Spending more than 45 billion VND to upgrade the commune-level road in Nam Dinh

Hà Vi |

Nam Dinh - Vu Ban District spent more than 45 billion VND to renovate and upgrade the Vinh Hao commune axis road with a length of 3.9km.

The project to renovate and upgrade the main road of Vinh Hao commune (Vu Ban district, Nam Dinh province) is 3.9km long; invested by the People's Committee of the district, with a total estimated cost of more than 45 billion VND.

Accordingly, the project runs through 4 villages of Vinh Hao commune including Vinh Lai, Ho Sen, Cuu Hao and Tien Hao with 208 households related to site clearance.

To speed up the project's site clearance, the Vinh Hao Commune Party Committee has issued a thematic Resolution on focusing on leading the site clearance work for the commune's axis road upgrade project. The People's Committee of the commune has coordinated with the district's site clearance council to organize a conference to deploy site clearance work, and at the same time directed the villages to focus on propaganda and mobilization, ensuring strictness, publicity, transparency, and creating consensus among the people.

In addition to the project to renovate and upgrade the main road of Vinh Hao commune; from the beginning of 2025 to now, the whole Vu Ban district has implemented site clearance for 18 projects. In addition to site clearance and started construction of infrastructure for residential areas concentrated in communes, the district site clearance council has implemented site clearance for key projects such as: the project to renovate and upgrade the 3.33km long Lien Minh commune axis road, invested by the district People's Committee, with a total estimated cost of about 30 billion VND; the project to build Kim Thai industrial cluster; Hop Hung industrial cluster...

Hà Vi
RELATED NEWS

Agree on the policy of building a VND29,000 billion road connecting Nam Dinh - Hoa Lu

|

Nam Dinh - Agree on the policy of building a landscape axis road connecting Nam Dinh with Hoa Lu (Ninh Binh province).

Panorama of the So River overpass on the 6,400 billion VND route in Nam Dinh

|

Nam Dinh - So River Overpass is one of the large bridges on the new Nam Dinh - Lac Quan - coastal road, which has now completed about 75% of the construction volume.

Inauguration of the 1,200 billion VND bridge, a new symbol of Nam Dinh

|

Nam Dinh - Thien Truong Bridge is considered a new symbol of Nam Dinh and has just been officially inaugurated, put into operation and use.

Proposal to reduce the retirement age for direct workers

|

Trade union officials proposed that the leaders of Bac Ninh province propose to the Government to reduce the retirement age for direct workers to suit the reality of life.

Thousands of people brave the rain to visit Hung Temple festival on Han Thuc Tet

|

Phu Tho - April 19 (ie March 3rd of the lunar calendar - Lunar New Year), despite the rainy weather, thousands of people and tourists pilgrained to Hung Temple.

Case of 20 people suspected of bread poisoning: Ministry of Health requests strict handling

|

20 cases hospitalized for emergency treatment with symptoms of poisoning after eating bread in Nghe An province. The Ministry of Health requests to investigate the origin of food supply.

Pickup truck stuck while trying to overtake a level crossing in Hanoi

|

Hanoi - When the barrier was lowering, the pickup truck driver still drove the vehicle in, then got stuck close to the railway tracks.

Russian air defense shoots down HIMARS missiles and 568 Ukrainian UAVs in 1 day

|

Russian air defense forces shot down a US-made HIMARS missile and 568 Ukrainian fixed-wing UAVs within 24 hours.

Agree on the policy of building a VND29,000 billion road connecting Nam Dinh - Hoa Lu

Lương Hà |

Nam Dinh - Agree on the policy of building a landscape axis road connecting Nam Dinh with Hoa Lu (Ninh Binh province).

Panorama of the So River overpass on the 6,400 billion VND route in Nam Dinh

Lương Hà |

Nam Dinh - So River Overpass is one of the large bridges on the new Nam Dinh - Lac Quan - coastal road, which has now completed about 75% of the construction volume.

Inauguration of the 1,200 billion VND bridge, a new symbol of Nam Dinh

Lương Hà |

Nam Dinh - Thien Truong Bridge is considered a new symbol of Nam Dinh and has just been officially inaugurated, put into operation and use.