Progress of 30 key projects and works in Hai Phong City

Hoàng Khôi |

Hai Phong - Hai Phong City People's Committee has just announced the implementation situation of 30 key projects and works in the area as of the end of the second quarter of 2026.

According to Resolution No. 74/NQ-HDND dated December 8, 2025 of the City People's Council on the city's socio-economic development plan for 2026, the list of key projects for 2026 includes 31 projects. In Document No. 553/BQL-PTDA dated April 24, 2026, the Project Management Board for Investment in Construction of Transport Works proposed to remove 1 project from the List of key projects, which is the Project to invest in building the western intersection of the city and Vo Nguyen Avenue extended adjacent to Gia Binh airport. Reason: According to the direction of the City People's Committee in Document No. 133/VP-TB dated April 7, 2026, the Project Management Board is studying the Ring Road I in the West Hai Phong area according to the plan to reduce and divert traffic, organize, and ensure traffic safety for National Highway 5. Therefore, the study of building the western intersection of the city will be implemented after agreeing on the plan to build Ring Road I. At the same time, this is a project passing through 2 localities, it is necessary to carry out procedures to report to

Among the 30 key projects, the city has inaugurated the project to invest in the construction, repair, and embellishment of the Ben K15 relic complex, Do Son ward (inaugurated on the occasion of the 71st anniversary of Hai Phong Liberation). In addition, 2 projects are expected to exceed the Q2 target; 18/30 projects are expected to complete the Q2 target. 8/30 projects are expected not to complete the Q2 target, striving to complete the 2026 target. Among the 30 projects, one project has not determined its progress, which is the project to invest in the construction of a domestic solid waste treatment plant using waste burning technology for electricity generation in Dinh Vu, Hai An. The reason is that the city is waiting for opinions on the feasibility of the project from functional agencies.

Regarding the settlement and handling of backlog projects, according to Plan No. 51/KH-UBND, the city has 151 projects and works that need to be focused on removing and resolving. Up to now, 38/151 projects have been completed removing difficulties and obstacles (including: 28 projects under the authority of the City People's Committee; 10 projects under the authority of the Commune-level People's Committee); plans have been developed to solve difficulties and obstacles for 103/151 projects (including: 66 projects under the authority of the City People's Committee; 37 projects under the authority of the Commune-level People's Committee). The remaining 10 projects have identified plans and proposed to seek opinions on handling plans.

At the regular meeting in June 2026, Chairman of Hai Phong City People's Committee Do Thanh Trung requested localities to focus on accelerating the disbursement of public investment capital; removing bottlenecks in construction price index, site clearance, resettlement, and project adjustment.

The Chairman of the City People's Committee requested to review all outstanding projects, social housing projects, centralized waste treatment areas, real estate facilities and projects facing difficulties to focus on thoroughly handling them, creating new resources for growth.

Hoàng Khôi
RELATED NEWS

A series of Ca Mau wind power projects face difficulties

|

Ca Mau is planned for 48 wind power projects with more than 3,000 MW, but many projects are still behind schedule, not fully exploiting their potential due to obstacles in mechanisms, transmission infrastructure and investor capacity.

Hai Phong recovers hundreds of public houses and land facilities used for wrong purposes

|

Hai Phong - Hai Phong Housing Management and Trading Co., Ltd. manages 273 land and house locations that are public assets not used for residential purposes.

Proactively dismantling violating works on agricultural land in Hai Phong

|

Hai Phong - 2 households in village 1 Viet Hai, Cat Hai special zone have voluntarily dismantled violating works on agricultural land.

Awakening the tourism potential of the Hoa Binh lake area needs more "push"

|

The tourism potential of the Hoa Binh lake area is very large, but there is still a lack of infrastructure, planning and appropriate mechanisms to attract investment and sustainable development.

Avoiding functional forces, personal data traders transfer to online markets

|

Without direct transactions, without meeting customers, but just spending money, personal data can be easily bought and sold at unbelievably cheap prices.

10th grade benchmark score in Ho Chi Minh City, the highest school takes 24.75 points

|

On June 30, the Ho Chi Minh City Department of Education and Training (GDĐT) announced the benchmark scores for 10th grade enrollment into public high schools for the 2026-2027 school year.

A series of Ca Mau wind power projects face difficulties

Nhật Hồ |

Ca Mau is planned for 48 wind power projects with more than 3,000 MW, but many projects are still behind schedule, not fully exploiting their potential due to obstacles in mechanisms, transmission infrastructure and investor capacity.

Hai Phong recovers hundreds of public houses and land facilities used for wrong purposes

Hoàng Khôi |

Hai Phong - Hai Phong Housing Management and Trading Co., Ltd. manages 273 land and house locations that are public assets not used for residential purposes.

Proactively dismantling violating works on agricultural land in Hai Phong

Hoàng Khôi |

Hai Phong - 2 households in village 1 Viet Hai, Cat Hai special zone have voluntarily dismantled violating works on agricultural land.