In the early days of July, in many highland communes of Tuyen Quang province, machinery and workers are operating bustlingly at the construction site of boarding school projects.
6 inter-level boarding primary and secondary school (TH&THCS) projects in this locality are being implemented in Minh Tan, Thanh Thuy, Pho Bang, Son Vi, Xin Man, Pa Vay Su border communes.
PV recorded at the construction site of Minh Tan Inter-level Boarding School for Primary and Secondary School, nearly 500 officials and workers are working continuously according to the 3-shift, 4-shift motto.


After a long period of construction, to date, all 12 newly built building blocks and 3 renovated building blocks have completed the rough construction. Construction units are implementing items such as plastering walls, tiling, and auxiliary infrastructure.
Mr. Nguyen Trung Kien - Project Commander (Tu Lap Construction Co., Ltd.) said: "Up to now, the progress has reached more than 60% of the plan. The unit always mobilizes from 400 to 600 officials and workers at the construction site, working continuously, divided into many shifts, many construction teams including holidays.
As for the Thanh Thuy Inter-level Boarding School project, all 10/10 building blocks have been deployed simultaneously, reaching more than 70% of the volume. More than 400 workers are always on duty at the project site.
Similarly, the project progress in Pho Bang, Son Vi, Xin Man and Pa Vay Su communes also reached from 40% to 70% of the workload.
With the goal of completion before August 2026, all projects are forced to accelerate progress to be handed over in time.
According to contractors, the implementation of projects faces some difficulties when time is rushed, labor resources are scarce, and the terrain of the highlands is dangerous. The construction process also generates unexpected geological factors.
According to Mr. Luong Van Doan - Director of the Project Management Board for Construction Investment of Tuyen Quang province, the investor always proactively removes arising problems at the site, regularly checks the contractor's capacity and organizes construction supervision.
In particular, contractors are required to carry out construction in accordance with design and technical standards. The quality of materials and equipment put into the project must be ensured. Acceptance, payment, and management of contracts must be ensured according to regulations.
Contractors increase large-capacity machinery, supplement manpower for items with large volumes. Construction progress is built in detail weekly, item by item. At the same time, organize overtime, increase construction teams to compensate for volume and shorten implementation time.
In addition to the above 6 projects, Tuyen Quang is also carrying out investment procedures for 11 inter-level boarding schools, phase 2 in the communes: Ban May, Thang Tin, Lao Chai, Tung Vai, Nghia Thuan, Can Ty, Bach Dich, Thang Mo, Sa Phin, Lung Cu and Dong Van.
Currently, 10/11 projects have submitted feasibility study reports for appraisal, of which the Dong Van School project has been approved by the People's Committee of Tuyen Quang province.