Lam Dong removes land bottlenecks on Bao Loc - Lien Khuong expressway

Phúc Khánh |

Lam Dong - After more than 5 months of construction, the Bao Loc - Lien Khuong expressway is facing site clearance problems, it is necessary to focus on removing them to ensure progress.

Key highway

Bao Loc - Lien Khuong expressway is more than 73km long, with a total investment of about 18,000 billion VND.

The project is expected to shorten travel time from Ho Chi Minh City to Da Lat to about 3 hours when completed in 2027.

Hinh anh mo phong cao toc Bao Loc - Lien Khuong. Anh: Nha dau tu cung cap
Simulated image of Bao Loc - Lien Khuong expressway. Photo: Investor provided

The project is invested in the public-private partnership (PPP) method, invested by the T&T Group - Phuong Trang - Phuong Thanh joint venture, with an expected construction time of about 30 months.

The expressway not only removes traffic bottlenecks at Bao Loc Pass but also creates motivation for socio-economic development in the region, forming a satellite urban chain along the Dong Nai - Bao Loc - Duc Trong axis.

Cao toc Bao Loc - Lien Khuong, doan di qua dia phan Phuong 1 Bao Loc. Anh: Phuc Khanh
Bao Loc - Lien Khuong expressway, section passing through Ward 1, Bao Loc. Photo: Phuc Khanh

However, up to this point, the actual construction progress has not met the requirements due to problems in site clearance.

Along with that, Lam Dong province is urgently reviewing construction material mines, increasing supply capacity to meet construction needs in the coming time.

Faced with this situation, Lam Dong Provincial People's Committee has directed departments, branches, and localities to focus on removing difficulties and accelerating the project progress.

Cong tac do dem phuc vu giai phong mat bang duoc xem la khau then chot cua Du an. Anh: Phuc Khanh
The measurement work to serve site clearance is considered a key stage of the Project. Photo: Phuc Khanh

More than 5 months after the commencement date (June 29, 2025), the Bao Loc - Lien Khuong expressway is entering a key stage, focusing on handling site clearance problems and completing legal procedures related to forest land.

According to Bao Loc - Lien Khuong Expressway Joint Stock Company, the project enterprise has basically completed the organizational structure and mobilized enough personnel.

Owner's equity has been fully contributed; loan applications are being appraised to proceed with signing credit contracts with banks, with a total estimated value of about 8,000 billion VND.

Focus on removing bottlenecks

An important legal milestone has just been completed when the project enterprise fully paid the cost of reforestation.

Tinh Lam Dong trien khai chi tra boi thuong cho cac ho dan co dat thu hoi thuc hien Du an cao toc. Anh: Phuc Khanh
Lam Dong province deploys compensation payments to households whose land is recovered to implement the expressway project. Photo: Phuc Khanh

Currently, functional agencies of Lam Dong province are implementing procedures to change the purpose of forest use according to regulations.

At a recent working session, Mr. Nguyen Hong Hai - Vice Chairman of Lam Dong Provincial People's Committee requested the investor to review the entire work, concretize the recommendations so that the government can promptly remove obstacles.

In January 2026, investors must consolidate the apparatus and open representative offices in localities where the road passes through to strengthen coordination.

Cong tac chi tra boi thuong duoc trien khai khan truong de Du an dam bao tien do. Anh: Phuc Khanh
Compensation payment work is being urgently deployed to ensure project progress. Photo: Phuc Khanh

Regarding site clearance, the Provincial People's Committee assigned the Provincial Land Fund Development Center to focus on deploying at key locations.

The project needs to recover more than 582ha of land, affecting over 2,450 households - which is identified as a key stage determining progress.

Provincial leaders requested that when the site is handed over, the contractor must immediately mobilize manpower and machinery to construct, avoiding waiting.

In terms of technology, the consulting unit has completed about 90% of the survey volume and 60% of the technical design; out of 19 bidding packages of the project, 7 bidding packages are prioritized for early implementation.

According to the plan, in the first quarter of 2026, the project enterprise will complete appraisal, sign credit contracts and select construction contractors.

From March to June 2026, the project will deploy detailed surveys, approve construction drawing designs and large-scale construction.

On January 13, more than 300 households in Hiep Thanh commune (Lam Dong) came to Agribank Duc Trong Branch to receive compensation money for the project.

From January 13 to 15, the Provincial Land Fund Development Center coordinated with the bank to pay compensation money to 274 eligible cases - this is the first locality to implement the project's payment.

Phúc Khánh
RELATED NEWS

Lam Dong starts paying compensation for Bao Loc - Lien Khuong expressway

|

Lam Dong - The locality is implementing the payment of compensation and site clearance for households whose land has been recovered to implement the Bao Loc - Lien Khuong expressway.

Lam Dong speeds up the completion of the Bao Loc - Lien Khuong expressway site clearance

|

Lam Dong - Localities have basically completed the work of building land prices, ensuring the progress of site clearance for the Bao Loc - Lien Khuong Expressway Project.

Officially build Bao Loc - Lien Khuong Expressway, open an inter-regional economic development axis

|

The Bao Loc - Lien Khuong Expressway project has officially started construction, creating a strategic connection, expanding the space for inter-regional economic development for the region.

Former South Korean President Yoon Suk Yeol faces death penalty

|

On January 13, prosecutors proposed the death penalty for former South Korean President Yoon Suk Yeol.

Inside the 100-year-old memorial house under relocation as Ring Road 2.5

|

Hanoi - The revolutionary memorial house of Mr. Ta Dinh Tan in Cau Giay ward is under site clearance and relocation according to the Ring Road 2.5 project plan.

Russia mobilizes forces to attack in retaliation against Ukraine overnight

|

Russia launched a large-scale attack overnight in response to Ukrainian attacks on civilian facilities on Russian territory.

Many officials of Soc Son commune were named because hundreds of land dossiers were overdue

|

Hanoi - The inspection team determined the responsibility of many officials of Soc Son commune for delays and sluggishness in resolving dossiers, affecting people's rights.

Hanoi opens roads worth more than 1,300 billion VND in January 2026

|

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is expected to be completed and technically opened to traffic in January 2026.

Lam Dong starts paying compensation for Bao Loc - Lien Khuong expressway

Phúc Khánh |

Lam Dong - The locality is implementing the payment of compensation and site clearance for households whose land has been recovered to implement the Bao Loc - Lien Khuong expressway.

Lam Dong speeds up the completion of the Bao Loc - Lien Khuong expressway site clearance

Phúc Khánh |

Lam Dong - Localities have basically completed the work of building land prices, ensuring the progress of site clearance for the Bao Loc - Lien Khuong Expressway Project.

Officially build Bao Loc - Lien Khuong Expressway, open an inter-regional economic development axis

Hà Vy |

The Bao Loc - Lien Khuong Expressway project has officially started construction, creating a strategic connection, expanding the space for inter-regional economic development for the region.