Overview of 11 boarding school projects in Cao Bang ahead of schedule

Long An |

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.

Many projects are behind schedule

Cao Bang is focusing efforts to accelerate the construction progress of 11 inter-level boarding schools in border communes to ensure their commissioning before the 2026-2027 school year.

However, reality shows that most projects are still behind schedule compared to the set plan.

According to the Investment and Construction Project Management Board of Cao Bang province, phase 1 deploys the construction of 11 primary and secondary boarding schools in border communes.

By May 24, all 11 projects had completed the design dossiers for ground leveling, foundation and body of the project.

Dự án xây dựng trường nội trú liên cấp Trà Lĩnh đang là dự án đạt tiến độ tốt nhất 55%. Ảnh: Trọng Lộc
The Tra Linh inter-level boarding school construction project is currently the project with the best progress of 55%. Photo: Trong Loc

Among these, only 2 projects in Tra Linh and Ha Lang communes basically meet the schedule according to the plan. Many items have been constructed to the stage of completing the 2nd and 3rd floors, roofing the attic or installing formwork beams for the 4th floor.

Four projects in Dam Thuy, Quang Trung, Quang Han and Tong Cot communes have only partially met the progress, while the remaining 5 projects in Duc Long, Lung Nam, Truong Ha, Phuc Hoa and Dinh Phong are still behind schedule.

The total capital allocated for projects in 2026 is more than VND 1,737 billion. By the end of May 2026, the disbursed value reached more than VND 163.7 billion, equivalent to 9.42% of the assigned capital plan.

Trường nội trú liên cấp Phục Hòa được xây dựng bằng nguồn kinh phí hỗ trợ từ TP Hà Nội hiện có tiến độ thi công chậm nhất, đến tháng 6.2026 dự án đạt 17%. Ảnh: Trọng Lộc
Phuc Hoa Inter-level Boarding School, built with funding support from Hanoi City, currently has the slowest construction progress, reaching 17% by June 2026. Photo: Trong Loc

Records of Lao Dong Newspaper reporters on the 10th and 12th of June at 11 construction sites show that, in addition to the Tra Linh project reaching about 55% of the volume and Ha Lang reaching 38%, the remaining projects are facing difficulties in progress.

At the Quang Han inter-level boarding school project, with a total investment of 190 billion VND, the construction progress as of June 9 has only reached about 18%. The project is currently basically completing the foundation and is deploying the construction of the 1st floor.

Representatives of the contractor consortium including Dong Duong Co., Ltd. and Quang Hung Co., Ltd. said that the construction process encountered difficulties due to unfavorable geological conditions.

Manpower shortage

During the actual implementation process, the construction unit discovered mud pocket terrain. This type of terrain was not identified during geological survey drilling, forcing additional foundation treatment and excavation of weak waste soil affecting project progress.

Dự án xây dựng trường nội trú Đình Phong đạt tiến độ thi công 18%. Ảnh: Trọng Lộc
The construction project of Dinh Phong boarding school reached a construction progress of 18%. Photo: Trong Loc

However, the contractors affirmed that they will focus resources and strive to complete the basic items before August 30 to serve the new school year.

According to Mr. Do Kien Cuong - Head of Project Management Department 2, Investment and Construction Project Management Board of Cao Bang province, the biggest difficulty currently is the shortage of skilled labor.

There are projects where contractors have to pay more than 1 million VND per working day to retain human resources, but it is still very difficult to recruit," Mr. Cuong said.

Faced with the risk of many projects being behind schedule, Chairman of Cao Bang Provincial People's Committee Le Hai Hoa has just sent a letter of encouragement and called on contractors to accelerate the construction of 11 inter-level boarding schools in the area.

Theo đại diện chủ đầu tư, yếu tố thời tiết, nguồn nước cũng là một nguyên nhân làm chậm bước chân của các nhà thầu thi công. Ảnh: Trọng Lộc
According to the representative of the investor, weather and water sources are also a reason for slowing down the steps of construction contractors. Photo: Trong Loc

According to the Chairman of Cao Bang Provincial People's Committee, the border school construction campaign has entered the final sprint phase, but many projects have not yet reached the committed progress.

He requested contractors, design consulting units and supervision consultants to review all resources, mobilize the best cadres, engineers and construction teams for the projects.

Not waiting. Not holding back. Not doing it in the style of keeping the normal pace," the Chairman of the Provincial People's Committee emphasized in a letter to construction units.

Previously, in May 2026, Cao Bang Provincial People's Committee issued two consecutive telegrams requesting the entire project to switch to an emergency construction status during the rainy season.

The province established the Campaign Command in the Provincial Investment and Construction Project Management Board, assigning Vice Chairman of the Provincial People's Committee Vu Dinh Quang to directly direct, coordinate and handle arising difficulties.

Vào ngày 2.6 vừa qua, Quân khu 1 đã bàn giao 440 cán bộ, chiến sĩ trực tiếp đến các dự án tham gia hỗ trợ xây dựng. Ảnh: Trọng Lộc
On June 2nd, Military Region 1 handed over 440 officers and soldiers directly to projects participating in construction support. Photo: Trong Loc

Contractors are required to organize construction according to the "3 shifts, 4 teams" plan, mobilize maximum manpower and equipment, and at the same time develop weather response scenarios to ensure the goal of completing 11 schools before August 30, 2026.

In parallel with accelerating the construction progress, Cao Bang province also directed the preparation of a team of teachers, facilities and teaching equipment so that schools can go into operation immediately after completion, avoiding the situation where the project is completed but cannot be operated.

Long An
RELATED NEWS

Cao Bang prepares natural disaster response plan early

|

Cao Bang is developing scenarios and plans to respond to natural disasters early.

Cao Bang Chairman sends letter hoping contractors will accelerate 11 border boarding schools

|

Chairman of Cao Bang Provincial People's Committee Le Hai Hoa has just sent a letter to construction contractors at the construction site of the inter-level boarding school.

Deputy Prime Minister Le Tien Chau inspects progress of 3 boarding schools in Cao Bang border area

|

Cao Bang - Deputy Prime Minister requests localities to accelerate the construction progress of 3 boarding general schools in border areas.

The numbers show that Elon Musk is incredibly rich

|

Elon Musk became the first person in the world to own more than 1,000 billion USD, with asset scale far exceeding what most people can imagine.

Pretty girl" Ngo Lan Huong: I studied at Foreign Trade University and once thought I would work in import and export

|

Em xinh say hi Ngo Lan Huong shared about her professional views and the past of almost not pursuing art.

Gold prices rise sharply, stores are bustling with traders trading on the weekend

|

Gold prices increased sharply again at the end of the week, causing many people in Hanoi to go to gold stores to buy, accepting to queue to wait for transactions.

Ukraine lost more than 1,460 soldiers last week

|

The Russian Ministry of Defense said on June 12 that Ukrainian forces lost more than 1,460 soldiers in the operating area of the Western Combat Group in the past week.

Cao Bang prepares natural disaster response plan early

Tân Văn |

Cao Bang is developing scenarios and plans to respond to natural disasters early.

Cao Bang Chairman sends letter hoping contractors will accelerate 11 border boarding schools

Tân Văn |

Chairman of Cao Bang Provincial People's Committee Le Hai Hoa has just sent a letter to construction contractors at the construction site of the inter-level boarding school.

Deputy Prime Minister Le Tien Chau inspects progress of 3 boarding schools in Cao Bang border area

Tân Văn |

Cao Bang - Deputy Prime Minister requests localities to accelerate the construction progress of 3 boarding general schools in border areas.