The first locality to hand over full land for Hanoi Ring Road 4 project

HỮU CHÁNH |

Of the 7 districts in Hanoi that Ring Road 4 passes through, only one locality has handed over enough land for the project.

Component project 2.1 - construction of parallel road (urban road) of Ring Road 4, the section through Hanoi is about 58km long, passing through Soc Son, Me Linh, Dan Phuong, Hoai Duc districts, Ha Dong district, Thanh Oai and Thuong Tin districts.

The project is divided into 4 packages including package 8 through Soc Son and Me Linh districts (13km), package 9 through Dan Phuong and Hoai Duc (23km), package 10 through Ha Dong district and Thanh Oai district (12km) and package 11 through Thuong Tin district (10km).

Up to now, the Hanoi Traffic Construction Project Management Board (Project Management Board) has received 776.82/786.2 hectares of land, equivalent to 48.35km/52.73km, reaching 91.7%.

Currently, the project still has 8.3% of the land area, equivalent to more than 4.4km in length, that has not been cleared. There are still many interruptions and delays along the entire construction route.

a
The high-voltage power line infrastructure at the construction site of the North-South railway overpass through Me Linh district has not yet been relocated. Photo: Huu Chanh

According to the Project Management Board, this 4.4km is not located in one locality or one section of the route but is scattered across 6/7 districts including Me Linh, Dan Phuong, Hoai Duc, Thanh Oai, Thuong Tin and Ha Dong district.

Up to now, only Soc Son district has handed over enough land for the Hanoi Ring Road 4 project.

Representatives of some districts and counties that Ring Road 4 runs through said that most of the agricultural land has been cleared. The project sites that have not been cleared yet are related to residential land, old graves and the relocation of high-voltage power line infrastructure.

Regarding site clearance work in the Hanoi section, the Project Management Board said that priority should be given to handing over items critical to the project's progress such as high-voltage pole foundations and weak soil treatment.

Regarding land clearance for residential land, currently the remaining land volume is mainly residential land in 5 districts: Ha Dong, Me Linh, Dan Phuong, Hoai Duc, Thanh Oai facing difficulties due to problems in applying the 2024 Land Law and current regulations.

Along with that are difficulties related to determining the origin of the land, and the large difference between the starting and ending prices.

Mot khu dan cu o xa Chu Phan (huyen Me Linh) chua duoc giai phong mat bang. Anh: Huu Chanh
A residential area in Chu Phan commune (Me Linh district) has not yet been cleared. Photo: Huu Chanh

The Project Management Board requests the Department of Natural Resources and Environment to continue to preside over and research compensation, support and resettlement policies to comply with regulations, ensuring consistency throughout the project.

At the meeting to review the progress of the Ring Road 4 project on December 12, Hanoi Party Secretary Bui Thi Minh Hoai requested agencies, units, departments and districts to focus their efforts, and coordinate with relevant ministries and branches to consult on mechanisms and policies, striving to complete the project's site clearance before the Lunar New Year 2025.

After about 17 months since the commencement of the Ring Road 4 project, 4 construction packages in Hanoi have been simultaneously deployed on a route length of 48.35km with 32 construction points (23 road points, 9 bridge points).

The output to date is about 1,810/4,205 billion VND (reaching 43.04% of the contract value and 100% of the 2024 plan). Hanoi strives to complete the parallel road project in the fourth quarter of 2025.

HỮU CHÁNH
TIN LIÊN QUAN

27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

|

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.

Total construction force, completion of parallel road of Ring Road 4 by 2025

|

According to plan, the parallel road of Ring Road 4 through Hanoi, Hung Yen and Bac Ninh will be completed in 2025. Contractors are focusing on construction, closely following the schedule.

Trump asks US Supreme Court to delay TikTok ban

|

President-elect Donald Trump has moved to delay the ban on TikTok in the US.

Rocks and soil on An Khe Pass continue to slide down National Highway 19

|

Binh Dinh - After the flooding and landslide incident half a month ago, National Highway 19, the section through An Khe Pass, continued to collapse, affecting traffic on the route.

Singapore team confident of comeback against Vietnam team

|

Singapore players believe they will create a miracle against Vietnam in the second leg of the ASEAN Cup 2024 semi-finals, despite losing 0-2 in the first leg.

Career as Vice Principal of University of Theatre and Cinema before acting in Tao Quan

|

Meritorious Artist Bui Nhu Lai had taken on many roles before participating in Tao Quan 2025.

"Sister Who Makes Wave is not pink, the training schedule is very harsh"

|

In this week's "Saturday Afternoon Cafe", former Wushu athlete Thuy Hien shared interesting behind-the-scenes stories in "Sister Who Makes Wave 2024".

Deputy Director of Economic Security Department becomes Director of Lang Son Police

|

Lang Son - Colonel Nguyen Tien Trung, Deputy Director of the Department of Economic Security, Ministry of Public Security, was transferred and appointed to the position of Director of the Provincial Police Department.

27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

NHÓM PV |

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.

Hiện trạng nơi xây cầu vượt sông Hồng, sông Đuống trên Vành đai 4

NHÓM PV |

Có 3 cây cầu lớn trên Vành đai 4 sẽ được đầu tư xây dựng gồm Hồng Hà và Mễ Sở qua sông Hồng, cầu Hoài Thượng qua sông Đuống.

Total construction force, completion of parallel road of Ring Road 4 by 2025

NHÓM PV |

According to plan, the parallel road of Ring Road 4 through Hanoi, Hung Yen and Bac Ninh will be completed in 2025. Contractors are focusing on construction, closely following the schedule.