Two key expressways in Lam Dong accelerate day by day, hour by hour

Phúc Khánh |

Lam Dong - Two key expressway projects are being accelerated in construction progress, and the shape of the roads is gradually being revealed.

Accelerate simultaneous construction

The two expressways Tan Phu - Bao Loc and Bao Loc - Lien Khuong have a total length of nearly 140km, with a total investment of more than 36,000 billion VND.

This is a strategic traffic axis connecting the Central Highlands with the southern key economic region.

Hình hài hai tuyến cao tốc Tân Phú - Bảo Lộc và Bảo Lộc - Liên Khương đang dần hình thành. Ảnh: Phúc Khánh
The shape of the two Tan Phu - Bao Loc and Bao Loc - Lien Khuong expressways is gradually taking shape. Photo: Phuc Khanh

The expressway not only opens up new development space for Lam Dong but is also expected to promote regional linkages, develop logistics, tourism and attract investment.

After a period of completing procedures and removing difficulties, at the end of April 2026, 14 construction teams simultaneously launched operations, and the shape of the key expressway is gradually taking shape.

Hiện tại, 14 mũi đã đồng loạt thi công, đẩy nhanh tiến độ dự án cao tốc trọng điểm, chiến lược của tỉnh Lâm Đồng. Ảnh: Phúc Khánh
Currently, 14 fronts have simultaneously constructed, accelerating the progress of the strategic expressway project of Lam Dong province. Photo: Phuc Khanh

The Tan Phu - Bao Loc project has 927 affected cases with a compensation area of more than 393ha. To date, the province has approved compensation for 590 cases, reaching more than 64%, with a total budget of about 610 billion VND.

Meanwhile, the Bao Loc - Lien Khuong project has more than 2,400 affected cases with a compensation area of about 537ha.

The locality has approved compensation plans for more than 96% of cases with a total budget of more than 2,695 billion VND; more than 1,670 households have received money and handed over land.

Mr. Nguyen Hong Hai - Vice Chairman of Lam Dong Provincial People's Committee - assessed that the simultaneous deployment of 14 construction fronts is the result of a thorough preparation process, close calculations associated with reality.

The organization of many parallel construction teams aims to maximize the time fund, flexibly according to the progress of site handover.

Trên tuyến cao tốc Bảo Lộc - Liên Khương, những vị trí bàn giao mặt bằng đang được thi công. Ảnh: Phúc Khánh
On the Bao Loc - Lien Khuong expressway, site handover locations are under construction. Photo: Phuc Khanh

At many locations along the route such as Km162, Km166, Km186+819 and sections passing through Bao Lam 2 commune, construction and leveling work has been urgently deployed from the early days.

Mr. Nguyen Quy Hoang - Project Commander of Phuong Thanh Company - said that the unit is accelerating construction at locations that meet the conditions to compensate for progress, ensuring the project is completed on schedule and with quality.

People agree to hand over land

Along with the determination of the government and investors, people in the project area have agreed to hand over the site for the long-term benefit of the locality.

Người dân địa phương phấn khởi khi
People agree to hand over the site so that the contractor can accelerate the project progress. Photo: Phuc Khanh

Mr. Bui Quang Kham - Head of Residential Group 18, Ward 1, Bao Loc - said that there are more than 100 households in the area subject to land acquisition to implement the Tan Phu - Bao Loc expressway project.

People are very agreeing and supporting the project. Most households have received compensation money and are urgently handing over the site to the construction unit," Mr. Kham said.

Mr. Do Van Tin (Bao Lam 2 commune) has 1.1ha of production land in the area to be recovered to serve the construction of the Bao Loc - Lien Khuong expressway.

Người dân xã Bảo Lâm 2 cưa vườn cà phê bàn giao mặt bằng cho dự án cao tốc. Ảnh: Chính Thành
People in Bao Lam commune 2 cut down coffee gardens to hand over land for the expressway project. Photo: Chinh Thanh

This is a large project of the State, serving the long-term development of the whole region, so when compensated reasonably, people are always ready to accompany the project to be implemented soon," Mr. Tin shared.

Mr. Luu Hong Long - Chairman of Da Huoai Commune People's Committee, the locality has handed over about 50% of the site to the construction unit. However, the biggest difficulty currently is still the application of compensation prices.

Phó Chủ tịch UBND tỉnh Lâm Đồng Nguyễn Hồng Hải kiểm tra thực tế tuyến cao tốc Tân Phú - Bảo Lộc qua xã Đạ Huoai. Ảnh: Phúc Khánh
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai inspects the Tan Phu - Bao Loc expressway through Da Huoai commune. Photo: Phuc Khanh

One project but with two different compensation prices at different times, leading to a difference of about 3 billion VND for 37 households. The locality is focusing on completing legal documents and committing to hand over the entire site before June 30," Mr. Long said.

Mr. Ho Van Muoi - Member of the Party Central Committee, Chairman of Lam Dong Provincial People's Committee - emphasized: "This is not only a key project of the province but also a national key project. Everyone must be dedicated, devoted, and implement it every day, every hour with the spirit of not being slow.

Đồng chí Hồ Văn Mười, Ủy viên Ban Chấp hành Trung ương Đảng, Phó Bí thư Tỉnh ủy, Chủ tịch UBND tỉnh Lâm Đồng thăm hỏi, động viên người dân thuộc diện giải phóng mặt bằng vùng dự án cao tốc đi qua
Chairman of Lam Dong Provincial People's Committee Ho Van Muoi visits and encourages people affected by site clearance for the expressway project in Ward 1, Bao Loc. Photo: Chinh Thanh

Chairman of Lam Dong Provincial People's Committee requested departments, branches, and localities to strengthen coordination, handle dossiers as soon as they are resolved; and at the same time thoroughly grasp the spirit of "where there is land, construct there" to ensure the progress of the entire project.

Phúc Khánh
RELATED NEWS

The shape of Ngoi Buc bridge on the Noi Bai - Lao Cai expressway expansion project

|

After many months of day and night construction, Ngoi Buc bridge - an important item of the Noi Bai - Lao Cai expressway expansion project has taken shape.

Lam Dong removes land bottlenecks on Bao Loc - Lien Khuong expressway

|

Lam Dong - After more than 5 months of construction, the Bao Loc - Lien Khuong expressway is facing site clearance problems, it is necessary to focus on removing them to ensure progress.

The shape of Huu Nghi - Chi Lang Expressway before the route is opened

|

At the Huu Nghi - Chi Lang expressway project, thousands of workers are making efforts to complete the goal of connecting the route.

Passenger car plunges into An Khe pass cliff in Gia Lai, 3 people injured and killed

|

Gia Lai - Collision between a truck and a passenger car on National Highway 19 through An Khe Pass, causing the passenger car to plunge into a ravine, 1 person died, 2 people were injured.

President Trump dislikes feedback on Iran's peace proposal

|

US President Donald Trump expressed "disapproval" of Iran's response to the peace proposal and said that it was "unacceptable".

Stock market enters a new wave of growth in Q2/2026

|

The stock market is regaining positive signals with the expectation that the VN-Index may head towards a higher zone if it exceeds 1,920 points.

VAR decision could change Arsenal's history

|

Arsenal coach Mikel Arteta praised the courage of the referees, after refusing West Ham's dramatic late equalizer.

Expecting the Digital Front to promote the effectiveness of connecting and uniting people

|

Ho Chi Minh City delegates expect the Vietnam Fatherland Front to continue to strongly innovate its activities in a modern direction, promote digital transformation, and promote the effectiveness of the Digital Front.

The shape of Ngoi Buc bridge on the Noi Bai - Lao Cai expressway expansion project

Bảo Nguyên |

After many months of day and night construction, Ngoi Buc bridge - an important item of the Noi Bai - Lao Cai expressway expansion project has taken shape.

Lam Dong removes land bottlenecks on Bao Loc - Lien Khuong expressway

Phúc Khánh |

Lam Dong - After more than 5 months of construction, the Bao Loc - Lien Khuong expressway is facing site clearance problems, it is necessary to focus on removing them to ensure progress.

The shape of Huu Nghi - Chi Lang Expressway before the route is opened

Văn Quyết |

At the Huu Nghi - Chi Lang expressway project, thousands of workers are making efforts to complete the goal of connecting the route.