saddened to report:

Ready to provide direct legal advice to thousands of workers and laborers

|

Many problems will be answered at the Legal Consulting Program organized by Lao Dong Newspaper, Vietnam Bar Federation and Ho Chi Minh City Labor Federation on June 21.

Lang Son urgently builds 7 multi-level boarding schools in border commune

Khánh Linh |

Lang Son - 7 boarding schools in border communes are being urgently deployed.

Overview of 11 boarding school projects in Cao Bang ahead of schedule

Long An |

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.

Lao Cai announces enrollment plan for 4 boarding schools in border areas

Đinh Đại |

Lao Cai - The province has just approved the enrollment plan for boarding primary and secondary schools in 4 border communes.