Bao Loc - Lien Khuong expressway is slow to construct due to incomplete design documents

Phúc Khánh |

Lam Dong - Although more than 67% of the site has been handed over, the Bao Loc - Lien Khuong expressway project cannot be implemented due to incomplete technical design documents.

On June 23, at a working session on the progress of disbursement of public investment capital for the two Tan Phu - Bao Loc and Bao Loc - Lien Khuong expressway projects, Chairman of Lam Dong Provincial People's Committee Ho Van Muoi requested localities and investors to focus on ensuring responsibility and commitment to progress.

Tỉnh Lâm Đồng tổ chức buổi làm việc đánh giá tiến độ thi công 2 dự án cao tốc trọng điểm trên địa bàn. Ảnh: Hoài Thanh
Lam Dong province organizes a working session to assess the progress of construction of 2 key expressway projects in the area. Photo: Hoai Thanh

Provincial leaders criticized the investor of the Bao Loc - Lien Khuong expressway project for delays in completing legal procedures, technical design documents and credit contracts.

The province requests that the relevant contents must be completed by July 15 at the latest to be eligible for construction deployment.

The Chairman of the Provincial People's Committee emphasized the requirement for investors to mobilize sufficient resources, take advantage of existing land, and organize construction according to the motto "where there is land, construction is carried out there".

The Bao Loc - Lien Khuong expressway project is more than 73km long, with a total investment of nearly 18,000 billion VND, passing through 10 communes and wards with 2,464 affected households, and a recovered area of more than 681ha.

In 2026, the project was allocated nearly 2,940 billion VND of public investment capital, and more than 331 billion VND has been disbursed for compensation and support.

Chủ tịch UBND tỉnh Lâm Đồng Hồ Văn Mười yêu cầu chủ đầu tư, các sơ, ngành, địa phương tập trung tháo gỡ khó khăn, vướng mắc để 2 dự án cao tốc
Chairman of Lam Dong Provincial People's Committee Ho Van Muoi requested investors, departments, branches, and localities to focus on removing difficulties and obstacles so that the 2 expressway projects can be implemented on schedule. Photo: Hoai Thanh

According to the Construction Investment Project Management Board No. 1 of Lam Dong province, so far localities have handed over about 421ha of land, reaching more than 67%.

However, the contractor has only leveled and cleared the ground, and has not started construction because the technical design documents and estimates of the route sections have not been approved.

Director of Lam Dong Department of Construction Le Ngoc Tien said that the responsibility for the slow progress belongs to the investor when the dossier was not completed as committed, although he promised to complete the design drawings on May 30, but has not implemented it, expected to be completed in July.

Cao tốc Bảo Lộc - Liên Khương chậm thi công do chưa hoàn thiện hồ sơ thiết kế. Ảnh: Phúc Khánh
Bao Loc - Lien Khuong expressway is slow to construct due to incomplete design documents. Photo: Phuc Khanh

For the Tan Phu - Bao Loc expressway project, 66km long, with a total investment of more than 18,000 billion VND, more than 76ha of land has been handed over.

In 2026, the project was allocated nearly 1,750 billion VND, and about 204 billion VND has been disbursed. However, some items have not yet completed technical design approval and credit contract signing, affecting the overall progress.

Provincial leaders requested departments, branches, localities and investors to closely coordinate and remove obstacles to accelerate the progress of the two key expressway projects.

Phúc Khánh
RELATED NEWS

Two key expressways in Lam Dong accelerate day by day, hour by hour

|

Lam Dong - Two key expressway projects are being accelerated in construction progress, and the shape of the roads is gradually being revealed.

Bao Loc - Lien Khuong expressway is behind schedule

|

Lam Dong - Leaders of Lam Dong Provincial People's Committee criticized the investor of the Bao Loc - Lien Khuong Expressway Project for delays in project preparation and implementation.

Lam Dong removes land bottlenecks on Bao Loc - Lien Khuong expressway

|

Lam Dong - After more than 5 months of construction, the Bao Loc - Lien Khuong expressway is facing site clearance problems, it is necessary to focus on removing them to ensure progress.

Decisively complete the flood control project in Ho Chi Minh City area in 2026

|

The Standing Deputy Prime Minister requested that the tidal flood control project in Ho Chi Minh City phase 1 must be definitively completed in 2026.

Temporarily banning and restricting vehicles on many roads in Hanoi from June 24-25

|

Hanoi - The temporary ban and restriction of vehicles on many roads on June 24 and 25 to serve the 13th National Youth Union Congress.

Tricks to make fake license plates, avoiding traffic tickets

|

In the center of Hanoi, many establishments still publicly accept to make fake license plates, advertising to help customers avoid the remote fine system.

Strong El Nino is about to appear, early warning of extreme natural disasters

|

Forecasting and early warning is the key to proactively preventing and minimizing damage caused by El Nino in 2026.

Two key expressways in Lam Dong accelerate day by day, hour by hour

Phúc Khánh |

Lam Dong - Two key expressway projects are being accelerated in construction progress, and the shape of the roads is gradually being revealed.

Bao Loc - Lien Khuong expressway is behind schedule

Phúc Khánh |

Lam Dong - Leaders of Lam Dong Provincial People's Committee criticized the investor of the Bao Loc - Lien Khuong Expressway Project for delays in project preparation and implementation.

Lam Dong removes land bottlenecks on Bao Loc - Lien Khuong expressway

Phúc Khánh |

Lam Dong - After more than 5 months of construction, the Bao Loc - Lien Khuong expressway is facing site clearance problems, it is necessary to focus on removing them to ensure progress.