30 months of construction of highway through 3 northern provinces

HỮU CHÁNH |

If an investor is found in the first quarter, the 113km Ring Road 4 expressway will start construction in the second quarter of 2025 and be completed after 30 months of construction.

Beltway 4 of the Capital region is implemented according to 7 component projects, of which component project 3 is the "backbone" including a 113km long expressway.

The project has a total investment of nearly 56,300 billion VND, of which the sub-project uses state capital to support the project of about 26,700 billion VND, and the project part uses capital from BOT investors of about 29,500 billion VND.

Hanoi has separated projects using state budget capital including the construction of Hong Ha bridge, the section of Ring Road 3 from before the National Highway 6 intersection to the end of the Hanoi - Hai Phong expressway intersection (including Me So bridge); Hoai Thuong bridge; the 9.7km connecting section with Noi Bai - Ha Long expressway.

The remaining items will be implemented by investors using their own capital and credit capital in the form of public-private partnership (PPP).

Phan dat o giua duong song hanh Vanh dai 4 duoc chua de xay dung du an thanh phan 3. Anh: Huu Chanh
The land in the middle of the parallel road of Ring Road 4 is left to build component project 3. Photo: Huu Chanh

At component project 3 on investment in building the expressway system under the public-private partnership (PPP) method, the leader of the Hanoi People's Committee said that project implementation is still very difficult.

The city has surveyed the level of interest of investors, however, not many investors have participated because businesses must meet the minimum criteria for a large, complex transportation project.

Accordingly, investors must have equity capital of at least 15% of the total project investment of more than VND 4,400 billion; must have completed a project with a total investment of at least 50% of the total investment of the Ring Road 4 project (about VND 28,100 billion).

Investors must mobilize about 29,525 billion VND of capital, of which loans from credit institutions account for about 85%, with a long payback period.

The leaders of the Hanoi People's Committee assessed that large capital sources could cause difficulties for credit institutions and banks, affecting investors' ability to mobilize capital.

For the above reasons, not many domestic investors participate in forming consortiums that meet the requirements.

According to the plan, component project 3 needs about 30 months of construction; while if favorable conditions are met in the first quarter of 2025 when an investor is selected, construction can begin in the second quarter of 2025.

Ring Road 4 passes through Hanoi 57km, Hung Yen 19km, Bac Ninh 27km and the connecting route towards Noi Bai - Ha Long highway is about 9.7km.

Of which, the low-lying section is about 32km long, the elevated section is more than 80km long. The road has 6 lanes, a parallel road system on both sides, a green corridor, technical infrastructure works and land reserved for the belt railway. The design speed of the route is 100km/h.

Nut giao cao toc Vanh dai 4 voi Quoc lo 6 (Ha Dong, Ha Noi). Anh: UBND TP Ha Noi
Intersection of Ring Road 4 with National Highway 6 (Ha Dong, Hanoi). Photo: Hanoi People's Committee

The project will invest in building 8 complete interchanges. Of which 5 are in Hanoi; 2 are in Hung Yen province; 1 is in Bac Ninh province. At the same time, the project will invest in building 7 branches connecting to the parallel roads on both sides.

According to the plan, Ring Road 4 will be completed and put into operation in 2027. Together with the parallel road system, when completed, Ring Road 4 will contribute to relieving traffic congestion, connecting provinces and creating new development space for the entire capital region, including Hanoi, Hung Yen and Bac Ninh.

HỮU CHÁNH
TIN LIÊN QUAN

Accelerating the progress of the 57km road through Hanoi, to be completed by the end of 2025

|

Hanoi - Many engineers and workers took a break for the New Year holiday to stay at the construction site, striving to complete the Ring Road 4 project in the capital region by the end of 2025.

Putting aside Tet holiday to focus on construction of Ring Road 4 in the Capital region

|

On the first day of 2025, workers at the construction site of Ring Road 4 were still busy working to meet the schedule of completing the parallel road this year.

Construction of a 112km-long expressway with a capital of nearly VND56,300 billion will begin in 2025

|

The Ring Road 4 Expressway is over 112km long, with a total investment of nearly VND56,300 billion through Hanoi, Hung Yen and Bac Ninh, and is expected to start construction in the second quarter of 2025.

Vietnam team needs to prepare a second option besides Xuan Son

|

Sports Perspective No. 196 and former player Nguyen Manh Dung discussed the journey of the Vietnam National Team at the ASEAN Cup 2024.

Experts make surprising predictions about gold prices in 2025

|

In 2025, many experts predict that gold prices will continue to increase amid many supportive factors.

One side rakes in the money, the other suffers when Ukraine shuts off Russian gas valve

|

Russia points out the beneficiaries and the worst affected when Ukraine stops the transit of Russian gas.

Xuan Son responds to the actions of the Thai national team's central defender

|

Thailand's defense struggled for more than 90 minutes against Nguyen Xuan Son's impressive performance.

Decoding the appeal of the million-view video of "Mother's Cuisine"

|

In today's Podcast, you will listen to the 5-year journey of building and developing the million-view Youtube channel "Mother's Cuisine".

Accelerating the progress of the 57km road through Hanoi, to be completed by the end of 2025

HỮU CHÁNH - KHÁNH AN |

Hanoi - Many engineers and workers took a break for the New Year holiday to stay at the construction site, striving to complete the Ring Road 4 project in the capital region by the end of 2025.

Putting aside Tet holiday to focus on construction of Ring Road 4 in the Capital region

KHÁNH AN - HỮU CHÁNH |

On the first day of 2025, workers at the construction site of Ring Road 4 were still busy working to meet the schedule of completing the parallel road this year.

Construction of a 112km-long expressway with a capital of nearly VND56,300 billion will begin in 2025

HỮU CHÁNH |

The Ring Road 4 Expressway is over 112km long, with a total investment of nearly VND56,300 billion through Hanoi, Hung Yen and Bac Ninh, and is expected to start construction in the second quarter of 2025.